Report of
the Select Committee on Appropriations on the oversight visit to
1.
Introduction
The Select Committee on
Appropriations (the Committee) was established in terms of section 4(3) of the
Money Bills Amendment Procedure and Related Matters
Act, No 9 of 2009 (the Act). In terms of section 4(4) of this Act, the Committee
has the powers and functions conferred to it by the Constitution, legislation,
the standing rules or a resolution of a House, including considering and
reporting on:
Furthermore, the mandate of the
Select Committee on Appropriations encompasses the Committee’s functions to
legislate, conduct oversight of the Executive; promote public participation,
facilitate international agreements and review matters of public interest in
relation to National Treasury and its entities, and the South African Reserve
Bank.
1.1
Overview
The oversight visit took place on 19
August 2011. A meeting to brief the Committee about the Project was held at
1.2 Terms
of reference
The visit formed part of the
Committee’s ongoing interaction with provinces on their expenditure on
conditional grants.
The oversight visit emanated from
the Hospital Revitalisation Grant (HRG) first quarter expenditure submissions
of the 2010/11 financial year made to the Committee on 19-20 October 2010. During
the deliberations, the provincial Departments of Health raised a number of
challenges that contributed to the under-spending of the HRG allocation. Among
other things, was the appointment, by the provincial Departments of Public Works,
of under-performing contractors; poor construction work by contractors; and
late payment of contractors.
1.3 Purpose
of the Visit
The purpose of the oversight visit
was to achieve the following:
2. Submission
by the department
The MEC of Health, Hon Fezi
Ngubentombi, welcomed the Committee to
Due to prior
commitments, the MEC left and the HOD, Dr Sipho Kabane andhis team made a
presentation on the progress of Pelonomi Hospital Revitalisation Grant project to
the Select Committees. The Department reported, in October 2010, that
expenditure on the Hospital Revitalisation Grant amounted to R22.5 million (i.e.
20 per cent) of the adjusted budget amount of R111.0 million.
With respect
to the progress made on the projects, the Department submitted that it had the
initial contractor was underperforming and as a result it was removed from
site. A new contractor, Shabach
Construction, recommended by the Professional Consultant was then appointed.
The Department
reminded the Committee that the following challenges were noted:
·
Under expenditure of the grant;
·
Poor contract management;
·
Lack of appropriate skills to manage
infrastructure projects; and
·
Late appointment of contractors.
The Department went further to
report that to address the above challenges, the following interventions were
made:
·
Appointed three engineers to improve
contract management and planning.
·
Established a forum between themselves
and the Department of Public Works to improve the management of Revitalisation projects.
·
Bilateral meeting at an Executive
level were also conducted.
·
Issued a Mora letter (warning
letter) to a poor performing contractor to move off site if the contractor
causes any further delays to the project.
The
interventions led to improved communication and collaboration between the two Departments.
It further improved the quality of the Pelonomi Hospital Revitalisation project
management.
As of the 30
June 2011, the province has spent R21.3 million (35 per cent) of the allocated
budget of R61.0 million for the 2011/12 financial year.
2.1
The Department submitted that the Pelonomi
Hospital Revitalisation Project is made up of four subprojects. That is Pelonomi
Intensive Care Unit, Pelonomi Radiology upgrade, Specialised Clinics (Out
Patient department)/Casualties, New entrance and perimeter fence.
|
Project name |
Allocated budget for 2011/12 |
First quarter expenditure |
Percentage spent at first quarter |
Physical progress to date |
Projected % stage of project |
|
|
R’ 000 |
R’ 000 |
% |
% |
% |
|
Pelonomi ICU |
35 |
5.3 |
15 |
22 |
56.7 |
|
Pelonomi radiology Upgrade |
8 |
6.9 |
87 |
97 |
100 |
|
Specialised Clinics (Out Patient
Department)/ Casualties |
10 |
8.8 |
88 |
100 |
100 |
|
New Entrance and Perimeter Fence |
8 |
0 |
0 |
100 |
100 |
|
Total |
61 |
21 |
34% |
- |
- |
The Committee was informed that the
progress of the project was very slow and the contractor’s performance and quality
of work on the site was poor. The floor screed had to be redone, more than four
times. This was as a result of poor quality plaster being used to make the
floor screed, which had to be removed. The project was further delayed by a
disagreement between the contractor and the department’s consultant on the
project. The Department also reported that at some stage the contractor
abandoned the site and when the contractor returned stringent terms were put in
place.
At the time of the Committee’s visit,
the specialised clinic called (OPD)/Casualties was at a planning stage, of
which 88 per cent of the planning work has been completed. The procurement
process of the New Entrance and Perimeter Fence project was still in the early
stage as the tendering process was closed on 05 August 2011.
3. Challenges at the
The Committee was informed that there
were serious delays with the appointment of the contractor for the Intensive
Care Unit. As a consequence to that the ICU machinery has not been procured. After
the contractor had been appointed, there were problems with pace of work, poor
workmanship in some areas and a lack of supervision. The Department reported
that for the sub-project: Radiology, Clinical Engineering and Links, the
contractor was behind schedule. However, the Department is adamant that the
project will be finished on schedule.
The Committee was informed that following
interventions by the Departments of Public Works and Health the progress on the
whole project has improved tremendously.
The Department
submitted to the Committee that the Pelonomi Hospital Revitalisation project
was 6 months behind schedule. On the other hand, the Consultant reported that
the project might be finish in February 2012 but the department was adamant
that it will be complete before end of 03 November 2011. The Department
reported that the Penelomi Hospital Revitalisation Project would be completed
by 3 November 2011; however the consultant raised doubts about the contractor’s
ability to meet this deadline and stated a more realistic date would be
February 2012.
4. Site
Visits
The management of the Department,
and the consultant, Goldblah Yuill Architects (represented by Mr J Van der
Merwe), led the Committee on a site visit to the following sub-projects:
The Department reported that they
had received state of the art equipment but their challenge was that the hospital
is under-staffed. To overcome this challenge, the staff needs to be trained on
how to use the new equipment. The Department added that retaining competent
staff is a challenge due to competition with the private sector. Hospital
management reported that they have observed a concerning trend in terms of black
student enrollments in the Health Faculty of the University of Free State that
do not complete their degrees.
The Department proceeded with the
Committee to the Trauma and Spinery Unit that will be installed
with Magnetic Resonance Imaging (MRI)
equipment, which will amount to about R15 million. Due to the slow progress on
the implementation of the project, the equipment cannot be purchased at this
stage.
.5. Observations
5.1 The main challenge on the
Pelonomi Hospital Revitalisation project lies with the underperforming
contractor, who needs to be closely monitored.
5.2 Abandonment of the project by
the contractor, which was appointed without the involvement of a professional
consultant, and the contractor’s work which was below the required standard are
the two major factors that contributed to a delay of this project.
5.3 There are signs that the main
contractor has cash flow challenges. This is due to the fact that progress is only
made once the department has made payments to the contractor.
5.4 The Committee found it
concerning that the Department was not taking the recommendations of the
consultant seriously as the consultant was being paid by the department for his
expert advice. This could be viewed as wasteful expenditure.
5.5 The Committee noted that the management
of the Department was not in touch with the project. The Committee is of the
opinion that too much trust is being placed in an underperforming contractor,
thus undermining the purpose of the consultant.
5.6 The project is progressing but
at a very slow pace. Regarding the completion date, the Committee agrees with
the consultant that the project will most likely be completed around February
2012.
6.
Recommendations
The Select Committee on
Appropriations makes the following recommendations:
6.1 The consultant, Goldblah Yuill Architects, should
closely monitor quality of work the contractor, Shabach
Construction, and the Department should have more supportive of
the consultant;
6.2 The
6.3 The
Report to be
considered.