ATC121130: Report of the Select Committee on Appropriations on the Progress with the Local Government Turnaround Strategy, Operation Clean Audit By 2014, and the Establishment of the Municipal Infrastructure Support Agency, dated 27 November 2012
Standing Committee on Appropriations
REPORT OF THE SELECT COMMITTEE ON
APPROPRIATIONS ON THE PROGRESS WITH THE LOCAL GOVERNMENT TURNAROUND STRATEGY, OPERATION
CLEAN AUDIT BY 2014, AND THE ESTABLISHMENT OF THE MUNICIPAL INFRASTRUCTURE
SUPPORT AGENCY, DATED 27 NOVEMBER 2012
1.
Introduction
The
Committee invited the Department of Cooperative Governance and Traditional
Affairs (
CoGTA
) to a meeting on 29 August 2012, to make
presentations on the following:
·
Local Government Turnaround Strategy;
·
Operation Clean Audit by 2014; and
·
Municipal Infrastructure Support Agency.
During
the meeting referred to above the Committee decided not to continue with the
engagement on the presentation on progress with Operation Clean Audit because it
contained insufficient information.
CoGTA
was
requested to prepare a more detailed report to present to the Committee at a
later date.
During
a follow-up meeting on 17 October 2012, a delegation from the Department of Cooperative
Governance and Traditional Affairs, led by the Director-General, presented a
more detailed report on the progress with Operation Clean Audit by 2014, as
requested by the Committee at the meeting of 29 August 2012.
2. Department of Cooperative
Governance and Traditional Affairs progress report on Local Government
Turnaround Strategy
The
Local Government Turnaround Strategy (LGTAS) had been approved by Cabinet in
December 2009 and had been intended as the overarching strategy that included
flagship projects such as Operation Clean Audit, Business-Adopt-a-Municipality,
Revenue Enhancement as well as the Special Purpose Vehicle - now the Municipal
Infrastructure Support Agency (MISA) - and
CoGTA
indicated that as a result of restructuring in the
Department there had been a state of paralysis for approximately 18 months from
2011 to the middle of 2012; with uncertainty on political and administrative
levels. The original LGTAS team had also been disbanded in the beginning of
2011. However,
CoGTA
reported that due to the buy-in
of the provinces and municipalities to the impetus of the LGTAS, some of them
continued implementing some components of the strategy, like the establishment
of provincial coordinating committees of
OPCAs
and
the institutionalisation of LGTAS units in provinces.
With
the arrival of the new Minister for Cooperative Governance and Traditional
Affairs, there had been a renewed focus and emphasis on the acceleration of the
LGTAS. The strategy had been revived with a refined focus on 108 targeted
municipalities. These had been approved by MINMEC on 25 May 2012. The following
priority areas, that would be critical in improving municipal audit outcomes,
were identified:
·
Accelerating service delivery;
·
Enhancing good governance;
·
Promoting sound financial management;
·
Fighting corruption; and
·
Facilitating sustainable infrastructure development.
According to
CoGTA
, the
LGTAS was being co-ordinated by a team of senior officials from three branches
within
CoGTA
. The state of permanence of the team was
being finalised.
CoGTA
branches were in the process
of incorporating and mainstreaming the LGTAS into their Annual Performance
Plans (
APPs
).
CoGTA
identified
the following key stakeholders for the roll-out of LGTAS:
·
National
Departments of Energy, Water Affairs, Public Works, Economic
Development, Human Settlements, Rural Development and Land Reform, and Environmental
Affairs;
·
Heads of provincial
CoGTA
departments;
·
Provincial sector departments;
·
Provincial LGTAS coordinators;
·
Municipal Managers of district and local
municipalities
·
CoGTA
Technical
Support Units;
·
CoGTA
branch
representatives;
·
South African Local Government Association (SALGA) National
and Provincial Executive Officers; and
·
Municipal Infrastructure Support Agency (MISA)
deployees
.
3. Department of Cooperative
Governance and Traditional Affairs progress report on Operation Clean Audit by
2014
3.1 Vision, goal and purpose
CoGTA
reported that the guiding vision of Operation Clean Audit
by 2014 (OPCA), was that by 2014, all 278 municipalities would achieve
unqualified audit opinions on their Annual Financial Statements.
CoGTA
further stated that their strategic goal was to
provide assistance to all municipalities to achieve sustainable improvement of
systems for maintaining quality financial and information management. They
further reported that their strategic purpose was to address all issues raised
by the Auditor-General and to reduce the vulnerability to risks in the
municipal financial management and governance process through targeted
interventions.
3.2 Objectives and performance
The
first objective had been that between 2010 and 2011, no municipality would
receive adverse and disclaimer audit opinions. This objective had not been
achieved. According to preliminary results, 50 disclaimers and seven adverse audit
opinions had occurred.
The
second objective had been that 60 per cent of all municipalities would achieve
unqualified audit opinions by 2012. This had not been achieved. According to
preliminary results, 44.5 per cent of municipalities had achieved unqualified
audit opinions for the 2010/11 financial year.
The
final two objectives had been for at least 75 per cent of municipalities to
achieve unqualified audit opinions by 2013; and for 100 per cent to achieve unqualified
audit opinions by 2014.
CoGTA
conceded that these
targets were unlikely to be achieved. They reported that, through combined
effort and commitment, they believed that at least 70 per cent of
municipalities would achieve clean audit opinions by 2014.
3.3 Alignment with LGTAS focus areas
CoGTA
reported that from July to the end of August 2012, visits
had been conducted to all provinces to discuss the provincial LGTAS action
plans for the 108 identified municipalities.
A report on the profile of the 108
municipalities in relation to the five LGTAS focus areas would be concluded by
the end of November 2012.
3.4 Audit outcomes
CoGTA
presented the progress report with regard to municipal
audit outcomes from the 2008/09 to the 2010/11 financial years as follows:
Audit Opinion
|
2010/11
|
2009/10
|
2008/09
|
Clean
|
5%
|
2%
|
0,3%
|
Financially
unqualified with findings
|
41%
|
43%
|
41%
|
Financially
unqualified financial statements
|
46%
|
45%
|
42%
|
Qualified
|
20%
|
26%
|
17%
|
Adverse
|
5%
|
3%
|
4%
|
Disclaimer
|
23%
|
25%
|
37%
|
Audits not issued
|
6%
|
2%
|
0,3%
|
Total
municipalities
|
278
|
278
|
278
|
AFS submission
outstanding
|
3%
|
2%
|
0,3%
|
(Based on information as at 27 July 2012)
|
|
|
|
CoGTA
reported that the above table showed an improvement in the
municipalities that had received financially unqualified opinions without
findings and those with findings from 42 to 46 per cent. They further pointed
out that the number of municipalities that received a qualified opinion had
fluctuated. In the two previous financial years, there had been no improvement
in municipalities that had received adverse and disclaimer opinions.
3.5 Action plan
CoGTA
reported that they had developed an action plan that
clustered activities to be undertaken up to 2014 within the context of the
following three critical areas identified from the Auditor-Generals report:
·
Leadership (political and administrative);
·
Governance; and
·
Financial management.
The
action plan identified stakeholders responsible for particular actions in the
drive to support municipalities to achieve better audit opinions. A Local
Government MINMEC meeting had been convened in September 2012, to which
municipalities that consistently achieved a clean audit; municipalities that
consistently failed to submit Annual Financial Statements and municipalities
that had shown significant improvement, had been invited. This had been in order
for them to share with MINMEC what issues needed to be looked at, and for
MINMEC to refine the action plan accordingly. From this engagement it had
become clear that the key drivers for clean administration, leading to good
financial management, included the following:
·
The leadership take ownership of key controls.
·
Audit recommendations are consistently implemented.
·
Governance structures (
MPACs
,
finance portfolio committees, audit committees, internal audit units and risk
management committees), are functional.
·
An action plan is developed and properly implemented.
·
There are proper financial management skills.
·
Record keeping is good.
At
the same time, the following factors that negate the achievement of a clean audit
had been identified:
·
Lack of ownership by political leadership and management.
·
Lack of financial management skills.
·
Repeated findings are not addressed properly.
·
Non-availability of critical staff during the audit process.
·
Non-functional governance structures.
3.6
Support to municipalities
CoGTA
reported that they had already taken steps to support
municipalities in the areas of governance and leadership, fighting corruption,
and financial management.
3.6.1
Governance and leadership
According
to
CoGTA
, they had supported the appointment of municipal
managers and chief financial officers (
CFOs
). They
reported that 219 out of 278 municipal manager posts and 278 CFO posts had been
filled by the end of September 2012. In addition, draft regulations for
municipal senior managers had been developed, governing the appointment and
conditions of service of municipal managers and section 56 managers. These
regulations had been tabled at the MINMEC of 16 September 2012 and consultations
pursuant to the MINMEC decisions were being finalised.
CoGTA
further reported that it had supported municipalities in
developing and implementing recruitment and retention strategies. Work was
being conducted in a pilot municipality, with the intention to roll it out to
69 municipalities.
CoGTA
had also supported
municipalities to develop technical skills and in this regard, two human
resources officials from 35 municipalities had attended a three day programme
hosted by the
CoGTA
indicated that guidelines on the establishment of Municipal
Public Accounts Committees (
MPACs
) had been put in
place and they had also supported the establishment of
MPACs
.
CoGTA
also monitored governance structures such as Audit
Committees and Internal Audit Units. They reported that, although 79 per cent
of municipalities had established Internal Audit Units.
CoGTA
reported that these units may not meet the Office of the Accountant-Generals
desirable maturity levels.
3.6.2
Fighting corruption
CoGTA
reported that they continued to train municipal officials
on ethics management and that the following district (DM) and local
municipalities (LM) had been trained and were establishing ethics committees:
·
Cacadu
DM (
Koega
LM,
Makana
LM,
Kougama
LM,
Camdeboo
LM);
·
Alfred Nzo DM (Matatiele LM, Umzimvubu
LM);
·
OR Tambo DM (Mhlontlo LM, Nyandeni LM,
Ngquza Hill LM, King Sabata Dalindyebo LM); and
·
Overberg
DM (
Mosselbay
LM).
3.6.3
Financial management
CoGTA
reported that they had supported 39 municipalities in
4. Municipal Infrastructure Support
Agency
4.1 Background
The acting Chief Executive Officer (CEO) of the Municipal Infrastructure
Support Agency (MISA) reported to the Committee that MISA was one of the Local
Government Turnaround Strategy (LGTAS) targets meant to introduce a turnaround
mechanism in dealing with the provisioning, refurbishment and maintenance of
municipal infrastructure. MISA had officially been proclaimed as a government
component on 11
May 2012, with
CoGTA
as
its principal department. Prior to this,
CoGTA
had piloted
the implementation of MISA and its programmes through a unit within the
Department called the Special Purpose Vehicle for Infrastructure Development
Unit.
The acting CEO further reported
that MISA became the direct successor in responsibility to the support
programme that the Development Bank of Southern Africa (DBSA) had been
providing through the
Siyenza
Manje
project. In 2011 government had taken a decision to unbundle
Siyenza
Manje
, with the
infrastructure component transferred to
CoGTA
and the
financial management component transferred to National Treasury.
4.2 Strategic
focus
The acting CEO reported that
CoGTA
had taken
into account the lessons to be learned from the implementation of
Siyenza
Manje
,
identified in both the
Siyenza
Manje
Evaluation Report and the submission by the Financial
and Fiscal Commission to the Select Committee on Finance. In light of these,
the following five key strategic focus areas had been identified:
4.2.1
Municipal Infrastructure
Diagnosis
This was a scientific and in-depth assessment of the
state of the municipal infrastructure required for the provision of water, sanitation,
roads,
electricity
and refuse removal services.
4.2.2
Technical Support
This entailed providing specialised technical support to municipalities
through the deployment of technical experts to develop master plans,
feasibility studies, business plans, as well as the design and implementation
of infrastructure projects.
4.2.3
Municipal Capacity
Development
This involved the building and/or strengthening of the in-house capacity
of municipalities to be able to develop, operate and maintain their infrastructure
on their own in the medium to long term.
4.2.4
Sector capacity and
skills development interventions
This referred to interventions designed to enhance the technical
capacity of local government. These include skills development programmes such
as bursaries,
learnerships
and internships for
infrastructure development as well as partnerships with tertiary institutions
and professional bodies.
4.2.5
Monitoring and Evaluation
This involved specialised technical experts
undertaking the monitoring of the development, management and maintenance of
the municipal infrastructure to ensure enhanced and sustainable delivery of
municipal services.
4.3
Diagnosis and findings
The
acting CEO reported that
a total of 88 municipalities had been subjected to a
diagnosis to evaluate their municipal infrastructure provisioning. These
municipalities had been identified in conjunction with provincial governments
using the following criteria as a basis for
prioritisation
:
·
High infrastructure and basic services backlogs;
·
Low technical capacity;
·
High vulnerability; and
·
Low economic base and/or inability to collect revenue.
The
acting CEO reported that, although findings had differed from one municipality
to the next, the following common findings had been identified:
·
Lack of appropriate skills in planning and technical
units for infrastructure maintenance.
·
Absence of infrastructure master plans.
·
Overloaded infrastructure requiring refurbishment
(especially waste water treatment plants).
·
Ageing
infrastructure
leading
to service interruptions.
·
Serious challenges in supply chain management
processes when procuring infrastructure projects as well as in contract
management.
·
Lack of infrastructure maintenance (water, sanitation,
roads, electricity, land fill sites).
·
Lack of bulk infrastructure (water, sanitation, roads,
electricity, land fill sites).
·
Huge infrastructure backlogs.
·
Insufficient government funding and a need for MISA to
support municipalities to mobilise additional private sector funding for
infrastructure projects.
·
High vacancy rate in technical positions.
He indicated that MISA had learned the following lessons from the above
findings:
·
There was a need for central and effective
coordination of support in order for the programme to succeed.
·
Multi-year planning was a key instrument for
infrastructure delivery.
·
MISAs
programmes
must focus on the sustainability of the infrastructure and the municipality.
All
MISAs
interventions must
recognise
the central role of skills development and capacity building.
·
All
MISAs
support
programmes must have clear deliverables and milestones and there must be
consequences for non-delivery.
4.4 Interim
arrangements
The acting CEO reported that, apart from himself - who was a directly
appointed employee of MISA - and two senior officials seconded from COGTA, MISA
was staffed with short-term transferees and employees of the DBSA, whose contracts
would end by the end of September 2012. Included in the DBSA transferees were 81
technical experts in the fields of engineering and planning. This situation
would allow MISA to
finalise
its organisational
development and policies. According to the acting CEO, full implementation was
targeted for 7 September 2012.
The 2012 Medium Term Expenditure Framework provided a total
amount of R613 million for MISA, and was distributed as follows:
·
R197 million (2012/13);
·
R202 million (2013/14); and
·
R214 million (2014/15).
5. Findings
During
interaction with the Department of Cooperative Governance and Traditional
Affairs and the National Treasury the Select Committee on Appropriations made
the following findings:
5.1
There is no capacity within provincial departments to
implement the plan presented by
CoGTA
.
5.2
There is a need for
CoGTA
and
MINMEC to jointly monitor the implementation of the action plan.
5.3
There is a need for a local government fiscal framework
summit to clarify local government fiscal policy.
5.4
There is a long turnaround time to fill strategic positions
in municipalities such as municipal managers and chief financial officers
positions.
5.5
CoGTA
has no clear strategy to deal with
the lack of capacity within municipalities and provincial departments.
5.6
There is a need to analyse the correlation between the
improved audit
outcomes
and
failure to submit audited financial
statements in time or not at all. While clean audit improved from 0.3% in
2008/09 to 5% in 2010/11, financially unqualified remain at 41% and financially
qualified increased from 42% to 46%; the failure to submit audited financial
statements incidences increased from 0.3% in 2008/09 to 3% in 2010/11 and
outstanding audits increased from 0.3% in 2008/09 to 6% in 2010/11.
5.7
There is a need for
CoGTA
to
specify the number of seconded officials to MISA and places where they are
stationed.
5.8
CoGTA
is silent on non-compliance with
the MFMA which is a general cause of negative audit opinions in most
municipalities.
5.9
CoGTA
over-emphasised the establishment
of certain structures such
as
municipal public accounts committees (
MPACs
) rather than
their performance.
Analysis of the facts do not show
any positive correlation between the
establishment
of such structures and
improved audit opinions and that casts
doubt
on the effectiveness of
such structures.
5.10
The Departmental rapid response team that used to do such
good work is no longer active.
5.11
There is a need to assess the viability of certain
municipalities.
5.12
There is a need for the Committee to call all
CoGTA
MECs
during the in-year
monitoring of the plans by municipalities to address audit queries.
5.13
The majority of municipalities continue to rely on
consultants.
5.14
The lack of progress in municipalities receiving disclaimer
and adverse audit opinions casts doubt on the value for the money spent.
5.15
There are some duplications of support to municipalities by
various stakeholders.
5.16
The target of clean audits for all municipalities by 2014
will not be achieved.
6. Recommendations
After
interaction with the Department of Cooperative Governance and Traditional
Affairs and the National Treasury, the Select Committee on Appropriations
recommends the following:
6.1
The Department of Cooperative Governance
and Traditional Affairs should conduct a skills audit in provincial departments
to assess the extent of the lack of capacity within provincial departments.
6.2
The Department of Cooperative Governance
and Traditional Affairs and MINMEC should develop a joint strategy to monitor
the implementation of the action plan.
6.3
The Department of Cooperative Governance
and Traditional Affairs should facilitate the planned local government fiscal
framework summit to clarify the local government fiscal policy.
6.4
The Department of Cooperative Governance
and Traditional Affairs should ensure that the turnaround time to appoint
municipal managers and
CFOs
is minimised.
6.5
The Department of Cooperative Governance
and Traditional Affairs should come up with a clear strategy to deal with the
lack of capacity within municipalities and provincial departments.
6.6
The Department of Cooperative Governance
and Traditional Affairs should ensure that failure to submit financial
statements for audit is taken seriously.
6.7
The Department of Cooperative Governance
and Traditional Affairs should provide the Committee, in writing, with the
number of seconded officials in the Municipal Infrastructure Support Agency (MISA)
and also the places they are located, within two months of the adoption of this
Report by the NCOP.
6.8
The Department of Cooperative Governance
and Traditional Affairs should ensure that steps are taken against failure to
comply with applicable legislation since such incidences are the main causes of
wasteful and fruitless expenditure and corrupt practices.
6.9
The Department of Cooperative Governance
and Traditional Affairs should not only focus on compliance with the establishment
of certain structures but also on their functionality as well as effective
leadership.
6.10
The Department of Cooperative Governance
and Traditional Affairs should revive the rapid response team that was
established when Operation Clean Audit was introduced.
6.11
The Department of Cooperative Governance
and Traditional Affairs should provide clarity on what constitutes viability so
as to guide future municipal demarcations.
6.12
The Committee will in future invite the
provincial
CoGTA
MECs
during the in-year monitoring of municipalities compliance with audit queries.
6.13
The
Department of Cooperative Governance and Traditional Affairs should develop a
strategy that will minimise the use of consultants by municipalities and where
consultants are used, there is transfer of skills.
6.14
The
Department of Cooperative
Governance and Traditional Affairs should prioritise municipalities with
disclaimer and adverse audit opinions for intervention.
6.15
The Department of Cooperative Governance
and Traditional Affairs should ensure that there is proper coordination of all
the interventions in municipalities to avoid any duplication of support.
6.16
Due to the consistent criticism by the
Auditor-General about the poor quality of Annual Financial Statements submitted
by municipalities for auditing, the Department of Cooperative Governance and
Traditional Affairs should re-evaluate the 2014 Operation Clean Audit target
because it is not possible to achieve.
Report
to be considered.
Documents
No related documents