SUMMARY
The Department of Public Works met with the Committee to present detail on the
key programmes of the Department and the various directorates. Service delivery
would be improved and state properties would be managed in a more effective
manner. Policy initiatives were outlined and important aspects of the overall
strategy explained.
Members asked various questions including on payment for consulting engineers,
the Department’s contribution to the Expanded Public Works Programme, the need
to improve the public tender process, enhanced implementation at the provincial
and local level, the disposal of state immovable assets, the nature of skills
training programmes, preparations for the 2010 World Cup and the need to
improve intergovernmental relations.
MINUTES
Department of Public Works presentation
Ms L Bici (Deputy Director-General-Policy
Development) provided detail on the Department’s core business areas and the
Chief Directorates. The value plan was outlined that strove to improve service
delivery, enhance capacity and promote asset management. The Department would
support the Accelerated Shared Growth Initiative of South Africa through its
various programmes. Detail was provided on the Department’s strategic
initiatives and the Service Delivery Improvement programme. Policy initiatives
were outlined including transformation of the property and construction
industries and the asset disposal strategy. The Department’s contribution to
the Expanded Public Works Programme (EPWP) was explained.
Discussion
Mr Adams asked whether consultant engineers received 18% of the total project
cost in fees. He asked whether the R2 million for the maintenance of the
parliamentary precinct facilities was included in the R73 million budget. Clarity was sought on a plan to expand the urban
redevelopment project to other cities. R33 million for the contribution to EPWP
appeared to be minimal. The Department had to communicate with municipalities
and form partnerships to drive EPWP. He asked whether asset registers had been
completed and sought clarity on the number of long-term leases in existence.
The public tender process had to become more efficient and under-utilised
assets should be disposed of. The Department’s contribution to emerging
contractors was requested.
The Chairperson noted that the Department had to focus on provincial and local
government in order to fulfil its constitutional mandate. The presentation
should include specific information derived from the provinces such as the
number of emerging contractor incubators and gender and youth programmes. A
progress report on the implementation of the EPWP was required. Individual
success stories with regard to skills enhancement should be recounted. He asked
where existing incubators were situated. Clarity was sought on the process to
dispose of state immovable assets. Skills training programmes had to have clear
exit points based on the standard of training achieved to enable recipients to
operate independently.
Ms H Matlanyane (ANC) commented on the poor quality
of the Members’ official residences and asked whether maintenance could be
improved. She asked for a breakdown of the disposal of property per province.
Ms Bici stated that the nature of the presentation
would be improved in future with more pertinent detail provided. Key programmes
would be highlighted. A database of emerging contractors had been established
based on a list of criteria. Contractors worked on projects ranging in budget
from R1 million to R30 million. Contractors would serve a period of three years
on the database before operating independently. Contractor incubators were
positioned throughout the country. Contractors involved in fronting would be
removed from the database. The regeneration project had been initiated in Tshwane as the administrative capital of South Africa.
Irregularities in the public tender process were being investigated. The
Department’s Portfolio Analysis Unit investigated the use of state-owned
properties and determined whether disposal should occur. Many buildings were in
a dilapidated state and were surplus to government needs. Checks and balances
were in place to oversee the process and prevent corruption. A public tender
process advertised the sale of assets. Tenders went before the Department’s
Tender Committee for evaluation and then to the Director-General for approval.
The Minister granted the final approval.
Mr Z Ntsaluba (Chief Financial Officer) confirmed
that consultants received 18% of the total project’s value as a fee. The R2
million for the maintenance of the Parliamentary precinct was included in the
R73 million total budget. Intergovernmental relations
between the Department and the provincial and local government sectors could be
improved. The condition of housing for Members would be investigated.
Ms Bici declared that external consultants had to be
employed as the placing of such skills in the Department would be too costly.
The use of consultants also aligned the Department’s projects with industry
best practice. The asset register captured key information including size of
property, cost, current use etc. Illegal occupiers of state property would be
identified and asked to vacate the premises. Information on long-term leases
would be made available to Members. Currently, R1.4 billion was leased from the
private sector. A study had concluded that a combination of leases and state
owned property was the cost-effective approach to accommodation needs.
Mr M Lieuw-Kie-Song (EPWP) stated that the R33
million budgeted for EPWP was for technical support and not for implementation
of projects. A project management unit within the Department communicated with
provincial and local government on the EPWP. Technical support was provided to
the provinces. Provincial steering committees were in place in all provinces.
EPWP coordinators were in place in the major cities. Technical support to
municipalities would be co-ordinated. Various projects were in place with
provincial governments to drive the EPWP such as contractor-learnership
programmes. The list of participating municipalities would be forwarded to the
Committee.
Ms Bici stated that a disposal strategy for
properties was in place to assist Black Economic Empowerment and skills
development. The strategy had been submitted to Cabinet. Discussions were
taking place with financial institutions to make funding available for Black
landlords.
The Chairperson noted that a similar response had been made in 2004 but the
Department continued to struggle to generate suitable levels of co-operation in
the provinces to national initiatives. He asked what steps the Department could
take to heighten support at the provincial and local level.
Mr Ntsaluba stated that a relative autonomy existed
at the provincial level in terms of public works and infrastructure that
complicated matters. However, co-operation did occur between the spheres of
government.
Ms Bici responded that the Department did exercise
influence at the provincial level. The service delivery programme would be
implemented to improve the Department’s impact at the local level. Liaison with
provincial governments would be conducted to enhance co-operation and ensure
implementation of legislation.
The Chairperson reiterated that the Department had to adopt a hands-on approach
in the provinces. He asked whether the Department assisted the Departments of
Correctional Services and Water Affairs and Forestry in terms of infrastructure
development. He asked about preparations for the 2010 World Cup.
Mr Ntsaluba stated that the Director-Generals of the
various Departments had to account for expenditure of allocated amounts as the
budget for the EPWP had been devolved. The building of dams was the sole
responsibility of the Department of Water Affairs and Forestry. The Department
assisted with the costing for the building of prisons for Correctional
Services. The costs had increased since the budget had been finalised and a
reduced number of prisons would now be constructed. Interaction with the
Department of Sport and Recreation would occur with regard to the World Cup.
The meeting was adjourned.