Questions and Replies

Filter by year

14 March 2017 - NW168

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(a) When will the water use licences for the (i) Somkhele Mine and (ii) Anthracite Colliery, found in the iMfolozi Wilderness area, be granted, (b) what volume of water is allocated to each specified mine and (c) what is the source of the water?

Reply:

 

(a)(i) The records of My Department only indicate that we have received a Water Use License Application from Tendele Coal Mining (Pty) for Somkhele Anthracite Mine. The Water Use License was issued on 4 August 2014 for Section 21 (b), (c), (g), (i) and (j) water uses of the National Water Act, 1998 (Act No. 36 of 1998). The authorization for abstraction was issued on 10 September 2010.

(a)(ii) Anthracite Colliery has not submitted a Water Use License Application to my Department.

(b) The volume abstracted is 750 000 cubic metres of water per annum for Tendele Coal Mining (Pty) for Somkhele Anthracite Mine.

(c) Tendele Coal Mining (Pty) for Somkhele Anthracite Mine abstracts water from the UMfolozi River.

 

24 February 2017 - NW208

Profile picture: Ross, Mr DC

Ross, Mr DC to ask the Minister of Water and Sanitation

(1)(a) What are the reasons that Rand Water blocked the storm water pipes in Oak Avenue, Primrose, Germiston, when laying new pipes and (b) when will the situation be rectified; (2) (a) what procedures can residents follow to claim damages due to flooding of their properties caused by Rand Waters blocking the storm water pipes and (b) to whom can claims be submitted; (3) whether copies of all the relevant claim forms can be provided to Mr D C Ross?

Reply:

(1) Following the heavy rains during December 2016, it became evident that the storm water system in the Primrose area could not handle the quantity of storm water. An assessment was jointly initiated by both Ekurhuleni and Rand Water to identify if Rand Water had disturbed the storm water infrastructure whilst laying the new pipeline. The process is still in progress.

(2) The claims can be sent to Rand Water (contact person, Mr Bafana Gamede – (011) 682 0362 or Ekurhuleni pending the outcome of the investigation.

(3) Claim forms will be provided by the respective entity pending the outcome of the investigation.

---00O00---

24 February 2017 - NW207

Profile picture: Ross, Mr DC

Ross, Mr DC to ask the Minister of Water and Sanitation

(1)(a) When last did Rand Water upgrade its water pipes in the (i) Buurendaal, (ii) Highway Gardens, (iii) Harmelia, (iv) Tunney, (v) Elandsfontein and (vi) Klopper Park suburbs in the Ekurhuleni Metropolitan Municipality in Gauteng and (b) how old are the current water pipes in these specified suburbs; (2) (a) how many burst pipes has Rand Water experienced in the specified suburbs since 1 January 2016, (b) how many liters of water were lost and (c) what is the value of the loss of this water?

Reply:

(1) The above mentioned six suburbs situated in the Ekurhuleni Metropolitan Municipality (EMM) in Gauteng are supplied with potable water from the Rand Water’s H5 and H11 bulk water supply pipelines (details in the table below). The pipelines are supplied through gravity (not pumped) from the Rand Water’s Klipriviersberg Reservoirs situated some 20 kilometers away.

Pipeline Description

Date Laid (Year)

Age (Years)

Operating Pressure (Bar)

Estimated Flow (Mℓ/d)

750mm H5 Steel Pipeline

1955

62

11

65

1110mm H11 Steel Pipeline

1963

54

`7

150

The Ekurhuleni Metropolitan Municipality draws water from these bulk pipelines at strategic bulk supply points and water is further distributed to areas through the network of municipal distribution pipelines. The Rand Water’s H5 and H11 pipelines currently have adequate capacity to supply the water demands for the EMM suburbs. However, the following projects are already underway to augment the future anticipated water requirements:

      • Pipeline O6 augmentation Phase 1 Palmiet to Germiston – 2100mm pipeline
      • Pipeline Shamrock Road - Airfield pipeline (G37/H37) – 1200mm pipeline

The above projects are scheduled for commission before the end of 2017. These projects will add extra capacity in the bigger Germiston area. Our asset management philosophy identifies and prioritizes pipelines aged at 60 for conditional assessment. The H5 and H11 pipelines are aged between 54 and 62 years and still within their condition and operating lifecycle. H11 is marginally over 60 and is prioritised for conditional assessment.

(2) A total of four (4) leaks on H5 and five (5) leaks on H11 pipeline were experienced since the said date with the loss with a total of 275kl water loss to the value of R1 858.88.

---00O00---

24 February 2017 - NW169

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

Whether a water use licence has been applied for in respect of the proposed Fuleni Coal Mine; if not, why not; if so, what (a) would be the source of this water and (b) volume has been applied for?

Reply:

The applicant has not applied for a Water Use Licence. Water Use Licensing is a demand driven service which is initiated by the prospective applicant.

My Department does not have a Water Use Licence Application for Fuleni Coal Mine, hence it will not be able to determine the source and the volume of water required for the proposed mine.

---00O00---

24 February 2017 - NW133

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

With regard to the Amathole District Municipality project to build toilets in villages in the district, (a) when did the project begin, (b) what are the details of the progress of the project, (c) how many toilets have been built thus far and (d) what are the (i) current and (ii) projected costs of the project?

Reply:

(a) Amathole District Municipality appointed a service provider for the sanitation project on 1 September 2014.

(b) To date, of 66 700 Units, a total to some 30 409 Units are completed whilst 36 291 Units are still outstanding.

(c) Refer to (b) above.

(d)(i) The current estimated cost is R 288 064 457, 00.

(d)(ii) The projected cost to complete the project is R508m which includes payments of invoices not paid to service providers.

---00O00---

24 February 2017 - NW237

Profile picture: Jooste, Ms K

Jooste, Ms K to ask the Minister of Water and Sanitation

Is there a maintenance plan to ensure that the water pipes in the (a) Buurendaal, (b) Highway Gardens, (c) Harmelia, (d) Tunney, (e) Elandsfontein and (f) Klopper Park suburbs in the Ekurhuleni Metropolitan Municipality in Gauteng specified suburbs are regularly maintained; if not, are the specified water pipes only repaired when there is a burst water pipe; if so, how often are the water pipes maintained?

Reply:

The following information was provided to My Department by the Municipality.

Ekurhuleni Metropolitan Municipality has a system of annual maintenance plans for all pipelines. The maintenance plans are used for scheduling all required maintenance. This is backed by a monitoring system which tracks time lines for repairing and replacing of burst and leaking water pipes. Ekurhuleni Metropolitan Municipality has a turnaround time of 48 hours to fix burst water and leaking water pipes. To ensure customer satisfaction, Ekurhuleni Metropolitan Municipality uses a Customer Relationship Management System, which monitors and tracks the reported cases.

In an effort to increase water supply to its consumers, Ekurhuleni Metropolitan Municipality treats every burst and leaking water pipe in a serious light. During early 2015, Ekurhuleni Metropolitan Municipality established a Rapid Response Unit, which its sole function is to address water losses within the Municipality areas, including the suburbs of (a) Buurendaal, (b) Highway Gardens, (c) Harmelia, (d) Tunney, (e) Elandsfontein and (f) Klopper Park.

---00O00---

21 December 2016 - NW2611

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

With reference to her reply to question 2195 on 31 October 2016, (a) for how many hours has each specified water board sat (i) in the (aa) 2013-14, (bb) 2014-15 and (cc) 2015-16 financial years and (ii) since 1 April 2016 and (b) what is the total amount that each of the specified board members was paid in (i) remuneration and (ii) any other allowances in the specified periods?

Reply:

Requesting the Honourable Member to refer to the Water Boards Annual Reports of each specified financial year.

---00O00---

21 December 2016 - NW2694

Profile picture: Purdon, Mr RK

Purdon, Mr RK to ask the Minister of Water and Sanitation

(1)With reference to the critical drought that is severely affecting major parts of the Republic, (a) which of the country’s major storage dams are currently under 35% capacity in each province and (b) what measures has her department put in place to urgently conserve the water in the specified dams; (2) whether each municipality affected by the dams is implementing stringent measures to conserve water; if not, (a) why not and (b) what steps will she take in this regard; if so, (i) did the specified municipalities receive direction from the Government and (ii) what are the further relevant details in this regard?

Reply:

(1)(a) Refer to Annexure A for the list of the country's major dams that are below 35%.

(1)(b) My Department develops annual operating rules which include drought restrictions rules. These are communicated to stakeholders at the System Operations Forums. In addition Joint Operations Committees are established to monitor progress on the implementation of water restrictions and advice provided on further interventions where necessary e.g installation of flow restrictors at household level or supply through water tankers, drilling of boreholes etc. Further details are given in the table and section 2 of the response below.

(2)(a) Yes. Most of the municipalities are implementing measures to conserve water and there is already a reduction in demand. The measures include:

  • Restrictors on the bulk meters and the reticulation meters, some municipalities are also restricting consumer meters;
  • Pressure Management;
  • Education and awareness;
  • Water rationing;
  • Monitoring Minimum Night Flows;
  • Active and passive leakage control, etc.

(2)(b) As mentioned in (a) above, most of the municipalities are already implementing Water Conservation and Water Demand Management measures, for those that are not yet implementing. It is mainly due to lack of human and financial capacity. The Department will continue engaging municipalities through the established structures and the municipalities must actively participate and report in this meetings and prioritize resources and budgets to implement Water Conservation and Water Demand Management.

---00O00---

Annexure A

Table1: Country’s Major Storage Dams below 35%

Provinces: Free State, KwaZulu-Natal, Mpumalanga, Limpopo, Eastern Cape, North West & Northern Cape

Reservoir

Name

Full Supply Capacity in 106 m3

%

Municipality supplied

Measures

Implementation

Free State

Bloemhof

1 240

20.4

Lekwa-Teemane Municipality Bloemhof, Kuruman,

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 12/08/16

(No 40203)

  • Restrictions for Domestic @15%andIrrigation @ 20% are being implemented
  • Early Warning systems established to monitor achievement of restrictions
  • Joint Operations Committee (JOC) formed to give direction to municipality on implementing the restrictions
  • Last SOF held on 1 December 2016

Kalkfontein

325

3.7

Kopanong Municipality

(Koffiefontein, Jacobsdal, Jagersfontein and Fauresmith)

Drought Operating Rule determined and communicated at the SOF

Restrictions gazetted on 19/02/16 (No 39718)

  • Restrictions for Domestic @ 40%&Irrigation @100% are being implemented
  • Early Warning systems established to monitor achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last Forum held on 29 November 2016

Allemanskraal

174

14.0

Masilonyana and Tswelopele Municipality (Brandfort, Bultfontein, Theunissen and Virginia)

Drought Operating Rule determined and communicated at the SOF

Restrictions gazetted on 12/08/16

(No 40203)

  • Restrictions for Domestic: 40%Irrigation 92% are being implemented
  • Early Warning systems established to monitor achievement of restrictions.
  • JOC formed to give direction to municipality on implementing the restrictions. -Last Forum held on 1 December 2016

Rustfontein

71

25.5

Mangaung Metropolitan

Drought Operating Rule determined and communicated at the SOF Part of Bloemfontein System.

Restrictions gazetted on 12/02/16

No 39679.

  • Restrictions for Domestic: 30%Irrigation: 75% are being implemented
  • Early Warning systems established to monitor achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions.
  • Last SOF held on 29 November 2016

Krugersdrift

71

26.0

Ikgomotseng and Soutpan

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 19/02/16: No 39718

  • Restrictions forDomestic: 20%Irrigation: 50% are being implemented
  • Early Warning systems established to monitor achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last SOF held on 29 November 2016

KwaZulu Natal

Goedertrouw

301

19.5

Umhlathuze, Umlalazi, Uthungulu

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 24/03/16, No 39860:

  • Restrictions for Domestic: 40%Irrigation: 80% Industrial: 15%are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last SOFs held on 12 July 2016

Albert Falls

288

27.3

Umgugundlovu, Ethekwini Metropolitan

Drought Operating Rule determined and communicated at the SOF. Part of the Umgeni system

Restrictions published on 24/03/16

(No 39860)

  • Part of the Umgeni Water Supply System which is currently at 47,6% and -Restrictions for Domestic: 15% Irrigation: 50%Industrial: 15%are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last SOF was held on 17 June 2016 as part of Mgeni SOF.

Mpumalanga

Kwena

158

23.9

Ehlanzeni

Drought Operating Rule determined and communicated at the SOF. Part of the Crocodile System.

Restriction notices issued by Inkomati/Usuthu Catchment Management Agency.

(Compliance not known yet)

  • Restrictions for Domestic, irrigation are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last Committee held on 2 November 2016 as part of the CROCOC

Driekoppies

250

20.5

Nkomazi

Drought Operating Rule determined and communicated at the Komati Joint Operations Forum. Part of the Komati Basin Water Authority (KOBWA)

Restriction notices were issued.

(Compliance not yet known)

  • Early Warning systems established to measure achievement of restrictions
  • JOC established to give direction to municipalities on implementing the restrictions
  • Last Forum held on 17 November 2016 as part of KOBWA

Limpopo

Middel-Letaba

171

16.3

Mopani Municipality

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 16/09/16

(No 1066)

  • Restrictions for Domestic 20%Irrigation 80% are being implemented
  • Early Warning systems established to measure achievement of restrictions.
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last Forum held on 29 April 2016 as part of the Shingwedzi CMF

Tzaneen

156

13.2

Mopani Municipality

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 16/09/16

(No 1066)

  • Restrictions for Domestic @ 20%& Irrigation @ 70% are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions.
  • Last Forum held on 25 October 2016

Nzhelele

51

8.6

Thulamela

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 16/09/16

(No. 1066)

  • Restrictions for Irrigation: 40% are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last Forum held on 21 April 2016

Flag Boshielo

185

17.7

Polokwane Metro

Part of the Polokwane System. Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 16/09/16,

( No 40284)

  • Restrictions for Domestic: 30%Mining: 55% are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC to be established to give direction to municipality on implementing the restrictions
  • Last Forum held on 25 May 2016

Rhenosterkop

204

16.3

Nkangala DM

Drought Operating Rule determined and communicated at the SOF. Restrictions gazetted on 16/09/16

(No. 1066)

  • Restrictions for Irrigation: 60%-70%(Depending on rainfall) are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last Forum held on 20th April 2016

Eastern Cape

Darlington

180

18.2

Nelson Mandela Metro

Drought Operating Rule determined and communicated at the SOF.

Receiving water from the Orange River System:

Restrictions published on 26/08/16 (No.40229)

The Dam is operated below 45% for Dam safety reasons

  • Restrictions of 15% on all transfers form the Orange River System are being implemented
  • Early Warning systems established to measure achievement of restrictions and communication is on-going to align information
  • Last Forum held on 20 September 2016

North West

Molatedi

200

25.2

Moses kotane

Drought Operating Rule determined and communicated at the SOF.

Restrictions gazetted on 14/10/16

(No. 40346)

  • Restrictions on Domestic @50%& Irrigation @75% are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • JOC formed to give direction to municipality on implementing the restrictions
  • Last Forum held on 16 August 2016 as part of the Marico CMF

Northern Cape

Reservoir

Name

Full Supply Capacity in 106 m3

%

Municipality supplied

Measures

Implementation

Spitskop

57

9.2

Mmamusa Municipality SchweizerReneke

Drought Operating Rule determined and communicated at the SOF.

30% restrictions on irrigation recommended. Achievement not yet visible

  • Restrictions on irrigation are being implemented
  • Early Warning systems established to measure achievement of restrictions
  • Last Forum held on 07 September 2016

13 December 2016 - NW2656

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

(a) What is the working status of the pumps delivering water from the Heyshope Dam in the Usutu catchment to the Vaal River upstream of Grootdraai Dam, (b) what was the capacity transferred in each month in the (i) 2015 and (ii) 2016 calendar years, (c) how many of the pumps worked during the specified period and (d) what amount was spent on the pumps during the period?

Reply:

(a) At Heyshope pump-station there are 4 pump-sets of which 2 pump-sets are currently functional and in operation. At Geelhoutboom pump-station there are also 4 pump-sets of which 2 are in operation. These two pump-stations are operating in series together with long sections of gravitational transfers.

At Heyshope refurbishment of the booster motor at pump-set 1 is underway and procurement for the mechanical motor and control valve refurbishment is in progress. At Geelhoutboom line 1 the motor refurbishment is being completed and it is anticipated that it will be back in operation by January 2017. The other pump-set is awaiting the replacement of bearings which is in progress and should be back in operation by December 2016.

(b)(i) The volume of water transferred in 2015 was 27, 9 million cubic meters

(b)(ii) The volume of water transferred in 2016 is 43, 7 million cubic meters.

(c) In 2015 Heyshope had 3 out of 4 pump-sets in operation and 2 out of 4 in 2016. At Geelhoutboom 1 out of 4 was operational in 2015 and this improved to 2 out of 4 in 2016.

(d) Since the rectification work is not completed as yet, a final figure is not available as yet. However to date R97.7million was spent at these two pump-stations.

---00O00---

13 December 2016 - NW2562

Profile picture: Alberts, Mr ADW

Alberts, Mr ADW to ask the Minister of Water and Sanitation

(1)Whether she is aware of the findings of the report concerning the performance and expense review of the country’s water provisions cycle undertaken by the National Treasury (details furnished); if not, why not; if so, (2) Whether the findings of the report have led to any new programmes or measures by her department; if not, why not; if so, what are the relevant details; (3) Whether, in accordance with the review, she has reached the conclusion that approximately 60% of municipal water infrastructure needs to be renewed; if not, why not; if so, (a) what the estimated cost will be to renovate the infrastructure and (b) over what period of time the infrastructure will have to be replaced or renovated; (4) Whether any steps (a) have been taken or (b) will be taken in this regard to obtain the required funds for the renovation of the infrastructure; if not, why not; if so, what are the relevant details?

Reply:

(1) Yes, I am aware of the findings that are presented in the National Treasury Expenditure and Performance Review (EPR). Please note that the key purpose of the review is to understand the financial implications of water services delivery, not to reflect specifically on sector performance and propose solutions. The Review has also developed an expenditure performance Costing Model that will facilitate regular discussions with National Treasury on the relationship between government expenditure and performance. The model measures (and predicts) performance against current (and future) levels of financial expenditure. The Review confirms what my Department already knows with regards to the current constraints to performance within the water (services) value chain. In fact, my Department provided the consultant with this insight during the initial data and information collection phase, prior to the publication of the Review, but was never given the opportunity to comment on any of the draft versions. The Final Review has not been circulated within my Department for comment.

(2) The findings contained in the Review have not led to any new programme or measures being implemented. My Department, as sector leader and as part of its mandated responsibility, continues to monitor sector performance and intervenes when appropriate, and has recently developed a Regulatory No Drop System in support of Water Conservation and Demand Management, and is finalising a comprehensive and detailed Water Sector Investment Framework, which forms part of an overarching National Water and Sanitation Master Plan.

My Department is also implementing Municipal Water Master Plans within 27 Priority District Municipalities in support of the Water Services Development Planning process, which will ultimately emanate in a pipeline of projects, to address the water services delivery problems that might exist.

(3) Yes, I am aware of the current state of infrastructure in the water sector, and specifically the state of asset management, and associated problems with infrastructure operation and management within municipalities. My Department is busy finalising a detailed municipal investment requirements analysis, which is part of the sector Investment Framework, to confirm the actual extent of the problem, financially, within municipalities. The Investment Framework will be completed in 2017, and my Department will, in due course, make recommendations over what period of time the infrastructure should be replaced, refurbished or extended, while taking into account the current economic environment in the country. The 59% quoted in the Review is based on a preliminary Departmental estimate of infrastructure renewal. Other studies have also based renewal on accumulated depreciation which is only a financial provision for the renewal of infrastructure. This implies that there is shortfall in funding.

(4) Due to this identified shortfall, my Department has engaged with National Treasury and COGTA to establish a new refurbishment fund. The required funds to support the investment requirements have not yet been secured from National Treasury. This will only happen once the Investment Framework has been finalised and the findings and recommendations have been presented and discussed internally within my Department, and once other lead sector departments, who are involved with municipal water services delivery, have had the opportunity to make their inputs. The funding is critical to ensure that the pipeline of projects emanating from the Water Services Master Plans are implemented.

---00O00---

13 December 2016 - NW2655

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

(1)Whether her department is experiencing any challenges with the transfer of water from the Tugela River to the Vaal River via the Drakensberg scheme; if so, what are the relevant details in this regard; (2) are the pumps on the transfer route working at full capacity; if not, (a) why not, (b) how long has each of the specified pumps not been working at full capacity, (c) what are the consequences and (d) how much will it cost to repair each of the specified pumps; (3) (a) what is the capacity of each of the pumps and (b) how many litres of water were transferred via the specified route from the Sterkfontein Dam to the Vaal Dam in each month of the (i) 2015 and (ii) 2016 calendar years to date?

Reply:

(1) My Department released the total volume of water from Sterkfontein dam to the Vaal dam as per the operating rule developed by the National Water Resource Planning unit. The initial release in the 2015/2016 hydrological year of 320.48 million cubic meters was completed between October 2015 and January 2016. The second release is underway peaking at 70 cubic meters per second to ensure the planned volume of 203 million cubic meters to be transferred by end December 2016. To date the release is occurring according to plan.

(2)(a) The transfer of water from the Woodstock to Sterkfontein dam occurred 80% according to plan. This was due to mechanical and electrical failures experienced at some of the pump-sets at Drieland Kilburn pump stations. These two pump-stations are working in series to lift water at a maximum flow-rate of 20m3/s (should there be adequate run-off in the river leading into the Woodstock dam).

(2)(b) At Driel pump-station, there are two sections of which section 1 has 2 out of 3 pump-sets functional and at section 2, there are 4 out of 5 pump-sets available. The mechanical fault at Driel 1 was attended to by a previously appointed contractor but failed after commissioning. This particular pump-set has been problematic for more than a year, but contractual matters are being attended to. The electrical motor at Driel 2 is out of service for the past 3 weeks and repair is imminent as procurement is being finalized.

At Kilburn section 1, 4 out of 4 pump-sets are in operation. At Kilburn section 2, we have 3 out of 4 pump-sets in operation. The motor of one pump-set is in for repairs at a contractor after it became dysfunctional in March 2016. The lengthy repairing period was caused due to a contractual dispute with the contractor which has been resolved and it is expected to have this pump back in operation shortly.

(2)(c) If the equipment is not available, the filling of Sterkfontein Dam will be delayed.

(2)(d) The cost for the repair work is R5m for Driel and R1.5m for Kilburn.

(3)(a) At Driel section 1 there are 3 pumps with a transfer capacity of 1m3/s each. At Driel section 2 there are 3 pumps with a transfer capacity of 2.6m3/s each and 2 pumps with a capacity of 4m3/s each. At Kilburn section 1 there are 4 pump-sets of 3.3m3/s each and at section 2 there are 4 pump-sets of 4m3/s each.

(3)(b)(i) The first transfer took place in 2015 from October to January 2016 for which the total of 320.48 million cubic meters was transferred.

(3)(b)(ii) To date about 85 million cubic meters was transferred since 7 November 2016 of the planned 203 million cubic meters.

---00O00---

13 December 2016 - NW2579

Profile picture: Khawula, Ms MS

Khawula, Ms MS to ask the Minister of Water and Sanitation

When will the residents of Wards 20 and 22 in the Kgetlengrivier Local Municipality in the North West get clean water?

Reply:

The residents of Wards 20 and 22 in the Kgetlengrivier Local Municipality in North West will get clean water once the funds for the pipeline are confirmed.

---00O00---

05 December 2016 - NW2193

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)What (a) is the current status of the Ermelo Waste Water Treatment Plant in Mpumalanga and (b) are the results of the water quality tests of the treated effluent in each month since 1 January 2016; (2) whether the specified plant complies with the standards for effluent discharge as regulated by her department; if not, what action has she taken to rectify the situation; if so, what are the relevant details?

Reply:

(1)(a) The Ermelo Wastewater Treatment Plant is currently receiving 12-16 Ml/day and is designed to handle 10 Ml/day. Overall, the infrastructure of the plant is in a bad condition and this has compromised the sewage treatment process to the extent that substandard effluent is being discharged.

(b) The Green Drop System, which the Department utilizes to monitor compliance levels of wastewater treatment works in the country, shows that the level of compliance for the plant from 01 January 2016 to September 2016 is zero for micro, physical and chemical parameters specific for wastewater effluent.

(2) The effluent from the plant does not comply with the general standard. The Department had meetings with the municipality, inspections were conducted and correspondence was also sent to the municipality. Due to the lack of response from the municipality, a task team (comprising DWS, the Departments of Human Settlements, Cooperative Governance and Traditional Affairs, Economic Development, Environment and Tourism as well as the District and Local Municipalities) was then established to address the concerns related to the plant. See Tables 1 and 2 below:

Table 1: Correspondence with the Municipality prior to establishment of the task team

DWS Action

Issues raised

Type of communication

Municipality response

Issued communication due to poor water quality discharging into the stream

  • sewage pollution
  • water use authorisation application

Letter dated 23 November 2009

None

Site inspection conducted on 14 July 2010

  • sewage pollution

Section 19 letter dated 19 July 2010

None

Site inspection conducted on 11 Nov 2011

  • sewage pollution at Pet Dam

Meeting held with the

municipality immediately after the inspection

The problem was resolved same day

Site inspection conducted on 14 June 2012

  • sewage spillages and poor effluent quality
  • reporting of pollution incidents
  • incomplete discharge charges forms
  • water use authorisation application
  • Poor attendance of stakeholder forum meetings

Meeting with municipality on 06 August 2012

Raised their challenges

Table 2: Correspondences with the Municipality after establishment of the task team

DWS Action

Issues raised

Type of communication

Municipality response

Issued communication based on the meeting held on 06 August 2012

  • sewage pollution
  • establishment of the Task Team

Letter dated 14 August 2012

None

Follow up

  • reminder to respond

Letter dated 11 October 2012

Submitted insufficient action plan on 14 November 2012

Task Team

Actions from minutes

Meeting on 26 September 2012 at Govan Mbeki Municipality

No feedback, the Municipality sent another person without information

Task Team

Actions from minutes

Meeting on 14 November 2012 at Lekwa Municipality

Attended

Task Team

Actions from minutes

Meeting on 06 February 2013 at Dr Pixley ka Seme Municipality

Did not attend

Issued a communication

  • Non-attendance of Task Team meeting

Letter dated 22 February 2013

None

Task Team

Actions from minutes

Meeting on 12 June 2013 at Gert Sibande District Municipality

Did not attend

Issued a communication

  • Action plan

Letter dated 22 August 2013

None

Assessment of WWTW on 29 October 2013 and 13 March 2014

  • Non-compliance letter

Letter dated 24 March 2014

None

The Department allocated R 44 275 029 million to refurbish the Ermelo Waste Water Treatment Plant in Mpumalanga. The project commenced in November 2015 and is scheduled for completion in January 2017.

---00O00---

01 December 2016 - NW2364

Profile picture: Steyn, Ms A

Steyn, Ms A to ask the Minister of Water and Sanitation

With reference to her reply to question 1023 on 5 July 2016, (a) how many boreholes did her department (i) drill, (ii) repair and/or (iii) upgrade since 1 October 2015, (b) what is the exact GPS location of each of the specified boreholes, (c) what were the costs of (i) drilling per meter and/or (ii) refurbishment in each case and (d) was water found at each of the boreholes?

Reply:

(a) A total of 626 boreholes were drilled and a total of 519 Repaired/Upgraded/Refurbished (refer to table 1 below for details).

(b) Refer to Annexure A for the GPS location of each specified borehole.

(c)(i) The cost were from R 250 - R 1 455 depending on geological formation and other variables.

(c)(ii) The cost of refurbishment in each case was R 53, 6 million.

(d) No, water was found in all the boreholes excerpt for a few cases in KwaZulu-Natal (KZN).

Table 1. List of boreholes per province including costs:

Province

  1. Number of Boreholes

Costs (Rands)

(d)

Water Found

 

(i) Drilled

(ii)Repaired

(i) Per m drilled

(ii) Refurbished

 

Eastern Cape

14

11

 

R 20,4 M

Yes

Western Cape

-

-

-

-

-

Northern Cape

23

47

R750-R 1455

R 21,7M

Yes

North West

322

105

R320

 

Yes

Gauteng

-

-

-

-

-

Limpopo

-

-

-

-

-

Mpumalanga

8

40

R 900

R 4,0M

Yes

KZN

188

281

R 250 –R350

R 7,5M

Yes

Freestate

71

35

R 711

 

Yes

TOTALS:

626

513

 

R 53,6 M

 

---00O00---

01 December 2016 - NW2574

Profile picture: Mbatha, Mr MS

Mbatha, Mr MS to ask the Minister of Water and Sanitation

(a) How many applications for water license’s has her department declined during the period 1 January to 31 December 2015 and (b) what was the reason for the refusal to issue a water license in each case?

Reply:

(a) A total of 69 Water Use License Applications were declined in the period 1 January to 31 December 2015.

(b) Refer to the table below for the various reasons applications were refused.

---00O00---

Number

Province

Type of water use(s) - indicate S25(2) & Volumes where applicable

Sector (e.g. Agric, mining, industrial, Forestry, Municipality/Govt Dept)

Signed Date

Reason for Decline

   

Water use(s) e.g. S21(a) - Groundwater/ surface water

     

1

Eastern Cape

21(a)

Agriculture

2015-03-01

Catchment fully allocated.

2

KwaZulu-Natal

21(e)©(i)

Industry

2015-04-08

Outstanding information

3

Limpopo

21(a)

Agriculture

2015-03-28

Catchment fully allocated.

4

Mpumalanga

21(a) and (b)

Agriculture

2015-04-30

Outstanding information

5

Free State

21 (a)

Agriculture

2015-04-30

Catchment fully allocated.

6

North West

21 (a,b, c, f, g &i)

Industry

2015-04-30

Outstanding information

7

Free State

21(a)

Agriculture

2015-04-30

Catchment fully allocated.

8

Free State

21(a)

Agriculture

2015-07-17

Catchment fully allocated.

9

Limpopo

21 (a)

Agriculture

2015-07-17

Catchment fully allocated.

10

Limpopo

21 a & g

Development

2015-07-17

Outstanding information

11

Mpumalanga

21 (a)

Agriculture

2015-08-30

Catchment fully allocated.

12

Limpopo

21 (a,c &i)

Industry

2015-08-31

Outstanding information

13

Mpumalanga

21 (b)

Agriculture

2015-09-01

Outstanding information

14

Limpopo

21 (a)

Agriculture

2015-09-02

Catchment fully allocated.

15

Free State

21 (a)

Agriculture

2015-10-04

Catchment fully allocated.

16

Northern Cape

21 (a)

Agriculture

2015-10-04

Catchment fully allocated.

17

Free State

21 (a)

Agriculture

2015-10-04

Catchment fully allocated

18

Eastern Cape

21 (d)

SFRA

2015-11-19

Proposed plantation will have negative impact on the existing water uses and Reserve

19

Eastern Cape

21 (d)

SFRA

2015-11-19

Catchment fully allocated

20

Northern Cape

21 (a)

Agriculture

2015-11-19

Catchment fully allocated.

21

Free State

21 (a)

Agriculture

2015-11-19

Catchment fully allocated

22

Free State

21 (a)

Agriculture

2015-11-19

Catchment fully allocated

23

Free State

21 (a,b,c&i)

Agriculture

2015-11-19

Catchment fully allocated

24

Northern Cape

21 (a)

Agriculture

2015-11-19

Catchment fully allocated

25

Limpopo

21 (a)

Agriculture

2015-11-19

Catchment fully allocated

26

Limpopo

21 (a&b)

Agriculture

2015-11-19

Catchment fully allocated

27

Limpopo

21 (a)

Agriculture

2015-11-19

Catchment fully allocated

28

North West

21 (a)

Development

2015-10-20

Geohydrological report outstanding. Section 21 (g) water use information and design drawing, capacity and final effluent from waste water facility are outstanding.

29

Limpopo

22 (a)

Agriculture

2015-10-04

Outstanding information

30

Free State

23 (a)

Agriculture

2015-06-12

Catchment fully allocated

31

Free State

24 (a)

Agriculture

2015-06-12

Catchment fully allocated

32

Western Cape

21 (c,i)

local government

2015-12-18

Outstanding information

33

Northern Cape

21 (a)

Agriculture

2015-10-04

Catchment fully allocated.

34

Limpopo

21 (a&b)

Agriculture

2015-10-21

Outstanding information

35

Limpopo

21 (a)

Agriculture

2015-12-18

Catchment fully allocated

36

Mpumalanga

21 (a,b,c,g&i)

mining

2015-12-18

Outstanding information

37

Limpopo

21 (a)

Agriculture

2015-12-18

Catchment fully allocated

38

Western Cape

21 (a&b)

local government

2015-12-18

The proposed storm water Detention Dam is for reducing the risk of frequently flooding of the village

39

Limpopo

21 (a)

Agriculture

2015-12-18

Catchment fully allocated.

40

Limpopo

21 (a)

Agriculture

2015-12-18

Catchment fully allocated.

41

Limpopo

21 (a)

Agriculture

2015-12-18

Catchment fully allocated

42

Limpopo

21 (a)

Industry

2015-12-24

Catchment fully allocated.

43

Limpopo

21 (a)

Agriculture

2015-12-18

Catchment fully allocated.

44

Western Cape

21 (a)

Agriculture

2015-12-19

Catchment fully allocated.

45

Free State

21 (a)

Agriculture

2015-07-30

Catchment fully allocated.

46

Free State

21 (a)

Agriculture

2015-08-25

Catchment fully allocated.

47

Free State

21 (a)

Agriculture

2015-08-25

Catchment fully allocated.

48

Free State

21 (a)

Agriculture

2015-08-25

Catchment fully allocated.

49

Limpopo

21 (a, g &j)

Mining

2015-08-07

Outstanding information

50

Northern Cape

21 (a)

Agriculture

2015-08-14

Catchment fully allocated.

51

Northern Cape

21 (a)

Mining

2015-08-27

Outstanding information

52

Northern Cape

21 (a)

Development

2015-08-14

Catchment fully allocated.

53

Northern Cape

21 (a)

Agriculture

2015-08-27

Catchment fully allocated.

54

Northern Cape

21 (a)

Agriculture

2015-07-17

Catchment fully allocated.

55

Northern Cape

21 (a)

Agriculture

2015-08-14

Catchment fully allocated.

56

Free State

21 (a)

Agriculture

2015-06-15

Catchment fully allocated.

57

Northern Cape

21 (a)

Agriculture

2015-05-28

Catchment fully allocated.

58

Northern Cape

21 (a)

Mining

2015-05-28

Outstanding information

59

Northern Cape

21 (a)

Local government

2015-06-02

Outstanding information

60

Northern Cape

21 (a)

Agriculture

2015-05-04

Catchment fully allocated.

61

Free State

21 (a)

Agriculture

2015-12-10

Catchment fully allocated.

62

Free State

21 (a)

Agriculture

2015-12-14

Catchment fully allocated.

63

Free State

21 (a)

Agriculture

2015-02-03

Outstanding information

64

Northern Cape

21 (a)

Agriculture

2015-04-24

Catchment fully allocated.

65

Northern Cape

21 (a)

Agriculture

2015-03-03

Catchment fully allocated.

66

Northern Cape

21 (a, g &j)

Mining

2015-11-27

Outstanding information

67

Northern Cape

21 (a,c&i)

Mining

2015-11-28

Outstanding information

68

Northern Cape

21 (a)

Agriculture

2015-11-29

Outstanding information

69

Northern Cape

21 (a,c,I,f&g)

Mining

2015-11-30

Outstanding information

28 November 2016 - NW2193

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)What (a) is the current status of the Ermelo Waste Water Treatment Plant in Mpumalanga and (b) are the results of the water quality tests of the treated effluent in each month since 1 January 2016; (2) whether the specified plant complies with the standards for effluent discharge as regulated by her department; if not, what action has she taken to rectify the situation; if so, what are the relevant details?

Reply:

(1)(a) The Ermelo Wastewater Treatment Plant is currently receiving 12-16 Ml/day and is designed to handle 10 Ml/day. Overall, the infrastructure of the plant is in a bad condition and this has compromised the sewage treatment process to the extent that substandard effluent is being discharged.

(b) The Green Drop System, which the Department utilizes to monitor compliance levels of wastewater treatment works in the country, shows that the level of compliance for the plant from 01 January 2016 to September 2016 is zero for micro, physical and chemical parameters specific for wastewater effluent.

(2) The effluent from the plant does not comply with the general standard. The Department had meetings with the municipality, inspections were conducted and correspondence was also sent to the municipality. Due to the lack of response from the municipality, a task team (comprising DWS, the Departments of Human Settlements, Cooperative Governance and Traditional Affairs, Economic Development, Environment and Tourism as well as the District and Local Municipalities) was then established to address the concerns related to the plant. See Tables 1 and 2 below:

Table 1: Correspondence with the Municipality prior to establishment of the task team

DWS Action

Issues raised

Type of communication

Municipality response

Issued communication due to poor water quality discharging into the stream

  • sewage pollution
  • water use authorisation application

Letter dated 23 November 2009

None

Site inspection conducted on 14 July 2010

  • sewage pollution

Section 19 letter dated 19 July 2010

None

Site inspection conducted on 11 Nov 2011

  • sewage pollution at Pet Dam

Meeting held with the

municipality immediately after the inspection

The problem was resolved same day

Site inspection conducted on 14 June 2012

  • sewage spillages and poor effluent quality
  • reporting of pollution incidents
  • incomplete discharge charges forms
  • water use authorisation application
  • Poor attendance of stakeholder forum meetings

Meeting with municipality on 06 August 2012

Raised their challenges

Table 2: Correspondences with the Municipality after establishment of the task team

DWS Action

Issues raised

Type of communication

Municipality response

Issued communication based on the meeting held on 06 August 2012

  • sewage pollution
  • establishment of the Task Team

Letter dated 14 August 2012

None

Follow up

  • reminder to respond

Letter dated 11 October 2012

Submitted insufficient action plan on 14 November 2012

Task Team

Actions from minutes

Meeting on 26 September 2012 at Govan Mbeki Municipality

No feedback, the Municipality sent another person without information

Task Team

Actions from minutes

Meeting on 14 November 2012 at Lekwa Municipality

Attended

Task Team

Actions from minutes

Meeting on 06 February 2013 at Dr Pixley ka Seme Municipality

Did not attend

Issued a communication

  • Non-attendance of Task Team meeting

Letter dated 22 February 2013

None

Task Team

Actions from minutes

Meeting on 12 June 2013 at Gert Sibande District Municipality

Did not attend

Issued a communication

  • Action plan

Letter dated 22 August 2013

None

Assessment of WWTW on 29 October 2013 and 13 March 2014

  • Non-compliance letter

Letter dated 24 March 2014

None

The Department allocated R 44 275 029 million to refurbish the Ermelo Waste Water Treatment Plant in Mpumalanga. The project commenced in November 2015 and is scheduled for completion in January 2017.

---00O00---

25 November 2016 - NW2113

Profile picture: Matsepe, Mr CD

Matsepe, Mr CD to ask the Minister of Water and Sanitation

What amount did (a) her department and (b) each entity reporting to her spend on advertising on the (i) Africa News Network 7 channel, (ii) SA Broadcasting Corporation (aa) television channels and (bb) radio stations, (iii) national commercial radio stations and (iv) community (aa) television and (bb) radio stations (aaa) in the 2015-16 financial year and (bbb) since 1 April 2016?

Reply:

(a) My Department has spent R37 800 269.05 in 2015/2016 and R6 840 941.20 since 1 April 2016 to date on advertising. Below is the breakdown as per request

(i) African News Network 7 channel

Item

2015/2016

1 April to date

(aa) television channels

R0.00

R0.00

(bb) radio stations

R450 000.00

R0.00

(ii) SA Broadcasting Corporation

Item

2015/2016

1 April to date

(aa) television channels

R22 528 202

R2 508 000

(bb) radio stations

R14 727 256.68

R2 499 712.20

(iii) National commercial radio stations

Item

2015/2016

1 April to date

(aa) television

R0.00

R0.00

(bb) radio station

R0.00

R1833 229

(iv) Community

Item

2015/2016

1 April to date

(aa) television

R0.00

R0.00

(bb) radio station

R94 810.37

R0.00

(b) Refer to Annexure A.

Annexure A

Below is the breakdown for entities as per request:

(b) Entities

(i)

(ii)

(aa)

(bb)

(iii)

(iv)

(aa)

(bb)

(aaa)

(bbb)

Amatola Water

None

None

None

None

None

None

None

None

None

None

Bloem Water

None

None

None

None

None

None

None

None

None

None

Lepelle N Water

None

SABC Limpopo Combo

Thobela FM; Phalaphala FM and Munghanalonene

R160 717,21

Capricorn FM

R68 400,00

None

R68 400,00

None

R68 400,00

Magalies Water

None

R53 530.00

None

R53 530.00

None

R9 700.00

None

R9 700.00

R63 230 00

None

Mhlathuze Water

None

None

None

None

None

None

None

None

None

None

Overberg Water

None

None

None

None

None

None

None

None

None

None

Rand Water

None

R 5 221 600 SABC Total

R 4 818 400 SABC TV

R 403 200 SABC Radio

R 586 515 Commercial Radio

R 161 758 Community Total

None

R 161 758 Community Radio

R 5 785 613 for 2015-16

R 184 260 since Apr 2016

Sedibeng Water

None

None

None

None

None

None

None

 

1 July 2016 – 30 March 2016: R523 387.80

1 April 2016 – 31 August 2016:R218 078.30

Umgeni Water

None

None

None

None

None

R135 000 (Community radio stations in July 2016)

None

None

None

R135 000 (Community radio stations in July 2016)

---00O00---

25 November 2016 - NW2193

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)What (a) is the current status of the Ermelo Waste Water Treatment Plant in Mpumalanga and (b) are the results of the water quality tests of the treated effluent in each month since 1 January 2016; (2) whether the specified plant complies with the standards for effluent discharge as regulated by her department; if not, what action has she taken to rectify the situation; if so, what are the relevant details?

Reply:

(1)(a) The Ermelo Wastewater Treatment Plant is currently receiving 12-16 Ml/day and is designed to handle 10 Ml/day. Overall, the infrastructure of the plant is in a bad condition and this has compromised the sewage treatment process to the extent that substandard effluent is being discharged.

(b) The Green Drop System, which the Department utilizes to monitor compliance levels of wastewater treatment works in the country, shows that the level of compliance for the plant from 01 January 2016 to September 2016 is zero for micro, physical and chemical parameters specific for wastewater effluent.

(2) The effluent from the plant does not comply with the general standard. The Department had meetings with the municipality, inspections were conducted and correspondence was also sent to the municipality. Due to the lack of response from the municipality, a task team (comprising DWS, the Departments of Human Settlements, Cooperative Governance and Traditional Affairs, Economic Development, Environment and Tourism as well as the District and Local Municipalities) was then established to address the concerns related to the plant. See Tables 1 and 2 below:

Table 1: Correspondence with the Municipality prior to establishment of the task team

DWS Action

Issues raised

Type of communication

Municipality response

Issued communication due to poor water quality discharging into the stream

  • sewage pollution
  • water use authorisation application

Letter dated 23 November 2009

None

Site inspection conducted on 14 July 2010

  • sewage pollution

Section 19 letter dated 19 July 2010

None

Site inspection conducted on 11 Nov 2011

  • sewage pollution at Pet Dam

Meeting held with the

municipality immediately after the inspection

The problem was resolved same day

Site inspection conducted on 14 June 2012

  • sewage spillages and poor effluent quality
  • reporting of pollution incidents
  • incomplete discharge charges forms
  • water use authorisation application
  • Poor attendance of stakeholder forum meetings

Meeting with municipality on 06 August 2012

Raised their challenges

Table 2: Correspondences with the Municipality after establishment of the task team

DWS Action

Issues raised

Type of communication

Municipality response

Issued communication based on the meeting held on 06 August 2012

  • sewage pollution
  • establishment of the Task Team

Letter dated 14 August 2012

None

Follow up

  • reminder to respond

Letter dated 11 October 2012

Submitted insufficient action plan on 14 November 2012

Task Team

Actions from minutes

Meeting on 26 September 2012 at Govan Mbeki Municipality

No feedback, the Municipality sent another person without information

Task Team

Actions from minutes

Meeting on 14 November 2012 at Lekwa Municipality

Attended

Task Team

Actions from minutes

Meeting on 06 February 2013 at Dr Pixley ka Seme Municipality

Did not attend

Issued a communication

  • Non-attendance of Task Team meeting

Letter dated 22 February 2013

None

Task Team

Actions from minutes

Meeting on 12 June 2013 at Gert Sibande District Municipality

Did not attend

Issued a communication

  • Action plan

Letter dated 22 August 2013

None

Assessment of WWTW on 29 October 2013 and 13 March 2014

  • Non-compliance letter

Letter dated 24 March 2014

None

The Department allocated R 44 275 029 million to refurbish the Ermelo Waste Water Treatment Plant in Mpumalanga. The project commenced in November 2015 and is scheduled for completion in January 2017.

---00O00---

22 November 2016 - NW2260

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)By what date will she give notice in the Government Gazette of the establishment of the newly amalgamated Mhlathuze and Umgeni Water Board, in terms of section 28(1) of the Water Services Act, Act 108 of 1997, as amended; (2) whether she will require that a selection panel be formed in terms of section 3(1) of schedule 1 of the specified Act; if not, why not; if so, by what date will the specified panel be established; (3) by what date will (a) the specified water board be fully operational and (b) a permanent (i) board and (ii) chairperson be appointed?

Reply:

(1) It is anticipated that the establishment of the single KwaZulu-Natal Water Board will be gazetted during the 2017/18 financial year. The establishment will be dependent on the outcome of the due diligence exercise.

(2) Yes, a selection panel will be constituted to recommend the appointment of Board Members for the single KwaZulu-Natal Water Board. The selection panel will be appointed during the 2017/18 financial year.

(3)(a) During the course of the 2017/18 financial year.

(3)(b)(i)During the course of the 2017/18 financial year.

(3)(b)(ii)During the course of the 2017/18 financial year.

---00O00---

22 November 2016 - NW2259

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

With reference to her reply to question 1961 on 7 October 2016, (a) on what statutory grounds was the specified interim transitional committee established, (b) for how long were the members of the specified council appointed, including the (i) Chairperson and (ii) Deputy Chairperson and (c) by what date does she expect to dissolve the specified council?

Reply:

(a) It is the Minister’s prerogative to appoint the Independent Transitional Committee. The Independent Transitional Committee will provide guidance and oversight during the establishment of the single KwaZulu-Natal Water Board.

(b) The members of the Independent Transitional Committee are appointed until such a time the single KwaZulu-Natal Water Board is established.

(c) The members of the Independent Transition Committee term of appointment will end when the single KwaZulu-Natal Water Board is established.

---00O00---

15 November 2016 - NW2318

Profile picture: Robinson, Ms D

Robinson, Ms D to ask the Minister of Water and Sanitation

Whether any (a) internal and/or (b) external forensic reports pertaining to (i) her department and/or (ii) each entity reporting to her were completed from 1 January 2009 up to the latest specified date for which information is available; if not, in each case, why not; if so, what is the (aa) name, (bb) subject matter and (cc) date of conclusion of each of the specified forensic reports?

Reply:

Refer to Annexure A for the internal and/or external forensic report pertaining to my Department and each entity.

---00O00---

Annexure A

Entity

(a)(ii)

(b) (ii)

(aa)

(bb)

(cc)

Department:

Yes

245 internal reports

Yes

28 external reports

Refer to Appendix A & B

Refer to Appendix A & B

Refer to Appendix A & B

Amatola Water

None

None

None

None

None

Bloem Water

None

None

None

None

None

Lepelle Northern Water

None

None

None

None

None

Magalies Water

None

None

None

None

None

Mhlathuze Water

1 internal forensic report

1 external forensic report

  • Dukuduku Report (internal forensic report)
  • ENS Report(external forensic report)
  • Allegations of Financial Misconduct relating to the Dukuduku project (internal)
  • Forensic Investigation Relating to allegations of misconduct by the Chief Executive Officer(external)
  • 2014 (internal)
  • November 2015(external)

Overberg Water

Forensic Investigation into alleged irregularities relating to non-compliance with corporate governance norms and standards and other related irregularities

None

GFIA report

Forensic Investigations

19 July 2016

Rand Water

Rand Water completed all material internal forensic investigations reports from 1 January 2009 up to the latest date for which information is available and reported in the integrated annual reports for the same period and duly submitted to the Department of Water and Sanitation.

Rand Water completed all material external forensic investigation reports from 1 January 2009 up to the latest date for which information is available and reported in the integrated annual reports for the same period and duly submitted to the Department of Water and Sanitation.

Internal and External Forensic Investigation reports

Forensic Investigations

June 2009;

June 2010;

June 2011;

June 2012;

June 2013;

June 2014;

June 2015; and

June 2016

Sedibeng Water

None

None

None

None

None

Umgeni Water

None

None

None

None

None.

WRC

None

The WRC had one forensic audit completed from 2009 until now. The information is available

Forensic Investigations: Bony Isaacs Productions

An investigation into the relationship between a service provider and employee which concluded in a disciplinary hearing.

15/07/2010

TCTA

See Appendix C

See Appendix C

See Appendix C

See Appendix C

See Annexure C

Appendix B

External Forensic Reports

No

Name

(aa)

Case reference number

Subject matter

(bb)

Date of Conclusion (cc)

1

GFIA report

99 20090519 101924

Alleged reckless driving

01 July 2011

2

GFIA report

9920091207030721

Procurement irregularities

01 July 2011

3

GFIA report

9920100409113046

Alleged Procurement Irregularities

01 July 2011

4

GFIA report

9920100512023430

Alleged Unethical Behaviour

01 July 2011

5

GFIA report

9920100616060609

Alleged abuse of Government Owned Vehicle

01 July 2011

6

GFIA report

3/6/3/2/1/0910/1

Fraudulent Actions Licences

01 July 2011

7

GFIA report

3/6/3/2/1/0910/2

Labour Relations Concerns

01 July 2011

8

GFIA report

3/6/3/2/1/0910/4

Altering of water course

01 July 2011

9

GFIA report

3/6/3/2/1/0910/19

Procurement Irregularities

01 July 2011

10

GFIA report

3/6/3/2/1/1011/1

Corruption Allegations

01 July 2011

11

GFIA report

3/6/3/2/1/1011/2

Theft of Government Goods

01 July 2011

12

GFIA report

99 20090420022811

Alleged corruption at Head Office

01 July 2011

13

GFIA report

99 20090824095823

Alleged nepotism at Vaal Dam

01 July 2011

14

GFIA report

99 20090304091333

Alleged theft of water at Clan William

01 July 2011

15

GFIA report

9 920 091 207 030 720

Investigation into the alleged procurement irregularities

01 July 2011

16

GFIA report

3/6/3/2/1(1/2009)

Fraudulent Actions Licences at Gauteng Region

01 July 2011

17

GFIA report

99 20090504021341

Investigation into the alleged corruption at Nelspruit

01 July 2011

18

GFIA report

99 20091124085637

Alleged corruption at Nelspruit

01 July 2011

19

GFIA report

3/6/3/2/1/1011/5

Concerns regarding the Harties Metsi A me Program

01 July 2011

20

GFIA report

99 20091014014052

Investigation into the alleged unethical behaviour at Hartbeespoort Dam

01 July 2011

21

GFIA report

99 20080331102532

Theft of Government property

01 July 2011

22

GFIA report

9920091020083109

Investigation into the alleged procurement Irregularities at Gauteng Region

01 July 2011

23

GFIA report

99 20090324094011

Alleged procurement irregularities at Head Office

01 July 2011

24

GFIA report

3/6/3/2/1/1112/21

Investigation into the alleged abuse of vehicles

01 July 2014

25

GFIA report

3/6/3/2/1/1011/9

Alleged Corruption and pipe failures Nandoni and Inyaka Dam In-house

22 Nov 2010

26

PWC report

3/6/3/2/1/1415/12

Investigation to determine the extent of fraudulent activities within Financial Management

15 Dec 2014

27

PWC report

3/6/3/2/1/1516/13

Investigation into the management of construction equipment

11 May 2016

28

Mazar Forensic Report

3/6/3/2/1/1516/18

Investigation into the alleged fraudulent activities and theft of mobile device

30 May 2016

Appendix C

TCTA Internal Investigations:

Financial Year

Subject Matter of Forensic Report

Date of Conclusion

2008/2009

  1. CEO’s Salary (Ms Mthembu) –;
  1. Cell phone Allowance –;
  1. Mr. Tutu Maluleke’s Incident and Ms Halima Nazeer’s incident – ;
  1. COO’s travel costs for study purposes – ;
  1. Transgression of FICA requirements – ;
  1. CFO’s invitation to Spa –.

14 May 2009

2009/2010

  1. Chief Treasury Dealer has been appointed without the correct qualifications for the job
  1. Non-compliance with company procedures by head of communications

03 July 2009

03 May 2010

2010/2011

1. The purchase of 300 Bafana Bafana soccer jerseys.

2. Allegation regarding the COO rarely being in office and incurring large unjustifiable cost to TCTA.

28 June 2010

17 June 2010

2012/2013

1.Investigation into allegations of irregularities raised against a senior staff member (PwC)

2.Procurement Review (Independent Consultant)

06 June 2012

4 December 2012

2013/2014

  1. Suspected Sick Leave Abuse
  1. Procurement of Site Vehicles Investigation
  1. Irregularities involving TCTA cell phone contracts (PwC)

13 May 2013

30 May 2013

14 May 2013

2014/2015

1. Unaccounted Tender Fees

2. Asset Verification (SnG)

3. Investigation into SED Projects for the Financial Year (PwC)

1 June 2014

30 June 2014

29 August 2014

2016/2017

1. Alleged Irregular executive appointments

2. Alleged Theft of Company Assets (SnG)

31 August 2016

27 July 2016

15 November 2016 - NW2228

Profile picture: Schmidt, Adv H

Schmidt, Adv H to ask the Minister of Water and Sanitation

(1)Whether, with reference to her reply to question 1716 on 27 September 2016, the funding allocated for the Sedibeng Regional Sewerage Scheme was spent in each financial year for which it was allocated; if not, in each case, why not; if so, in each case, what are the relevant details; (2) whether any of the funds allocated for the specified scheme were underspent in each financial year for which the funding was allocated; if not, in each case, what is the position in this regard; if so, in each case, what are the relevant details?

Reply:

 

1.The funding allocated for the Sedibeng Regional Sewerage Scheme was spent in each financial year as per allocation. The funding allocations and total expenditure from 2008/09 financial year to date are stipulated in Tables 1.1 and 1.2 below.

2. There had not been any under spending in each financial year mentioned above and the budget allocation for each project was based on cash flow.

---00O00---

TABLE 1.1: Funding allocations for Sedibeng Regional Sewerage Scheme project

PROJECT NAME

2008/09

R

2009/10

R

2010/11

R

2011/12

R

2012/13

R

2013/14

R

2014/15

R

2015/16

R

2016/17

R

TOTAL

R

Sedibeng Scheme

3 780 818

20 153 503

18 800 000

31 542 099

5 939 776

31 969 522

93 679 032

141 217 387

274 057 560

621 139 697

TABLE 1.2: Expenditure to date for Sedibeng Regional Sewerage Scheme project

PROJECT NAME

2008/09

R

2009/10

R

2010/11

R

2011/12

R

2012/13

R

2013/14

R

2014/15

R

2015/16

R

2016/17

R

TOTAL

R

Sedibeng Scheme

3 780 818

20 153 503

18 800 000

31 542 099

5 939 776

31 969 522

93 679 032

141 217 387

166 370 793

513 452 930

 

31 October 2016 - NW2194

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(a) When will the upgrades of the water treatment works at the (i) Amsterdam and (ii) Sheepmoor Bulk Water Schemes in Mpumalanga commence and (b) what are the (i) budgeted costs and (ii) timeframes in each case?

Reply:

(a) The upgrade of the water treatment works at the Amsterdam and Sheepmoor Bulk Water Schemes in Mpumalanga is anticipated for construction to commence during 2017/18 financial year. The design and implementation readiness study is currently being conducted in 2016/17 financial year.

It should be noted that the Amsterdam and Sheepmoor Bulk Water Shemes are one project.

(b)(i) The budgeted cost for the project is R31 million.

(b)(ii) The duration of the project is for four years, which is 2016/17 to 2019/20 financial years.

---00O00---

31 October 2016 - NW1912

Profile picture: Robertson, Mr K

Robertson, Mr K to ask the Minister of Water and Sanitation

With reference to her letter of 27 August 2016, addressed to Mr KP Robertson, (a) which (i) waste water treatment plants and (ii) sewerage pipelines are due to be (aa) upgraded and/or (bb) refurbished in the Chief Albert Luthuli Local Municipality in Mpumalanga, (b) by when are the specified improvements due to begin and (c) what portion of the R25 million allocated by her department through the Municipal Infrastructure Grant will be used in each case?

Reply:

Refer to the table below:

(a)(i) Name of Waste Water treatment plant

(a)(ii) (aa) Sewerage pipelines upgrade

(a)(ii) (bb) Sewerage pipelines refurbished

(b) Due date for specified improvements to begin

(c) Allocation through MIG

Emanzana phase II Waste Water Treatment Works (WWTW)

None

None

Technical report not yet approved

Allocated with R5 million

Selobella Extension 2&3 toilet top structure

None

None

Commenced on 01/07/2015

Top structure allocated with R6 million

Carolina Phase I WWTW

None

None

Will commence on 01/10/2016

Top structure allocated with R6 million

Ekulindeni WWTW

None

None

Technical report not yet approved

Allocated with R1 million

Elukwatini WWTW

None

None

Commenced on 01/07/2016

Allocated with R7 million

---00O00---

31 October 2016 - NW2155

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

With reference to 16 completed contracts regarding the progress of Phase II of the Lesotho Highlands Water Scheme, what is, in each case, the (a) nature of the work completed, (b) particulars of the parties to the contract, (c) date the contract was entered into, (d) date the work was completed and (e) total amount (i) paid and/or (ii) still payable in terms of the contract

Reply:

Refer to Annexure A regarding progress of the 16 completed contracts of Phase II of the Lesotho Highlands Water Scheme.

Annexure A

 

Contract #

Description

Company

Date of Award

Date

completed

Contract price (Rand)

Cost

at completion (Rand)

Water Transfer Awarded Contracts : Completed

 

 

 

 

2222A-C

Interim PMU-

JB Barry and Partners (Ireland)

12-Aug-11

Jan-14

19 459 612

19 459 612

             

2222D

Interim PMU-

Dr S Turner - Individual Service Contract

12-Aug-11

Jan-14

4 295 015

4 295 015

4002

Construction of Access Road to Polihali Weir

MOPS Civil Contractors Pty Ltd (- Lesotho company)

Nov-11

31-Mar-12

4 136 254

4 136 254

4001

Construction of Polihali Downstream Weir

LSP Construction (Lesotho company)

14-May-12

17-Oct-13

21 714 123

21 686 529

4014

Tlokoeng Housing Renovations

LSP Construction

Jan-14

Mar-14

1 171 385

1 171 385

3000

Design and Supervision of PolihaliWeir

AECOM and sub consultants

07-Dec-10

Oct-13

2 492 652

2 493 236

3003

LidarSurvey1

CK Aerial Surveys

12-Jun-12

31-Mar-13

1 771 250

1 771 250

3011

LidarSurvey2

CK Aerial Surveys

12-Jun-12

30-Sep-13

514 298

514 298

3017

Demarcation of Reservoir Boundary

Maleka, Ntsihlehle, Putsoa ( MNP)

May-14

30-Nov-15

7 950 100

8 215 930

6001

Baseline Study-Water Quality and IFR

Institute of Natural Resources

14-Jan-13

31-Aug-14

9 206 025

9 225 230

6002

Baseline Study - Biological, Archeological & Heritage

Coastal and Environmental Services (CES)

27-Nov-12

31-Mar-14

2 599 230

2 599 230

6008

Baseline Study - Public Health

NonyanaHoohlo and Associates

Dec-13

09-Jul-15

6 740 575

6 045 475

6000

Baseline Study - Socio-Economic

Coastal and Environmental Services (CES)

27-Nov-12

Oct-14

4 817 998

6 167 998

6000

Baseline Study-Socio-Economic

LHDA Inhouse

Inhouse

Dec-14

1 480

1 480

6031

Re-configuration of socio-economic database

GK Consulting

Jan-16

Feb-16

91 256

91 256

9006

Financing Strategy Consultant

Delloitte&Touche

Sep-14

Mar-15

1 335 907

1 335 907

 

TOTAL

 

 

88 297 160

89 210 085

31 October 2016 - NW2156

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

With reference to the five contracts regarding the progress of Phase II of the Lesotho Highlands Water Scheme that were awarded, what is, in each case, the (a) nature of the work completed, (b) particulars of the parties to the contract, (c) expected date of completion and (d) projected total value of the contract?

Reply:

Refer to Annexure A regarding the progress of the five contracts of Phase II of the Lesotho Highlands Water Scheme.

ANNEXURE A

Contract #

Description

Company

Date of completion

Tender price (Rand)

Cost to date (Rand)

           

Water Transfer Contracts being implemented 

2223

Project Management Unit

CDM Smith and Partners

Dec-2025

349 889 571

131 625 324

3009

Professional Services for the Urban Planning, D&S Project Housing & Associated Infrastructure

Polihali Infrastructure Consultants

Apr-2021

79 365 621

14 019 480

3014

D&S Polihali North Eastern Access Road

SMEC FMA Joint Venture

Sep-2016

28 453 705

4 936 235

3015

Professional services for the Evaluation, Optimisation, and Site Supervision of Geotechnical investigations

Jeffares and Green Joint Venture

Sep-2017

19 750 472

7 026 482

6013

RAP PNEAR and site establishment area(in house)

Inhouse by LHDA

Jun-2017

1 500 000

-

4016

Geotechnical investigations-Polihali Tunnel-drilling contractor

Diabor Pty Ltd

Aug-2017

49 238 075

12 515 273

     

Totals

528 197 444

170 122 794

D&S = Design and Construction supervision

RAP = Resettlement Action Plan

PNEAR = North East Access Road

D&S = Design and Construction supervision

ESIA = Environmental Social Impact Assessment

RAP = Resettlement Action Plan

31 October 2016 - NW2157

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

With reference to the eight contracts related to the progress of Phase II of the Lesotho Highlands Water Scheme that are in the process of procurement, what is, in each case, the (a) nature of the work that tenders are sought for, (b) status of the procurement processes, (c) expected date of awarding the contract and (d) projected total value of the contract?

Reply:

Refer to Annexure A regarding the progress of the eight contracts of Phase II of the Lesotho Highlands Water Scheme.

ANNEXURE A

Contract #

Description

Status

Date of award

Budget Estimate

Award price

           
           

Water Transfer Contracts being negotiated/ recently awarded

 

 

 

 

3004

D&S Western Access Road as Main Access Road to Polihali

Letter of Award issued

10-Oct-16

75 000 000

66 702 034

3008

D&S Telecommunications & Power Supply

Contract awarded

23-Sep-16

40 000 000

37 390 414

3022

D&S of Polihali Dam Diversion Tunnel

Letter of Award issued

05-Sep-16

85 000 000

82 460 556

6004

ESIA Western Access Corridor

Letter of Award issued

08-Sep-16

5 000 000

4 979 752

6014

ESIA Project Housing and Polihali Dam and Reservoir Site Establishment

Contract awarded

01-Sep-16

10 000 000

8 973 543

6006

RAP - Western Access Road & transmission line

Under negotiations

Expect early Nov 16

30 000 000

Under negotiations

6010

SHEQ Framework

Letter of Award issued

09-Sep-16

1 000 000

660 100

6015

RAP - Project Housing, main reservoir, major bridges & road realignments

Letter of Award issued

23-Aug-16

90 000 000

85 477 163

     

Total

336 000 000

286 643 562

D&S = Design and Construction supervision

ESIA = Environmental Social Impact Assessment

RAP = Resettlement Action Plan

SHEQ = Safety Health Environment and Quality

31 October 2016 - NW2195

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(a) What are the names of each board member of each of the country’s water boards that report to her, (b) when was each of the specified board members first appointed to sit in the respective boards, (c) what is the total number of consecutive terms that each of the board members has served, (d) what is the total number of consecutive years that each of the board members served on each respective board and (e) when does the current term of each of the board members on their respective boards end?

Reply:

Refer to Annexure A for information regarding board members of each water boards in the country.

---00O00---

Annexure A

Entity

(a) Names of Board Members

(b) When was the first appointment

(c)Total number of consecutive terms

(d) Total number of consecutive years

(e) When does the current term ends

Amatola Water

Nokulunga Mnqeta

1st February 2016

0

0

30th January 2020

 

Sizwe Hadebe

1st February 2016

0

0

30th January 2020

 

Lynette Louw

1st February 2006

2 Term

10 Years

30th January 2020

 

Brian Hollingworth

1st February 2016

0

0

30th January 2020

 

Mphoko Nzimande

1st February 2016

0

0

30th January 2020

 

Abraham le Roux

1st February 2016

0

0

30th January 2020

 

Eugene Jooste

1st February 2016

0

0

30thJanuary 2020

 

Tebogo Maenetja

1st February 2016

0

0

30thJanuary 2020

Bloem Water

Phitsane, TB

28/04/2009

2 Term

7 Years

31/03/2018

 

Matete, P

01/04/2014

1 Term

2 Years

31/03/2018

 

Van der Merwe, J

28/04/2009

2 Term

7 Years

31/03/2018

 

Maboe, MSS

28/04/2009

2 Term

7 Years

31/03/2018

 

Mokhesi, N

01/02/2005

3 Term

11 Years

31/03/2018

 

Bomela, LR

01/04/2014

1 Term

2 Years

31/03/2018

 

Phetwe, CM

01/04/2014

1 Term

2 Years

31/03/2018

 

Ellman, MJ

01/04/2014

1 Term

2 Years

31/03/2018

 

Mkiva, Z

01/04/2014

1 Term

2 Years

31/03/2018

Lepelle Northern Water

Mr. MPK Tshivhase

01 April 2016

1 Term

6 months

31/03/2020

 

Mr. MI Phasha

01 April 2016

1 Term

6 months

31/03/2020

 

Mr. NH Matsepe

01 April 2010

2 Term

6 months

31/03/2020

 

Ms. LLC Malamba

01 April 2010

2 Term

6 months

31/03/2020

 

Ms. MM Ntsaba

01 April 2016

1 Term

6 months

21/03/2020

 

Ms. JM Letsoalo

01 April 2010

2 Term

6 months

31/03/2020

 

Mr. BP Sebola

01 April 2010

2 Term

6 months

31/03/2020

 

Ms. TTC Hlongwa

01 April 2016

1 Term

6 months

31/03/2020

 

Ms. MA Mphahlele

01 April 2016

1 Term

6 months

31/03/2020

Magalies Water

Adv. MM Petlane

01/05/14

1st Term

2 Years

30/04/18

 

Ms. PN Nkwinika

01/07/09

2nd Term

6 Years

30/04/18

 

Mr. DR Sibanda

01/07/09

2nd Term

6 Years

30/04/18

 

Ms. MA Hlahla

01/07/09

2nd Term

6 Years

30/04/18

 

Mr. TT Mohapi

01/03/12

2nd Term

4 Years

30/04/18

 

Ms. TF Zondi

01/07/09

2nd Term

6 Years

30/04/18

 

Ms. N Mufamadi

01/05/14

1st Term

2 Years

30/04/18

 

Ms. TD Monewe

01/03/12

2nd Term

4 Years

30/04/18

 

Mr. FP Vilakazi

01/05/14

1st Term

2 Years

30/04/18

 

Ms. F Saloojee

01/05/14

1st Term

2 Years

30/04/18

 

Ms. S Lebeko-Ratlhagane

01/06/14

1st Term

2 Years

30/04/18

 

Kgosi SV Suping

01/06/14

1st Term

2 Years

30/04/18

Mhlathuze Water

Dudu Myeni (Chairperson)

01 February 2002

3rd Term

14 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Bonginkosi Mshengu

01 October 2014

1st Term

2 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Poppy Dlamini

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Musa Xulu

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Frederick Bosman

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Nonhlanhla Khumalo

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Amita Badul

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Nica Gevers

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Brian Rawlins

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

 

Simosenkosi Chamane

01 March 2011

1st Term

5 Years

28 February 2015 - Minister extended the term until a new board is in place.

Overberg Water

Mr Mpumelelo Ncwadi

1 September 2009

2

7 Years

30 April 2018

 

Mr Noel Bastiaan

4 April 2014

First Term

2 Years

30 April 2018

 

Ms Melinda Zass

4 April 2014

First Term

2 Years

30 April 2018

 

Ms Kim Montgomery

4 April 2014

First Term

2 Years

30 April 2018

 

Ms Nirvani Dhevcharran

4 April 2014

First Term

2 Years

30 April 2018

 

Advocate Derick Block

4 April 2014

First Term

2 Years

30 April 2018

 

Mr Adriaan Smuts

4 April 2014

First Term

2 Years

30 April 2018

Rand Water

Adv Faith Matshidiso Hashatse (Chairperson)

01 April 2009

2nd Term

7 years and 5 months

31 March 2018

 

Ms Sophie Molokoane-Machika (Deputy Chairperson)

12 June 2012

2nd Term

4 years and 3 months

31 March 2018

 

Ms Busiswa Cwengile Bam

01 April 2014

1st Term

2 years and 5 months

31 March 2018

 

Mr Dawood Coovadia

01 April 2005

3rd Term

11 years and 5 months

31 March 2018

 

MsLakela Kaunda

01 April 2014

1st Term

2 years and 5 months

31 March 2018

 

Mr Lefadi Makibinyane

01 April 2009

2nd Term

7 years and 5 months

31 March 2018

 

Ms Nomsa Georgina Mbileni

01 April 2014

1st Term

2 years and 5 months

31 March 2018

 

Mr Isaac Mmushi

01 April 2014

1st Term

2 years and 5 months

31 March 2018

 

Prof Frederick Otieno

01 April 2005

3rd Term

11 years and 5 months

31 March 2018

 

Mr Ramateu Monyokolo

17 February 2016

1st Term

8 months

31 March 2018

 

Ms Rene Aloise Kenosi

17 February 2016

1st Term

8 months

31 March 2018

Sedibeng Water

Mr MD Dikoko

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Ms MJ Ramataboe

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Mr EA Gaborone

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Ms GG Ramakarane

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Mr CD Mboweni

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Mr MM Mthombeni

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Dr PE Molokwane

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Adv SST Kholong

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

 

Ms KG Sereko

01-May-13

1 Term

3 Years, 4 months

30-Apr-17

Umgeni Water

Mr Andile Mahlalutye (Chairman)

01-Jul-09

1st Term

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Prof Imtiaz Vally

01-Jul-09

1st Term

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Ms Ziphozethu Mathenjwa

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Mr Teboho Nkhahle

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Ms Nombuso Afolayan

01-Jul-04

2nd Term

13 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Mr Graham Atkinson

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Mr Vasu Gounden

01-Jul-03

3rd Term

14 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Dr Takalani Dube

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Ms Thokozile Shezi

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Ms Nompumelelo Chamane

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Mr Visvin Reddy

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

Mr Thabani Zulu

01-Jul-09

1stTerm

7 Years

2013-06-30. Minister extended the term until a new board is in place.

 

31 October 2016 - NW2196

Profile picture: Macpherson, Mr DW

Macpherson, Mr DW to ask the Minister of Water and Sanitation

(a) How many directives did her department issue to municipalities for the discharge of ineffectively treated effluent (i) in the past five financial years and (ii) during the period 1 April 2016 up to the latest specified date for which information is available, (b) what were the (i) names and (ii) locations of each of the specified municipalities, (c) on what date was each of the specified directives issued and (d) what are the relevant details of all follow-up action taken by her department in each case?

Reply:

(a)(i) The number of directives issued to municipalities for the discharge of ineffectively treated effluent is a total of seventy (70) directives were issued to municipalities across the country to date. A Fifty six (56) of these were issued in the past five years.

TABLE 1 Breakdown per province for the past five (5) years:

Location

Non-compliance Letters

Pre-directives

Directives

Eastern Cape

02

18

01

Free State

18

07

10

Gauteng

10

07

13

KwaZulu-Natal

0

04

02

Limpopo

0

17

14

Mpumalanga

16

05

06

North West

01

14

08

Northern Cape

01

08

01

Western Cape

0

0

01

 Total

48

80

56

(a)(ii) The number of directives issued to municipalities for the discharge of ineffectively treated effluent since April 2016 is a total of fourteen (14) directives were issued.

TABLE 2 Breakdown per province since April 2016:

Location

Directives

Eastern Cape

01

Free State

0

Gauteng

5

KwaZulu-Natal

2

Limpopo

01

Mpumalanga

01

North West

02

Northern Cape

02

Western Cape

0

Total 

14

(b)(c) and (d) Refer to Annexure A for the names and location and dates of each specified municipalities.

---00O00---

Annexure A

Number of Non-compliance letters, Pre-directives and Directives Issued to Municipalities from April 2011 to March 2016

Non-compliance Letters

Notices/Pre-directives

(a) Directives and (c) date issued

(b)(i) Municipality name

(b)(ii) Location

(d) Follow up action taken

None

2016/01/30

2016/02/10

Metsimaholo Local Municipality 

Gauteng

This municipality is receiving support from the Department.

None

None

06/04/2016

Emfuleni Local Municipality-Pump station 10

Gauteng

This municipality is receiving support from the Department.

None

None

12/01/2016

Emfuleni Local Municipality-Pump station 2,3,10

Gauteng

This municipality is receiving support from the Department

None

None

06/04/2016

Emfuleni Local Municipality-Pump station 5

Gauteng

This municipality is receiving support from the Department

None

06/05/2014

Emfuleni LM Evaton gardens pump overflow

Gauteng

This municipality is receiving support from the Department

None

08/09/2014

22/08/2014

Emfuleni LM Kwamasiza Hostel

Gauteng

This municipality is receiving support from the Department

None

None

22/08/2014

Emfuleni LM Evaton Mahole

Gauteng

This municipality is receiving support from the Department

None

None

24/02/2011

Lesedi LM Balfour Sewage Works

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

30/09/2016

Ekuhuruleni Metro

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

08/04/2016

Mogale city LM: Manhole spillage

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

03/02/2014

Ekuhuruleni MetroMarlands, Germiston Sewer overflow

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

23/10/2014

Ekuhuruleni MetroMarlands, Germiston Sewer overflow

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

23/10/2015

Ekuhuruleni MetroMarlands, Sewer Affecting Scaw Operations

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

15/04/2015

02/06/2015

Lekwa Local Municipality:

TLC Pump Station Discharging Raw Sewage

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

24/07/2015

10/02/2016

Metsimaholo Local Municipality :

A Burst Sewage Pipe  

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

15/10/2014

Metsimaholo Local Municipality :Pump Station Not Working  

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

31/07/2014

Metsimaholo Local Municipality :Manhole Overflow  

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

02/11/2015

Phumelela Local Municipality :Manholes Were Blocked

Gauteng

This municipality is receiving support from the Department.

None

None

25/04/2016

Dipaleseng Local Municipality :Sewage Plant Was Overflowing

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2010/07/10

30/5/2011

21/12/2012

Govan Mbeki Local Municipality (Bethal WWTWs)

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

24/03/2014

None

None

Msukaligwa Local Municipality (Ermelo WWTWs)

Mpumalanga

This municipality is receiving support from the Department.

None

14/12/2015

None

Lekwa Local Municipality (Morgenson Oxidation ponds)

Mpumalanga

This municipality is receiving support from the Department.

30/11/2015

None

None

Ngwathe Local Municipality Parys

Gauteng

This municipality is receiving support from the Department.

13/12/2012

23/10/2014

None

Ngwathe Local Municipality Vredefort

Gauteng

This municipality is receiving support from the Department

23/02/2015

None

02/03/2015

Merafong Local Municipality: Kokosi WWTWS

Gauteng

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2016/09/07

2009/09/03

Lephalale Paarl, Zongesien, Marapong 

Limpopo

Action plan received and assessed on 16/09/2016. DWS to continue with monitoring for compliance.

None

2014/07/17

2015/09/21

 Mookgopong Local Municipality

Limpopo

The Department continues to engage with no- compliant municipalities that have been issued with notices and directives.

None

None

22/05/ 2013

Capricorn district municipality

Limpopo

This municipality is receiving support from the Department

None

None

19 /07 2013

Mopani district municipality

Limpopo

This municipality is receiving support from the Department

None

None

22 /04/2014

Modimolle Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

08 /08/ 2014

Polokwane Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

20/08/ 2014

Polokwane Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

21 /08/ 2014

Greater Letaba Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

21 /08/2014

Modimolle Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

02 /09/ 2014

Mopani Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

20/10/ 2014

Vhembe district Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

26/03/ 2015

Mopani District Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

26/03/2015

Mopani District Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

24 /06/ 2015

Mogalakwena Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

24/06/ 2016

Vhembe District Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

30 /09/ 2013

None

Vhembe district municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

19 /12/ 2013

None

Vhembe district municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

03 /05/ 2014

None

Musina Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

07 /03/ 2014

None

Vhembe District Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

15 /07/ 2014

None

Mookgophong Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

15 /07/ 2014

None

Mookgophong Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

22 /07/ 2014

None

Tzaneen Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

22 /07/ 2014

None

Modjadjiskloof Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

02 /09/ 2014

None

Tzaneen local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

02 /09/ 2014

None

Mopani district Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

06 /08/ 2015

None

Mogalakwena Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

04 /09/ 2015

None

Vhembe District Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

04 /09/ 2015

None

Vhembe District Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

28 /09/2015

None

Mookgophong Local Municipality

Limpopo

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

24 /09/ 2016

None

Lephalale Municipality

Limpopo

This municipality is receiving support from the Department

None

2013/07/23

2014/05/09

Govan Mbeki Local Municipality

Mpumalanga

This municipality is receiving support from the Department.

23/01/2014

23/01/2014

None

Thaba Chweu LM WWTW

Mpumalanga

This municipality is receiving support from the Department

10/03/2014

None

None

Victor Khanye LM WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

26/07/2013

None

09/05/2014, 2016/04/21

Govan Mbeki LM WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

6/11/2012, 16/08/2013

None

29/08/2013

Thaba Chweu LM WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

07/09/2012, 03/09/2013, 07/10/2016

None

28/08/2013

eMalahleni LM WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

26/07/2013

2016/04/21

None

Govan Mbeki LM WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

30/08/2013

None

None

Nkomazi LM WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

3/12/2012, 30/08/2013

None

None

Sekhukhune LM

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

07/10/2016

None

None

Dipaliseng WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

27/03/2013

None

None

Elias Motswaledi LM

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

27/02/2013

None

None

Chief Albert Luthuli LM

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

27/02/2013

None

None

Msukaligwa LM

Mpumalanga

This municipality is receiving support from the Department directives.

None

2015/08/03

None

Matibidi District Hospital WWTW

Mpumalanga

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2010/11/08

2010/12/03

2011/04/21

Moqhaka LM

Free State

Case resolved in 2013

None

None

2011/09/06

Moqhaka LM-non functiong pump station in Kroonstad

Free State

Case resolved in 2011

2012/06/25

2013/08/22

2013/09/20

Moqhaka Local Municipality

Free State

This municipality is receiving support from the Department

2011/05/23

2011/07/08

2012/06/12

Mantsopa Local Municipality-Thaba Patchoa

Free State

This municipality is receiving support from the Department.

2011/07/04

22/11/2011

26/3/2012

Umsobomvu LM - Colesberg WWTW

Free State

Plant upgraded - last inspection in May 2016

2012/06/01

2012/08/08

None

Umsobomvu LM - overflowing pump station in Norvalspont

Free State

Case resolved

2011/09/05

26/03/2012

None

Umsobomvu LM - Noupoort WWTWs

Free State

Plant upgraded –and last inspection in May 2016

None

19/04/2011

17/06/2011

Matjhabeng LM - Hennenman and Phomolong LM WWTW

Free State

Case resolved 2013

None

2012/08/11

2013/04/02

Masilonyana LM - Non functioning Theunissen WWTW

Free State

On inspection it was established that the problem had recurred. A revised action plan submitted in September 2016

None

24/04/2013

None

Masilonyana LM - non functioning Veilingskraal pum station

Free State

Case resolved

None

2013/07/02

None

Setsoto LM- sewage overflow in Van Soelen street

Free State

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2013/02/18

2014/06/25

2014/10/01

Rhenosterberg LM (Phillipstown pump station)

Free State

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/08/07

2015/11/19

None

Moqhaka LM Viljoenskroon pump stations

Free State

This municipality is receiving support from the Department.

2014/10/21

2015/11/19

None

Moqhaka LM overflowing manhole at shell depot

Free State

2011/05/23

2011/07/08

2012/06/12

Mantsopa Local Municipality-Thaba Patchoa

Free State

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2012/06/25

2013/08/22

2013/09/20

Moqhaka Local Municipality

Free State

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/01/08

2011/02/22

None

Letsemeng LM - Koffiefontein

Free State

Case resolved

2011/07/18

2011/09/19

None

Setsoto Local Municipality- Marquard Moemang Old

Free State

Upgrading completed early 2016,

Not resolved

None

None

17/08/2011

uMkhanyakude District Municipality (DM)

Kwa Zulu Natal

Monitoring inspections, ACIP funding allocated to the DM in 2012/13

None

None

03/10/2012

Ugu District Municipality

Kwa Zulu Natal

Monitoring inspections.

None

None

27/07/2016

eThekwini Municipality

Kwa Zulu Natal

Site inspections to monitor implementation of remedial actions.

None

None

21/09/2016

UThukela District Municipality

Kwa Zulu Natal

Representation received and assessed on 14/10/2016. Monitoring of Plan of Action.

2015/06/10

None

2014/07/17

Makana Local Municipality - Belmont WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/11/26

None

19/07/2016

Nelson Mandela Metropolitan Mun.

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

CHDM (Tarkastad Waste Disposal Site)

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

Amathole District Municipality - Peddie WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2014/08/13

None

None

Chris Hani DM - Sterkstroom WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2014/08/27

None

None

Amathole District Municipality-Fort Beaufort WWTW

Eastern Cape

This municipality is receiving support from the Department

2015/02/10

None

None

Amathole District Municipality-Fort Beaufort WWTW

Eastern Cape

This municipality is receiving support from the Department

2015/04/09

None

None

Kou-Kamma Local Municipality WWTW

Eastern Cape

This municipality is receiving support from the Department

2015/04/09

None

None

O.R. Tambo DM

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/06/10

None

None

Sunday's River Valley LM

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/08/28

None

None

Joe Gqabi DM - Burgersdorp

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/08/28

None

None

Department of Public Works, Elliotdale EC Govern

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/08/28

None

None

Dept. of Public Works-Elliotdale Correctional Ser

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/08/28

None

None

CHDM (Scanlen Sewer Pump Station)

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2015/08/28

None

None

CHDM - Cradock Waste Water Treatment Works

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/02/10

None

None

CHDM (Michausdal Sewer Pump Station)

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/03/07

None

None

Ndlambe LM - Alexandria WWTW

Eastern Cape

This municipality is receiving support from the Department

2016/03/07

None

None

Kelvin Jones Waste Water Treatment Works (NMBM)

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/03/31

None

None

Nelson Mandela Bay Metro Mun. - Swartkops River

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/05/12

None

None

Nelson Mandela Bay Mun - Driftsands WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

Cradock Landfill site

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

Amathole District Municipality-Butterworth WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

Chris Hani DM - Engcobo WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

OR Tambo DM - Tsolo WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

OR Tambo DM - Port St Johns WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/08/02

None

None

OR Tambo DM - Mqanduli WWTW

Eastern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

2014/06/19

City of Tshwane

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

2014/07/22

Ekurhuleni Metropolitan Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

2014/07/22

City of Tshwane

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

2014/09/08

Ngaka Modiri Molema DM (RMLM)

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2014/09/02

2015/10/19

City of Johannesburg

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None 

2016/02/11

The Municipal Manager: Ekurhuleni Metropolitan Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2015/04/22

2016/04/25

Thabazimbi Local Municipality-Thabazimbi Waste Water Treatment Works

North West

Representation received and assessed on 03.05.16. Follow-up site meeting Follow-up meeting held to assess the progress

None

2014/09/11

2016/07/11

Kgetleng River LM

North West

Representation received and assessed on 02.10.14. Follow-up meeting held

None

2016/07/15

2016/08/22

Rustenburg Local Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2010/08/05

2010/08/02

2016/09/19

Thabazimbi local municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2012/12/18

None

Randfontein local municipality

North West

This municipality is receiving support from the Department

None

2013/01/24

None

Rustenburg Local Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2013/04/11

None

NGAKA MODIRI MOLEMA DISTRICT MUNICIPALITY

North West

This municipality is receiving support from the Department

None

2013/05/14

None

Rustenburg Local Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2013/09/18

None

Thabazimbi Local Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2013/11/21

None

City of Tshwane ( Sunderland Ridge WWTW)

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2014/09/04

None

City of Tshwane

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2014/09/08

None

Ngaka Modiri Molema District Municipality

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2014/11/13

None

Rustendurg local Municipality(Sunrise Park )

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2015/01/26

None

Tai Hsiang cc Koi Empire Farm Nooitgedacht 534

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2015/03/04

None

Ngaka Modiri Molema District Municipality (MLM)

North West

This municipality is receiving support from the Department

None

2016/05/06

None

City of Tshwane - Sandpsruit WWTW

North West

Representation received and assessed on 05/08/2016. Follow-up site visit was conducted on 12-10-2016

None

2016/06/13

None

City Of Tshwane - Klipgat WWTW

North West

Representation received and assessed on 05/08/2016. Follow-up site visit was conducted on 12-10-2016

None

2016/06/21

None

City of Tshwane Metropolitan Municipality

North West

Representation received and assessed on 30/06/2016

10/10/2015

None

None

Tshwane MM - Thembisa

North West

30/08/2016

None

None

ERWAT - Olifantsfontein WWTW

North West

Representation received and assessed on 12/09/2016. DWS to monitor the action plan.

15/07/2016

19/08/2016

None

Rustenburg Local Municipality - Marikana Pumpstation

North West

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2015/11/04

2016/02/15

Sol Plaatjie

Northern Cape

This municipality is receiving support from the Department

None

2015/11/05

2016/06/29

Dikgatlong Municipality

Northern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

2008/12/01

None

Dikgatlong Municipality: Warrenton WWTW

Northern Cape

This municipality is receiving support from the Department

None

2015/12/08

None

Dikgatlong Municipality Kathu WWTW

Northern Cape

This municipality is receiving support from the Department

None

2015/12/08

None

Dikgatlong Municipality Deben WWTW

Northern Cape

This municipality is receiving support from the Department

None

2015/12/08

None

Dikgatlong Municipality Dingleton WWTW

Northern Cape

This municipality is receiving support from the Department

None

2015/12/08

None

Dikgatlong Municipality Olifantshoek WWTW

Northern Cape

This municipality is receiving support from the Department

None

2016/05/13

None

Dikgatlong Municipality

Northern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

2016/05/25

None

2016/06/29

Phokwane Municpality: Jan Kempdorp WWTW

Northern Cape

The Department continues to engage with non-compliant municipalities that have been issued with notices and directives.

None

None

2014/02/26

Oudshoorn Local Municipality

Western Cape

Meeting held on 02/06/2016, they had not complied with various conditions . The Department to continue with compliance monitoring.

None

None

28 /09/2016.

George LM

Western Cape

An action plan was received on 06 October 2016 with a Sludge Compliance plan. They were monitored and found to be adhering to the conditions.

 

17 October 2016 - NW1962

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)(a) When does a certain person’s (name furnished) term as the Chairperson of Mhlathuze Water Board end and (b) for how many years has she served on the specified board; (2) whether the specified person’s contract was renewed for her current position on the specified board; if not, why not; if so, (a) how many times has the specified person’s contract been renewed since her initial appointment to the specified board, (b) why was the specified person’s contract renewed in each case and (c) what are the full relevant details of the process followed to renew the specified person’s contract in each case

Reply:

(1)(a) Ms Dudu Myeni is the Chairperson of the Mhlathuze Water Board. The term of office for the Chairperson has been extended until such a time that a new Board is appointed.

According to the Public Finance Management Act, 1999 (PFMA), as amended, the Minister is the Executive Authority of the National Public Entity with ownership control over such entity. The PFMA defines ownership control as the “ability to exercise any of the following powers to govern the financial and operating policies of the entity in order to obtain benefits from its activities:

  • To appoint or remove all, or the majority of, the members of that entity’s board of directors or equivalent governing body;
  • to appoint or remove that entity’s Chief Executive Officer;
  • to cast all, or the majority of, the votes at meetings of that board of directors or equivalent governing body; or
  • to control all, or the majority of, the voting rights at a general meeting of that entity.

(1)(b) Ms Myeni served on the Board of Mhlathuze Water since 2002. To ensure continuity and good governance of the entity, the Minister decided to extend her term of office.

(2) No. Due to the establishment of a single Water Board in KwaZulu-Natal, the Chairperson’s term of office was extended until such time that a new Board is appointed.

(2)(a) The contract has been renewed three (3) times since her initial appointment.

(2)(b)(c) Refer to the response provided in (1)(a) above.

---00O00---

13 October 2016 - NW1815

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)(a) What is the extent of the water infrastructure maintenance being undertaken in the Mopani District in Limpopo and (b) why did the cost of the specified project increase from R 94,4 million to R 502,6 million in three months; (2) (a) Who has been appointed as contractor(s) on the specified project, (b) what amount has been paid to the specified contractor(s) to date and (c) what is the current status of the specified project; (3) Did the specified project go out on tender; if not, why not; if so, (a) what are the names of the companies that made submissions for the specified tender and (b) what is the name of the company that was awarded the specified tender?

Reply:

(1)(a) In 2009, the Giyani area was officially declared a disaster zone as a result of terrible water and waste water situation. It was consequently adopted into the Presidential Siyahlola Programme. To redress the situation in Mopani, I issued an emergency directive in August 2014 to my Department’s Implementation Agent, i.e. Lepelle Northern Water to regularise water and sanitation provision in the Mopani District area.

In implementing the Directive, various projects were identified, categorised and prioritised in the Short - term/ critical emergency projects and the Medium - Long term projects as follows:

  • Below are the short-term/ critical emergency projects that were completed.
  • 16 Priority Villages Groundwater Augmentation;
  • Nkhensani Hospital Groundwater Augmentation;
  • Giyani WWTW 1.5Ml/day (package plant);
  • Giyani WWTW (refurb-existing plant);
  • Morogholo Transfer Pumpstation;
  • Kremetart Transfer Pumpstation;
  • Khanyisa Booster Pumpstation;
  • Nsami Water Treatment Plant (Refurb of old plant);
  • Nsami Water Treatment Plant (New) and;
  • Kremetart High & Low Reservoirs.

In addressing the medium to long term and the sustainability of the Mopani area and its surroundings, a number of projects were identified. The identified projects are in different stages of planning and designs and implementation, such as:

  • Nandoni – Nsami bulk pipeline project to augument water supply to Giyani Town and the project currently under implementation;
  • Giyani bulk water pipelines (Pipeline A, B, C, D, F1 & F2) currently under implementation covering approximately 345km distance;
  • Revitalization of existing 154 boreholes with package plants to augment the water scheme while the bulk pipelines in progress and project expected to be completed by December 2016;
  • The designs of Giyani Reservoir 35ML, Giyani 14ML Waste Treatment plant, Giyani Village reticulation, Nandoni Water Treatment upgrade, Bambanana/ Nkambako bulk pipeline projects. The planning and designs have been completed and the projects are ready for implementation; and
  • The design of the Namakgale Waste Water Treatment Plant is progressing well and expected to be finalised by end December 2016.

(1)(b) Over and above the designs and the implementation of the short-term/ critical emergency projects, Lepelle Northern Water is currently undertaking the Operation and Maintenance on existing and new infrastructure in Giyani Town which include material and/or equipment purchasing to refurbish dilapidated infrastructure.

The specified operation and maintenance is on-going as and when required on site to maintain the existing and new infrastructure until handed over to the Water Service Authority.

(2)(a) The contractor appointed by Lepelle Northern Water is LTE Consulting on a Turnkey basis for the project.

(2)(b) The approved budget for the Mopani Intervention project is R2.2 billion. Out of the approved budget an amount of R1 391 838.00 has been spent to date which include the amount of R57 million of the specified project i.e. operation and maintenance for the planning, designs and implementation of the Mopani Intervention project.

(2)(c) As indicated above, the short–term/ critical emergency projects have since been completed. The medium-long term projects are various planning, designs and implementation stages. The specified operation and maintenance is on-going as when required on site to maintain the existing and new infrastructure before is handed over to the Water Service Authority.

(3) Due to the emergency situation and the urgency to redress the water and sanitation in Mopani area the project did not go through the open tender process. However, the appointment of the Service Provider was completed through the close tender process using Department Panel. The specified project of operation and maintenance is part of the Mopani Intervention programme. As indicated in (2) above, LTE Consulting was appointed on a Turnkey basis for the project. We are convinced that the method used to appoint LTE Consulting is in line with SCM policy and National Treasury guidelines applicable to emergency/disaster situations.

---00O00---

07 October 2016 - NW2078

Profile picture: Kalyan, Ms SV

Kalyan, Ms SV to ask the Minister of Water and Sanitation

(1)Whether each Head of Department (HOD) of her department signed a performance agreement since their appointment; if not, (a) what is the total number of HODs who have not signed performance agreements, (b) what is the reason in each case, (c) what action has she taken to rectify the situation and (d) what consequences will the specified HOD face for failing to sign the performance agreements; if so, (i) when was the last performance assessment of each HOD conducted and (ii) what were the results in each case; (2) whether any of the HODs who failed to sign a performance agreement received a performance bonus since their appointment; if not, what is the position in this regard; if so, (a) at what rate and (b) what criteria were used to determine the specified rate; (3) whether any of the HODs who signed a performance agreement received a performance bonus since their appointment; if so, (a) at what rate and (b) what criteria were used to determine the rate?

Reply:

(1) The Director General signed a performance agreement and was captured on Persal on 20 May 2016.

(1)(a) Nil.

(1)(b) Falls away.

(1)(c) Falls away.

(1)(d) Falls away.

(1)(e) Falls away.

(1)(e)(i) The last performance assessment of the HOD was for 2014/2015.

(1)(e)(ii) The Director General’s final score was 145% but did not receive a performance bonus in line with the Minister of Public Service and Administration (MPSA) directive. No pay progression was paid as the Director General was already remunerated on the maximum salary package of level 16 with no further salary progression possible.

(2) Falls away.

(3) Falls away.

---00O00---

07 October 2016 - NW2043

Profile picture: Figg, Mr MJ

Figg, Mr MJ to ask the Minister of Water and Sanitation

What formal qualifications does each of her department’s (a)(i) Chief Financial Officers and/or (ii) acting Chief Financial Officers and (b)(i) Directors-General and/or (ii) acting Directors-General possess?

Reply:

(a)(i) Mr SV Mkhize, the Chief Financial Officer (Main Account), is in possession of a National Diploma Accountancy, Advanced Project Management Programme, and a Master Degree in Business Administration.

Mr M Mofokeng, the Chief Financial Officer (Water Trading Account), is in possession of a National Diploma Accountancy, and a B Tech in Business Administration.

(a)(ii) Ms MS Manukuza, the Acting Chief Financial Officer (Main Account), is a Chartered Accountant and is also in possession of a Bachelors of Commerce (Accounting), and an Honors in Bachelor of Accounting Sciences.

(b)(i) The post of Director-General is currently vacant.

(b)(ii) Mr SV Mkhize is currently acting as Director-General of Water and Sanitation, refer to (a)(i) above for qualifications.

---00O00---

07 October 2016 - NW2007

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

What (a) are the reasons for the recent water shortages experienced in (i) the Emalahleni Local Municipality and (ii) Amsterdam in the Mkhondo Local Municipality in Mpumalanga and (b) steps is her department taking to manage the water shortages in each case?

Reply:

(a)(i) The recent water shortages experienced in Emalahleni Local Municipality was due to the following reasons:

  • There were two major leaks on the bulk lines at Oliphant’s Drive main entrance to Bankenveld Golf Estate where the line was leaking back into the Witbank Dam through storm water channel which made it difficult to trace the leak. The second major leak was on the bulk feeder line to Phola/Ogies where fittings were stolen for scrap metals.
  • Power failure at the Grobler Substation which affected the pumping of water at Point B which is a feeder reservoir to Point C resulting in water shortages.
  • The municipality also depends on mines to augment portable water supply. However, for the last three weeks, the Municipality has not been receiving constant water supply from the mines due to dropping of ground raw water from the mines owing to the drought.
  • Whilst the Municipality was experiencing the above mentioned challenges, Point D Reservoir which is the command reservoir was flooded on the night of
    11 September 2016 at 23h00 due to a bursting of a pipe in one of the delivery pipe which affected the whole of eMalahleni.

(a)(ii) A valve on the pipeline from the Westoe Dam was broken and after the repair, it took two days for the community to receive water due to reservoirs that should be filled up in the private farms before it could reach the community.

(b) It is envisaged that construction the Mkhondo Bulk Water Supply will start in 2017/18 financial and end in 2019/20 financial year.

In eMalahleni Local Municipality – Currently there is eMalahleni Bulk Water supply under construction. It will be completed in 2018/19 financial year.

---00O00---

07 October 2016 - NW1961

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)Whether, with reference to the appointment of a board and chairperson for the proposed merger of the Mhlathuze and Umgeni water boards, she required that a selection panel be constituted in terms of section 3(1) of Schedule 1 of the Water Services Act, Act 108 of 1997, as amended; if not, why not; if so, (a)(i) on what date and (ii) in which media were the relevant notices referred to in section 2(1) of Schedule 1 of the specified act published and (b) what are the further relevant details regarding constituting the specified panel in terms of the requirements set out in section 3(7) of Schedule 1 of the specified act; (2) whether the specified panel received any nominations for board members; if not, why not; if so, (a) which nominees were included on the shortlist and (b)(i) when and (ii) where were the specified shortlisted nominees interviewed; (3) whether the specified panel made any recommendations to her with regard to the proposed appointments (a) to the specified board and/or (b) of a chairperson; if not, why not; if so, what are the relevant

Reply:

(1) The appointment of the new Board and the Chairperson for the single KwaZulu-Natal Water Board has not yet commenced. However, it should be noted that an Independent Transitional Committee was appointed to provide strategic guidance and oversight during the establishment process. The Independent Transitional Committee consists of representatives from the Department of Water and Sanitation, KwaZulu-Natal Premier’s Office, KwaZulu-Natal Cooperative Governance and Traditional Affairs, Chairperson of the Board of Umgeni Water and the Chairperson of the Board of Mhlathuze Water so as to ensure the successful establishment of the single Water Board in KwaZulu-Natal.

The Chairperson of the Board of Mhlathuze Water was appointed as the Chairperson of the Independent Transitional Committee and the Chairperson of the Board of Umgeni Water was appointed as the Deputy Chairperson of the Independent Transitional Committee. In addition, in terms of the Water Services Act, 1997 (Act No. 108 of 1997) (WSA) as amended, Schedule 1 Section 3(1) is not applicable to the appointment of the Independent Transitional Committee.

The requirements set out in Schedule 1 Section 3(7) of the Water Services Act, 1997 (Act No. 108 of 1997) (WSA) as amended, is not applicable to the appointment of the Independent Transitional Committee.

(2) There is no new Board and Chairperson appointed for the single KwaZulu-Natal Water Board. The Independent Transitional Committee consists of representatives from the Department of Water and Sanitation, KwaZulu-Natal Premier’s Office, KwaZulu-Natal Cooperative Governance and Traditional Affairs, Chairperson of the Board of Umgeni Water and the Chairperson of the Board of Mhlathuze Water.

(3) Refer to answer in point (1) and (2) above.

---00O00---

07 October 2016 - NW2006

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)(a) What levels of E.Coli were detected in the water quality tests done for the Louise Road Dam in Del Judor in the Emalahleni Local Municipality in Mpumalanga in each month during the period 1 April 2016 up to the latest specified date for which information is available and (b) on what date was each such test conducted; (2) whether any risks to drinking water quality were detected in any of the specified tests conducted during the specified period; if so, in each case, what (a) risks were detected, (b) sources of risk have been identified and (c) is being done to address each risk?

Reply:

(1) My Department does not conduct tests for E. Coli on the Louise Road Dam, the dam was formed as a result of an unrehabilitated quarry. However, emergency samples were taken on 23 September 2016 to ascertain the levels of E. Coli in the dam.

(2)(a) None

(2)(b) None, my Department has no data in terms of the risks detected for the Louise Road Dam as it is not part of the two (2) sampling points where samples are taken on monthly basis for the drinking water compliance monitoring.

(2)(c) None

---00O00---

07 October 2016 - NW2122

Profile picture: Rawula, Mr T

Rawula, Mr T to ask the Minister of Water and Sanitation

By what date is she going to eradicate the bucket system in Grave Yard and Marikana informal settlements in the North West?

Reply:

The Bucket Eradication Programme is focusing on the eradication of bucket toilets in FORMAL areas and not informal areas. The North West Department of Human Settlement together with the relevant municipality should put measures in place to address the upgrading or the relocation of the informal settlement.

---00O00---

27 September 2016 - NW1721

Profile picture: Bilankulu, Ms NK

Bilankulu, Ms NK to ask the Minister of Water and Sanitation

(a) What progress has been made with regard to the Nooitgedacht Low Level Scheme Phase 2 project which is intended to augment water supply and alleviate water scarcity at the Nelson Mandela Bay Metropolitan Municipality (NMBM) and (b) what are the challenges that have been encountered with regard to completing the project?

Reply:

(a) Phase 2: This phase is fully funded by the NMBM. It entails the construction of an extension of the Nooitgedagt Water Treatment Works (Civil works) on the Western side, all Mechanical and Electrical work associated with the civil works and a new Pump Station. All the work is under construction and approximately 60% completed. This phase should be finished by end of June 2017.

Phase 3: This phase is fully funded by my Department. It entails an extension of the Nooitgedagt Water Treatment Works (Civil works) on the Eastern side (Augmentation of the WTW's by 70Ml/day), all Mechanical and Electrical work associated with the civil works, a new 45Ml Reservoir at Olifantskop, Cathodic Protection and AC mitigation on all bulk lines as well as the rehabilitation of the Chelsea Motherwell pipeline. All the work has gone out on tender which closes on Friday 2 September 2016. All the evaluation and adjudication processes will then follow and it is expected to appoint a contractor by end of October 2016 after which site establishment and construction should start. It will be a 24 months construction period and the anticipated completion date is December 2018.

(b) Phase 2: The only challenges experienced in this phase were rain delays. No further challenges were experienced.

Phase 3: One of the challenges experienced was the signing of a Tri-Partite agreement between the Implementing Agent, Amatola Water, (Appointed by the DWS), DWS and the NMBM. This should however be solved in due course.

Another challenge which caused a delay was the decision of the tender processes on whether to put the work out on different tenders since the work requires different disciplines and skills and/or whether all the work should go out as one tender. The decision was to put it out on one tender which as mentioned above is closing on Friday 1 September 2016.

---00O00---

27 September 2016 - NW1816

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)(a)(i) From which country did her department import the desalination package plant in Richards Bay, KwaZulu-Natal and (ii) at what cost and (b)(i) who is operating the specified plant and (ii) at what cost; (2) what is the (a) capacity of the specified plant and (b)(i) cost of desalinating and (ii) selling price of each kilolitre of water; (3) whether the correct tender processes were followed to procure the specified plant; if not, what is the position in this regard; if so, what are the relevant details; (4) why did she not consider any South African companies before the procurement of the specified plant?

Reply:

(1)(a)(i) The Desalination Package Plant is supplied by a local company in KwaZulu- Natal.

(1)(a)(ii) The total costs of package plant amount to R250 million excluding VAT.

(1)(b) The packed desalination plant will be operated by Mhlathuze Water at a cost yet to be determined as discussions are still ongoing.

(2)(a) A total of 10Mega Litres per day will be produced by the desalination plant.

(2)(b)(i) The cost of the desalination plant is R250 million excluding VAT.

(2)(b)(ii) The selling price of each kilolitre of water is R3.96.

(3) My Department's supply chain procedures were followed as per National Treasury guidelines.

(4) A local company was appointed to procure these services.

---00O00---

27 September 2016 - NW1814

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

(1)(a) When did the pipeline project between the Craigieburn Dam and Greytown in KwaZulu-Natal start and (b) what is the (i) budgeted cost of the specified project and (ii) distance of the pipeline; (2) whether the specified project has been completed; if not, (a) why not, (b) when will it be completed, (c) what is the cost of the project to date and (d) what is the total estimated completion cost of the project; if so, on what date was the specified project completed; (3) did the specified project go out on tender; if not, why not; if so, (a) what are the names of the companies that made submissions for the specified tender and (b) what is the name of the company that was awarded the specified tender?

Reply:

(1)(a) The pipeline project between the Craigieburn Dam and Greytown in KwaZulu-Natal started on 24 March 2015.

(1)(b)(i) The budgeted cost of the project was R203 802 607 including escalation, contingencies and VAT.

(1)(b)(ii) The distance of the pipeline is 35.0km

(2)(a) The project has not been completed due to poor performance of the three contractors appointed in the project which resulted in termination of the contracts.

(2)(b) It will take about eleven (11) weeks to complete the outstanding scope of the works. The actual start and completion dates will be negotiated between uMzinyathi District Municipality and the prospective replacement contractors once appointed through Section 32 of the Municipal Supply Chain Management Regulations.

(2)(c) The cost of the project to date is R79 493 188.

(2)(d) The total estimated cost to complete the project is R138 647 000.

(3) Yes, the project went out on tender.

(3)(a) The companies that made submissions for the specified tender are as follows:

Bankuna Engineering

V. Bhengu Construction

Sizabonke t/a Pilcon Projects

Moray & Dickson Construction

Shula Construction

Nongafa Construction

Igugulabafazi Developments

Soundrite Construction

JMngcwango Trading

Valente Bros (Pty) Ltd

Barleda 65 cc JV Busizwe

Ntandoyami JV

Velakude Trading JV Ugwadule Trading

R&B Pipelines JV Sikoti

TBA Construction

Blue Dot G Services

F&A Civils

Thembalethu Civils

Anvisba Civils

Lenong Azishe JV

WK Construction

Velekude JV Umzuzu cc

Cycade Pipelines

AM Pomolong JV

WBHO Construction

Tshenolo Resources JV Kufiki

Namandla Roads & Civils

Esor Construction

Cerimele Construction

Phumi JV Ishishini

Zanamanzi Services

 

(3)(b) The pipeline was broken into three contracts, and the contractors awarded the tenders were Soundrite Construction, Bankuna Engineering and Phumi/Ishishini JV.

---00O00---

27 September 2016 - NW1813

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

(1)(a) When was the raising of the wall of the Hazelmere Dam in KwaZulu-Natal approved, (b) what is the (i) approved budget and (ii) cost of the project to date, (c) when will the specified project be completed and (d) what is the expected completion cost of the specified project; (2) did the specified project go out on tender; if not, why not; if so, (a) what are the names of the companies that made submissions for the specified tender and (b) what is the name of the company that was awarded the specified tender?

Reply:

(1)(a) The project was approved as a Government water work on 8 June 2010.

(1)(b)(i) The approved budget is R593 million.

(1)(b)(ii) The Expenditure as at August 2016 is R233 million.

(1)(c) The expected completion date is January 2018 (revised per programme).

(1)(d) The expected completion cost is R620 million (revised).

(2) Yes, the project went out on tender.

(2)(a) Below are the names of the companies that made submissions for the tender:

 

BIDS RECEIVED

1.

Bicacon PTY/Mapitsi Civils/Setheo Consortium & SinoHydro Joint Venture (JV)

2.

Lubbe Construction

3.

Aveng Grinaker

4

Basil Read LTD/

Rodio Consortium

5.

MRC – DSB Consortium

6.

Group Five Coastal (PTY) LTD

(2)(b)

The name of the company that was awarded the tender is Group Five Coastal (PTY) LTD.

---00O00---

27 September 2016 - NW1812

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

Whether her department had any unspent budget funds at the end of the 2015-16 financial year; if not, what is the position in this regard; if so, (a) what was the amount of unspent budget funds at the end of the specified financial year and (b) what amount of unspent funds, if any, did she request the National Treasury to roll over; (2) Whether the National Treasury approved the roll-over of any unspent funds; if not, why not; if so, what amount?

Reply:

(1) My Department did have unspent budget funds at the end of the 2015-16 financial year.

(1)(a) My Department has recorded an under expenditure of R189.558 million for the 2015-16 financial year.

(1)(b) Of the reported under expenditure of R189.558 million, my Department had requested to rollover funds from 2015-16 financial year to 2016-17 financial year in an amount of R77.448 million.

(2) National Treasury did not grant approval to the Department’s request for rollover of funds as it has been deemed that the Department can accommodate the related expenditure within the existing baselines.

---00O00---

27 September 2016 - NW1722

Profile picture: Bilankulu, Ms NK

Bilankulu, Ms NK to ask the Minister of Water and Sanitation

(a) What progress has been made with regard to the Bucket Eradication Programme in the provinces where the specified programme has not been fully implemented and (b) what are the reasons for the delay in the completion of the specified programme?

Reply:

(a) The Bucket Eradication Programme is being implemented in the Northern Cape, Free State, North West and Eastern Cape Provinces, and the progress is indicated in the table below:

Province

Targets

Units Completed

Flushing

Not yet Flushing

Remaining to be constructed

Northern Cape

7618

7056

3685

3371

562

Eastern Cape

3319

3269

2919

350

50

North West

223

223

223

0

0

Free State

13880

13698

1827

11871

182

 

25040

24246

8654

15592

794

(b) Below are reasons for the delay in the completion of the specified programme:

  • Extreme difficult soil conditions exist in the Northern Cape with moderate conditions in the Free State Province which requires sophisticated machinery to enable the excavation of the rock formations;
  • In some towns, the extent of the sewer and water reticulation is in excess of 50km which with some difficult soil conditions slows the excavation process;
  • Due to the flat terrain of some projects, deep excavations for services, often as deep as 3m must be excavated to ensure gravity flows once connected;
  • Disruptions of existing services (due to excavations without drawings or designs of where existing services are located) such as water and electricity in some projects necessitate stoppages so as to restore the service before commencement.
  • The non-availability of materials (toilet structures, pipelines for water and sewer, conservancy tanks) have posed an additional delay in terms of acquiring such from suppliers often outside of the province;
  • Community protests or disputes over daily labour rates have delayed the project in some provinces for up to 3 weeks at a time.

---00O00---

27 September 2016 - NW1716

Profile picture: Schmidt, Adv H

Schmidt, Adv H to ask the Minister of Water and Sanitation

Whether any funds allocated to her department for the Sedibeng Regional Sewerage Scheme in the Sedibeng District Municipality in Gauteng by the Presidential Infrastructure Coordinating Committee have been withdrawn; if not, what is the position in this regard; if so, (a) what are the full reasons for the withdrawal of funds and (b) what amount of funding has been withdrawn?

Reply:

(a) The Sedibeng Regional Sanitation Scheme comprises the upgrade construction of the Sebokeng Waste Water Treatment Works (WWTW), upgrade of the Meyerton WWTW, review of the feasibility study for the possible upgrade of the Rietspruit and Leeuwkuil WWTW, the construction of the Regional WWTW in Sedibeng, as well as the upgrade of the associated bulk collection infrastructure; such as pipelines and pump stations. The Project has not been withdrawn, but is underway and the Sebokeng WWTW and Meyerton WWTW are under construction; and the Sedibeng Scheme is under implementation readiness study.

(b) No amount of money has been withdrawn.

---00O00---

13 September 2016 - NW1697

Profile picture: Bilankulu, Ms NK

Bilankulu, Ms NK to ask the Minister of Water and Sanitation

(a) What is her department’s time frames for (i) commencing with Phase 2 of the Lesotho Highlands Water project and (ii) completing the project, (b) at what stage will the preparatory work, including the appointment of contractors, be completed and (c) what impact will these have on the water resources available to South Africans?

Reply:

(a)(i) The Master Implementation Program, given the status of the Project it is currently, refer to the table below. It should be noted that, the completion of construction dates are dependent on some critical matters such as unforeseen rock conditions encountered when drilling the tunnel since limited geotechnical investigation can be done due to the tunnel alignment being situated very deep below the ground surface.

MASTER IMPLEMENTATION PROGRAM: CRITICAL DATES

Deadlines

Designs of advance Infrastructure commence

Apr 15 – end Sept 18

Award tenders for Polihali Dam design and Polihali Tunnel design

June 17, July 17

Award tenders for construction of Advance Infrastructure

Mar 17 – Oct 20

Award tenders for construction of Polihali Dam and Tunnel

Jul 19, Aug 19

Start impounding water in Polihali dam

May 23

Construction of Polihali Dam complete

Aug 24

Construction of Polihali to Katse Tunnel complete

Jan 25

Water delivery to RSA commence once Transfer Tunnel is complete

End Jan 25

(a)(ii) Delays encountered was due to the evaluating the complex bid documents and the severe adverse weather conditions since most of the work sites are situated high up in the Maluti Mountains.

(b) Refer to table above.

(c) My Department has established a Strategy Steering Committee consisting of all the Major Stakeholders of the Vaal River System (VRS). This Steering Committee is guiding the implementation of various interventions to ensure that there will be enough water in the system until LHWP Phase 2 (Polihali Dam) can deliver water.

Interventions such as the eradication of unlawful water use, implementation of Water Conservation and Water Demand measures, the desalination and re-use of Acid Mine Drainage, as well as the re-use of sewage return flows.

Although the occurrence of drought is a natural phenomenon causing restrictions to be imposed from time to time, over the medium long-term, the delay in the implementation of Polihali Dam will unfortunately cause periods when the implementation of the above mentioned interventions will not be sufficient to supply enough water which will increase the possibility of unnecessary or pre-mature restrictions in the VRS.

The VRS is currently in a drought situation and it was decided in consultation with the various Stakeholders in the VRS to start the process of implementing progressive water restrictions over the short-term to ensure that a basic water supply can be ensured.

---00O00---

09 September 2016 - NW1693

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

How many mining companies in Mpumalanga were issued with water rights licences (a) in the 2012-13 financial year and (b) since 1 April 2016, in each case indicating the (i) names, (ii) locations, (iii) products being mined at each of the specified companies, (iv) the volume of water approved and (v) source of abstraction of the water?

Reply:

(1) A total of 20 mining companies were issued with water use licenses in the 2012-13 financial year. Names, locations, products being mined, volume of water approved and the source of abstraction appear in Table 1:

Table 1: Details of mining companies issued with water use licenses, 2012-13, Mpumalanga

No

Name

Type of product

Property details

Province

Volume of water

Source of Abstraction

1

Total Coal SA-Forzando North

Coal

Portion 9, 24, and 10 of the farm Weltervreden 193 IS

Mpumalanga

237 600m3/a

groundwater

2

Xstrata - Platinum Flotation - Thorncliffe and Mototolo

Platinum

Thorncliffe 374 KT, Grooteboom 373 KT and Mototolo mine

Mpumalanga

85 775 m3/a

groundwater

3

African Exploration Mining and Finance Corporation: Vlakfontein Mine

Coal

Ptn 3 Vlakfontein 569 JR

Mpumalanga

N/A

N/A

4

Maphocs Mine

Coal

Mapochsgronde 500 JS; Ptn 0 Zwartkop 142 JS

Mpumalanga

341 676m3/a

groundwater

5

Universal Coal and Energy (Pty) Ltd - Kangala Coal Mining

Coal

Wolvenfontein 244 IR ptn 1&2

Mpumalanga

384 060m3/a

groundwater

6

HCI Khusela Coal (Pty) Ltd -Mbali Colliery

Coal

Ptn 16, 17 Klippoortjie 32 IS

Mpumalanga

477 597m3/a

groundwater

7

Corridor Mining

Coal

Ptn 0 Zwartkoppies 413 KS; Ptn 0 Waterkop 113 KT

Mpumalanga

8 820m3/a

Borehole

8

Stuart Coal (Pty) Ltd

Coal

Ptn 9 & 10 of farm Weltervren 227 IR

Mpumalanga

15 000m3/a

Borehole

9

Muhanga Mine: Emmerenthia

Coal

Ptn 13 &19 of farm Kafferstad 195

Mpumalanga

N/A

N/A

10

Sudor Coal -Elandsfontein

Coal

Elandsfontein 75 IS Portions. 4, 7 & 8

Mpumalanga

1 320m3/a

Borehole

11

Shanduka Coal (Pty) Ltd: MTC extension

Coal

Elandspruit 291 JS 14

Mpumalanga

1 801 825 m3/a

groundwater

12

Umcebo Mining: Kleinfontein

Coal

Kleinleeuwfontein 563 IS

Mpumalanga

1 200 m3/a

groundwater

13

Umcebo: Umsimbithi Wonderboom Mine

Coal

Ptn 14 farm klippan 452 JS, Ptn 2,3,6,12, 15, 19, 21,22,23,25 farm wonderfontein 428 JS

Mpumalanga

2 760 600m3/a

groundwater

14

Wildfontein Colliery

Coal

Wildfontein 420 JS

Mpumalanga

1 584m3/a

groundwater

15

Shanduka Coal: Graspan Colliery

Coal

Rietfontein 286 JS, RE of Ptn

Mpumalanga

1 033 315m3/a; 250 521m3

groundwater

16

Inkomati Anthracite Mine (Pty) Ltd

Anthrasite

Wildebeest 494 JU

Mpumalanga

125 420m3/a

groundwater

17

Xstrata Coal SA Tweefontein Complex: Optimasation Project

Coal

Tweefontein 13IS

Mpumalanga

4 354 815m3/a

groundwater

18

Muhanga Mine: Op Goedenhoop Mine

Coal

Opgoedenhoop 205 IS

Mpumalanga

16 800 m3/a

groundwater

19

Elitheni Coal (Pty) Ltd

Coal

Machubeni 3 Allotment Area

Mpumalanga

276 000m3/a

groundwater

20

Umnotho Wesizwe Resources (Pty) Ltd - Mooihoek Chrome Mine

Chrome

Mooihoek 255 KT 1

Mpumalanga

300m3/a

groundwater

A total of 22 mining companies were issued with water use licenses since 01 April 2016. Names, locations, products being mined, volume of water approved and the source of abstraction appear in Table 2:

Table 2: Details of mining companies issued with water use licenses since 01 April 2016, Mpumalanga

 

Number

Name

Product

Property details

Province

Volume

Source of Abstraction

1

Vergenoeg Mining Company (Pty) Ltd

Coal

Portion 4 of the farm Kromdraai 209 JR

Mpumalanga

255 000 m3/a

Surface water: Rust De Winter Dam

2

Delf Sand (Pty) Ltd: Cullinan

Sand

Brandbach JR , Portion 63 & 67

Mpumalanga

214 620 m3/a

Groundwater

3

Umzobanzi Coal and Energy cc: Schoongezicht coal

Coal

Schoongezicht, 308 JS, Portion 6.

Mpumalanga

N/A

N/A

4

Msobo Coal (Pty) Ltd: Veerdepan Mine

Coal

Verkeerdepan 50 IT

Mpumalanga

10 368 m3/a

Groundwater

5

Just Coal (Pty) Ltd: Bankfontein Colliery & Beneficiation Plant

Coal

Bankfontein 375 JS, portion 48

Mpumalanga

24 090 m3/a

Groundwater

6

Wescoal Mining (Pty) Ltd: Khanyisa Colliery

Coal

Portion 106 of the farm Heuvelfontein 215 IR

Mpumalanga

36 000 m3/a

Groundwater

7

Tubatse Chrome (Pty) Ltd

Chrome

Portion 6 of Goudmyn 337 KT

Mpumalanga

508 919 m3/a

Groundwater

8

Pembani Coal Caroline (Pty) Ltd

Coal

Re Kwaggafontein 8 IT

Mpumalanga

1 944 363 m3/a

Groundwater

9

Glencore Operations South Africa (Pty) Ltd: Merafe Venture Operations- Lydenburg Smelter

Coal

Plot 2541 of Lydenburg Extention 10

Mpumalanga

N/A

N/A

10

Eastside Coal Company (Pty) Ltd- Eastside Colliery

Coal

Paardeplaats 12 IT, the Remaining extent of Portion 1 & Haarlem 39 IT, Portion 1.

Mpumalanga

586 522 m3/a

Groundwater

11

Freddies Minerals (Pty) Ltd

Coal

Portion 2 of the farm Morelag 5 KU

Mpumalanga

7 300 m3/a

Groundwater

12

Dialstat Trading 115 (Pty) Ltd: Water Pipeline from Lakeside to Argent Colliery

Coal

Welgelegen 211 IR portion 9 &2

Mpumalanga

600 000 m3/a

Surface water, open void

13

Canyon Springs investments 82 (Pty) Ltd: Canyon Springs Coal Mine

Coal

Roodekoppies 167 JR, Portion 3, 4 and RE

Mpumalanga

641 800 m3/a

Groundwater

14

Universal Coal Development- Kangala Colliery

Coal

Portion 1 RE of the portion 2 of the farm Wolvefontein 244 IR

Mpumalanga

246 866.25 m3/a

Groundwater

15

Anglo Operations (Pty) Ltd: Goedehoop Colliery- Dump expansion and Briquetting plant

Coal

Portion 12, 17, 18 and 41 Koornfontein 27 IS

Mpumalanga

N/A

N/A

16

Omaruru Minerals (Pty) Ltd: Elandshoogte Gold Mine

Gold

Portion 3 of the farm Elandshoogte 270 JT

Mpumalanga

72 000 m3/a

Groundwater

17

Liquid Mist Trading (Pty) Ltd: Beneficiation Plant

Coal

Portion 137 of the farm Blesboklaagte 296 JS

Mpumalanga

19 710 m3/a

Groundwater

18

Bokoni Platinum Mine: Klipfontein Section

Platinum

Klipfontein 465 KS

Mpumalanga

66 792 m3/a

Groundwater

19

Barberton Mines (Pty) Ltd: Fairview Mine

Coal

Remaining extent of Fairview 708 JU

Mpumalanga

2 544 964 m3/a

Groundwater

20

Perisat Investments (Pty) Ltd: Rirhandzu Colliery

Coal

Vlakvarkfontein 213 IR Portion 4, 14 & 15

Mpumalanga

4 380 m3/a

Groundwater

21

Corridor Mining Resources: Twyfelaar section

Coal

Twyfelaar 119 TKT

Mpumalanga

4 800m3/a

Groundwater

22

Optimum Coal Mine (Pty) Ltd: Schoonoord Operations

Coal

Brakpan 163 IS and Schoonoord 164 IS

Mpumalanga

520 000 m3/a

Groundwater

---00O00---

07 September 2016 - NW1678

Profile picture: Schmidt, Adv H

Schmidt, Adv H to ask the Minister of Water and Sanitation

Whether funding has been allocated to her department through the Division of Revenue Act, Act 3 of 2016, for the provision of regional bulk infrastructure for the Sedibeng Regional Sewerage Scheme in the Sedibeng District Municipality in Gauteng; if so, what amount has been budgeted for the specified scheme in the (a) 2016-17, (b) 2017-18 and (c) 2018-19 financial years?

Reply:

Yes the Department through Regional Bulk receive conditional grant allocated in terms of Division of Revenue Act, 2016 (Act No. 3 of 2016) (DoRA).

Sedibeng Regional Sewerage Scheme is allocated funding as follows:

(a) 2016/17 - R50 000 000.00

(b) 2017/18 – R64 200 000.00

(c) 2018/19 – R100 000 000.00

---00O00---

07 September 2016 - NW1674

Profile picture: Stubbe, Mr DJ

Stubbe, Mr DJ to ask the Minister of Water and Sanitation

(a) How many bucket toilets are still being used in the (i) Ramona, (ii) Santa Centre and (iii) Lerato Park informal settlements in Kimberley in the Northern Cape, (b) what measures have been put in place to eradicate the bucket toilets in the specified areas and (c) by what date will her department introduce a proper sanitation system in the specified areas?

Reply:

(a)(i) The settlement Ramona (located in Galeshewe) is occupied by approximately 200 households however it is an informal settlement using the bucket system for sanitation.

(a)(ii) The Santa Centre is a formalized township with some 143 even from the approved general plan however some buckets in 210 households occupying the area or land are using bucket system for sanitation. Municipality will once land is identified, relocate the balance of the settlement and allocate stands accordingly.

(a)(iii) The Lerato Park (is a formalised township in terms of an approved Surveyor General Diagram) area is the subject of a new housing development with approximately 1400 housing units. Lerato Park can be classified as in-situ upgrading and relocating families to the new housing units. A total of 1200 households occupying the area are using the bucket system. Currently, the growth of the settlement exceeds the number of housing units to be constructed and alternative land must be identified by the municipality for the households that cannot benefit from the current housing development.

(b) and (c) Providing sanitation in informal settlements and the upgrading or relocation of settlements into a new human settlements in the main is the responsibility of the Provincial Department of Human Settlements and Local Government (Municipalities).

---00O00---

30 August 2016 - NW1695

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

Why was the R43 million tender for a regional water purification plant in the Umzinyathi District in KwaZulu-Natal that was initially awarded to a certain company (name furnished) cancelled and subsequently awarded to another company (name furnished) and (b) what criteria were used to award the specified tender to the specified company?

Reply:

(a) The tender in question was allocated a budget of R34 million and not R43 million. The tender was never awarded to any “certain company” before its cancellation. Out of five of the companies that had been shortlisted in terms of technical functionality, two of them were far above the allocated budget thereof, one was above, and two were far below the allocated budget, which would have compromised the quality of the final product.

(b) A Regulation 32 Appointment was done, with strict adherence to requirements related thereto in order to expedite the process of delivering a water purification plant quickly to the community of uMsinga Local Municipality that is experiencing serious water shortages in this time of drought. The company that was eventually awarded a tender and appointed is currently doing a good job at the cost which is within the allocated budget of the project.

---00O00---

30 August 2016 - NW1694

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)Which municipalities are benefiting from the Accelerated Community Infrastructure Programme in Mpumalanga; (2) what is the (a) nature of the interventions being implemented, (b) cost thereof and (c) time frames for each of the specified municipalities?

Reply:

(1) The Municipalities benefiting from the Accelerated Community Infrastructure Programme in Mpumalanga are the following:

  • Thaba Chweu Local Municipality;
  • Dr Pixley ka Seme Local Municipality; and
  • Emakhazeni Local Municipality (with 3 projects).

(2) Refer to the table below for the Nature of projects, cost and timeframe for each of the specified municipalities:

Municipality

Nature of the Project/Project Name/

Cost /Budget allocated for the Financial Year 2016/2017

Time frame

Emakhazeni LM

Refurbishment of Waterval Boven WWTW and Booster pump stations

R6 365 000

6 Months

(March-Nov)

Emakhazeni LM

Refurbishment of Belfast WWTW and Booster pump stations

R8 567 000

6 months

(March- Nov)

Emakhazeni LM

Refurbishment of Machadodrop WWTW

R2 000 000

6 months

(March-Nov)

ThabaChweu LM

Refurbishment of Lydenburg WWTW

R7 731 000

6 months

(March- Nov)

Dr PixleykaSeme LM

Refurbishment of Amersfoort WWTW and Booster pump stations

R3 302 000

6 months

(March -Nov)

Total

R27 965 000

 

---00O00---