Budgetary Review and Recommendation Report of the Portfolio Committee on Public Works on the Department of Public Works for the 2010/11 financial year, dated 20 October 2011.

 

The Portfolio Committee on Public Works, having considered the relevant reports and the Annual Report of the Department of Public Worksfor 2010/11, reports as follows:

 

1.                   Introduction

 

The Budgetary Review and Recommendation Report of the Portfolio Committee on Public Works arises from the fulfillment of the requirements of the Money Bills Amendment Procedure and Related Matters Act (No. 9 of 2009), which was signed into law on 16 April 2009. The aim of the Act is to provide for a procedure to amend money bills before Parliament and for norms and standards for amending money bills before provincial legislatures and to provide for related matters.

 

Following from the above, the report will outline progress made by the Department of Public Works as reported in the different reports, including the Strategic Plan, section 32 reports and the 2010/11 Annual Report of the department as well as the Auditor-General’s opinion in the Department’s 2010/11 Annual Report.

 

1.1        The mandate and role of the Committee

 

The Portfolio Committee on Public Works is guided by the Rules of Parliament and  the Constitution to play an oversight role over the Ministry, the Department of Public Works and its entities. In doing so, the Committee:

 

·         exercises its monitoring role in such a way that it contributes towards the improvement of the quality of life of all South Africans;

·         scrutinises legislation and other policies that impact on the spheres of Public Works;

·         facilitates interdepartmental and intergovernmental relationships at all spheres of government;

·         transforms the conduct of the Committee’s business to be sensitive to provincial interests at the national level;

·         learns to understand other international best practices relevant to its field of jurisdiction to serve all South Africans to its best.

 

1.2               The mandate of the Department

 

The Department of Public Works was allocated a functional mandate in terms of the Constitution of the Republic of South Africa. The Department is mandated to:

 

·         provide land and accommodation to national government departments and institutions;

·         manage such land and accommodation;

·         act as the custodian of national government’s immovable assets;

·         provide strategic leadership to the construction and property industries;

·         co-ordinate the implementation of the Expanded Public Works Programme;

·         have the Minister of Public Works carry out functions related to land and accommodation through the State Land Disposal Act (No. 48 of 1961).

 

The Department is also responsible for four entities that report to the Minister of Public Works as the executive authority. These entities comprise:

 

·         Agrèment South Africa;

·         Construction Industry Development Board (CIDB);

·         Council for the Built Environment (CBE);

·         Independent Development Trust (IDT).  

 

2.         Strategic Priorities and Measurable Objectives of the Department

 

   2.1        Strategic Priorities

 

2.1.1 The Department has identified the following six strategic goals:

 

a)       Providing strategic leadership for effective and efficient immovable asset management and in regard to the delivery of infrastructure programmes.

b)       Promoting an enabling environment for the creation of both short and sustainable work opportunities to contribute to the national goals of job creation and poverty alleviation.

c)       Contributing to the building of a developmental state and a comprehensive rural development framework through State assets.

d)       Ensuring transformation and regulation of the construction and property industries to ensure economic growth and development.

e)       Ensuring effective corporate governance and sound resource management.

f)         Ensuring improved service delivery in all departmental programmes to meet clients’ expectations and leverage stakeholder relations.

 

2.2        Measurable Objectives

 

Five critical programmes determine the work of the Department. Within each of the programmes, the Department identified a number of measurable objectives which are shown below per departmental programme:

 

Programme 1: Administration

 

2.2.1     Provide strategic leadership and support services, including the accommodation and overall management of the Department.

 

This programme reports on a number of sub-programmes related to support services, accommodation and management of the Department. This section will highlight the performance of the Department in meeting its targets, as well as its challenges.  

 

2.2.2     Finance and Supply Chain Management

 

The following targets were reached or exceeded:

 

a)       Due to the improved revenue and debtor management the Property Management Trading Entity (PMTE) achieved (62 per cent of planned 50 per cent reduction in the debtors book) by R1.3 billion of an estimated R2 billion. 

b)       Collected (97 per cent of a targeted 80 per cent in revenue) on invoices issued during the period under review.  

c)       Achieved (set target of 90 per cent compliant by 31 March 2011) for the improve management of moveable assets by a credible Asset Register.

d)       Improved Supply Chain Management with (82.7 per cent of a targeted 80 per cent compliance) with Service Level Agreements (SLA).    

 

The following targets were not met:

 

a)       Delays in the acquisition of financial systems meant 7 of 16 action plan outputs were achieved (44 per cent of targeted 70 per cent). Action Plans implemented to ensure Generally Accepted Accounting Principles (GAAP) compliance by the PMTE.

b)       Improved internal controls with 7 policies and procedures (80 per cent of targeted 90 per cent) developed and/or reviewed for implementation. 

c)       Accredited 16.2 per cent of a targeted 80 per cent of the Department’s suppliers.

 

2.2.3     Corporate Services

 

The following targets were reached or exceeded:

 

a)       Implemented the EPWP Web-Based System.

b)       Completed Virtual Private Network and is operational.

 

The following targets were not met:

 

a)       A total of 78 out of an annual target of 180 employees were vetted due to delays by the National Intelligence Agency (NIA) in terms of its internal processes in concluding the vetting process.

b)       A total of 413 out of an annual target of 1 000 companies were vetted, cleared and incorporated into the database. The process is dependent on a request from clients for clearance of service providers.  

 

2.2.4     Internal Audit and Investigation Services

 

The following targets were reached or exceeded:

 

a)       Improved compliance with all prescripts (92 per cent of targeted 80 per cent) audit reports.

b)       Risk assessment and meetings with functional Audit Committee of which 76 per cent of Audit Plan was implemented.

 

2.2.5     Strategic Management Unit

 

The following targets were reached or exceeded:

 

a)         Enterprise Risk Strategy was approved and presented to the Audit Risk Management Committee.

b)         All Risk Registers (at head office and in the regions) had been prepared and reviewed to only reflect critical risk issues for 2011/12 and appointments had been scheduled with all business units for risk assessment revision.   

 

The following targets were not met:

 

a)         Completed monitoring of high Risk Registers by reviewing and updating head office branches (Finance and Supply Chain Management; Policy and EPWP) and visited Kimberley, Mmabatho and Durban regions and monitored risks in preparation for 2011/12 assessments. The Bloemfontein region was not monitored due to the unavailability of managers.

 

2.2.6     Intergovernmental Relations and Parliamentary Services

 

The following targets were reached or exceeded:

 

a)       Co-ordinated 32 of a targeted 8 intergovernmental relations and other relate meetings.

b)       Effective management and facilitation of meetings between the Minister of Public Works and the entities, including the conclusion of the appointment of board members of Agrèment South Africa, CBE and CIDB.

 

2.2.7     Monitoring and Evaluation

 

The following targets were met:

 

a)       Finalised and approved the Monitoring and Evaluation Policy/Framework. In process of internal consultations. 

b)       Compliance with reporting requirements (80 per cent of targeted 80 per cent) of Monitoring and Evaluation policy with the conclusion of consultative workshops with branches and business units.

c)       Reported that performance reports were being submitted quarterly to the Department which, in turn, submitted them to National Treasury, Auditor-General and presents to Parliament.   

 

Programme 2: Immovable Asset Management

 

2.2.8     Provide and manage Government’s immovable property portfolio in support of Government’s social, economic, functional and political objectives.

 

The successes and challenges under the different sup-programmes are listed below, highlighting targets that were achieved or exceeded and those that were not met. The Department reported on the Asset Register as follows: 

 

Table 1: Immovable Asset Register as at 1 April 2010 to 31 March 2011

Asset

Opening Balance 1 April 2010

Disposal/(Archived)/Recon

Closing Balance 31 March 2011

Land Parcels

36 257

(362)

35 895

Dwellings

33 233

(177)

33 056

Non-Dwellings

42 014

(1 672)

40 342

Total

111 504

(2211)

109 293

 

The Asset Register consists of 35 895 land parcels and 73 398 buildings and structures vested in the national Government and falling under the custodianship of the Department of Public Works. The Asset Register also includes Defence Endowment Properties.

 

The following targets were reached or exceeded:

 

a)       Completed approval and implementation of National Vesting Plan.

b)       Completed approved Amnesty Call Strategy and Campaign.

c)       A 10 per cent of a targeted 2 per cent reduction in kilolitre water consumption in state-owned buildings.

d)       A total of 121 of targeted 64 buildings were identified and made accessible.

e)       A total of 1 031 of a targeted 1 000 hectares of land parcels were released for human settlement purposes.

f)         Compiled a total of 86 per cent of a targeted 50 per cent requests for new market valuations.

 

The following targets were not met:

 

a)       Populated Asset Register fields with (82 per cent of targeted 90 per cent) with essential information. Target not reached due to improvements for essential information being concentrated on properties that were confirmed as belonging to national Government.

b)       Project to include 10 per cent supplementary information in Asset Register fields was placed on hold due to priority given to the minimum requirements of the Auditor-General’s findings.

c)       A total of 35 per cent of a targeted 55 per cent of land parcels wasvested and the Department was in the process of aligning its statistics with those of the Department of Rural Development and Land Affairs.

d)       A total of 16 of 34 Service Level Agreements (SLA) have been signed by user departments.

e)       Inadequate resources resulted in the developed (59 per cent of targeted 70 per cent) property portfolio strategies.

f)         Developed (45 per cent of targeted 70 per cent) Client Asset Management Plans due to inadequate resources.

g)       Approval and implementation of investment strategy to increase revenue of State leased properties by 10 per cent has not been completed.

h)       A total of 6 of the targeted 20 foreign properties were disposed, which are subject to release of approval by the Department of International Relations and Cooperation (DIRCO).

i)         Ministerial approval for disposal of 14 properties for commercial purposes not completed with 25 properties still in approval process.

j)         A total of 34 of targeted 55 properties were disposed for land reform purposes with an additional 21 in approval process.

k)       Completed (76 per cent of targeted 80 per cent) annual project investment analysis due to inadequate resources.

l)         Negotiations and appraisals of 50 per cent annual municipal valuations calendar not completed due to inadequate resources.

 

The Department also highlighted the large maintenance backlog (which quantified the costs of improving the physical work environment), based on a consultant’s report dated June 2006. The Department estimated that for 2006 the backlog stood at approximately R24.3 billion which increased to R35.6 billion allowing for a 10 per cent escalation to date. The reported figures of the maintenance backlog could not be verified as they were not supported by technical condition assessments. In addition, not all the buildings were included in the assessment. It should also be noted that the Department reported in its 2009 Annual Report that by 2009 the maintenance backlog had risen to R16.6 billion from the 2007 estimate of R13.7 billion. If the backlog stood at 24.3 billion in 2006, what is the reason for its reduction in 2007 and 2009?

 

Funding had been requested from National Treasury to address the large maintenance backlog, and the Department planned to prioritise condition assessments for 2011/12. The current practice is to undertake maintenance on a reactive basis which resulted in over expenditure on planned and unplanned maintenance. In addition, the Department planned to complete Condition Asset Management Plans by March 2012. 

 

For the 2010/11 financial year, the Department spent a total of R2.01 billon on planned maintenance (R1.71 billion) and rehabilitation (R303.7 million). The Department indicated that maintenance was addressed through the following three programmes; Planned Maintenance Implementation Programme, Capital Works Implementation Programme and Day-to-Day maintenance). The programmes were not linked and were therefore not integrated.

 

Programme 3: Expanded Public Works Programme

 

2.2.9     Ensure the creation of work opportunities and the provision of training for unskilled, marginalised and unemployed people in South Africa by coordinating the implementation of the Expanded Public Works Programme.

 

The department reported on progress made in terms of reaching the set target for the creation of work opportunities and full-time equivalents (FTE), annual designated groups, as well as disbursement of the wage incentive across all sectors.

 

The following targets were reached or exceeded:

 

a)       Reached 62 per cent women and 51 per cent youth of the (designated targets of 55 and 40 per cent respectively.

 

The following targets were not met:

 

a)       Created 607 612 work opportunities (set target of 600 000) exceeded by 7 612. However, it should be noted that the set target for 2010/11 was 642 000 which means that the target was not reached by 34 388 work opportunities.

b)       Created 203 690 FTE of a targeted 260 000, which means 56 310 FTE were not created.

c)       0.45 per cent of the targeted 2 per cent of people with disabilities participated in the EPWP.

d)       59 per cent of the targeted 65 per cent qualified for the wage disbursement across all the sectors. 

 

The report by the Department on the EPWP raised concerns. The programme managed to exceed the targets for the designated groups (women by 7 per cent and youth by 11 per cent). However, a number of targets were not reached, including the percentage of people with disabilities, work opportunities, Full Time Equivalents (FETs) and wage disbursement.   

 

The disbursement of the Incentive Grants to provinces and municipalities is of concern as the Department reported a low uptake of these. Of the allocated R331 million for the EPWP infrastructure incentive to provinces, (only 56 per cent) or R182.4 million was disbursed. The EPWP infrastructure incentive to municipalities had an even lower uptake with R279.6 million (or 44 per cent) of the R622.9 million being disbursed for the year under review. The Department indicated that the low uptake of these incentives at provincial and municipal levels was due to underreporting and the low level of implementation of projects utilising labour- intensive methods.    

 

 

 

 

 

Programme 4: Property and Construction Industry Policy Regulations

 

2.2.10   Promote the growth and transformation of the construction and property industries, as well as uniformity and best practice in construction and immovable asset management in the public sector.

 

The department reported on progress made and challenges experienced in terms of policies developed, plans of action implemented, as well as legislation tabled.

 

The following targets were reached:

 

a)       Developed policies undergoing consultation: (Outdoor Advertising; Letting for Commercial Purposes; Demolition).

b)       Completed and submitted submissions on the Department’s review of the chapter dealing with Residences and other relevant sections of the Ministerial Handbook.   

 

The following targets were not met:

 

a)       The approval framework and 50 per cent implementation of Action Plan was not achieved. Currently under review with extensive consultation with the Department of Cooperative Governance and Traditional Affairs regarding the approach to extend the GIAMA to the local government.  

b)       The tabling of the Agrèment South Africa Bill before Parliament not achieved due to longer than anticipated time taken in the consultation with stakeholders. The business case for the establishment of Agrèment South Africa has been developed for submission to National Treasury.

c)       The tabling of the Expropriation Bill in Parliament not achieved. The Department was in consultation with National Treasury on the review Expropriation Act of 1975. It also undertook a regulatory impact assessment to consider the possible impact of the socio-economic, good governance, costs and risks impacts of the proposed legislative intervention.

d)       The review and development of the Department of Public Works White Papers were put on hold due to resource constraints.  

 

 

 

 

Programme 5: Auxiliary and Associated Services

 

2.2.11   Provide various services, including compensation for losses on the Government-assisted housing scheme, assistance to organisations for the preservation of national memorials, managing grants for the Parliamentary Village Management Board and meeting protocol responsibilities for State functions.

 

This programme is mainly concerned with the transfer of payments:

 

a)       R15.06 million was transferred to the Commonwealth War Graves, an annual contribution to mark and maintain the graves of members of the forces of the Commonwealth who died in World Wars I and II. 

 

3.                   Analysis of Section 32 Expenditure Reports

 

This report is based on the national budgets and expenditure report of the fourth quarter for the 2010/11 financial year.

3.1        Summary of Expenditure Outcome for the year

As at the end of the 2010/11 financial year, the Department of Public Works (DPW) had spent R6.567 billion or 89.16 per cent of its total adjusted appropriation amount of R7.365 billion, as reported in the Department’s latest Appropriation Statement. Thus, savings amounting to R797.983 million or 10.84 per cent have been realised for the 2010/11 financial year. Below is a graphical representation of the expenditure outcome for the 2010/11 financial year:

Table 1: Deviations against approved budget for the year ended 31 March 2011 (R’000):

Table 2: Deviations against approved budget per economic classification

The main expenditure activity for the Department occurred under programme 2, which also constituted 70.6 per cent of the total voted appropriation for the 2010/11 financial year. However, while underspending was recorded across most of the Department’s programmes, the largest underspending for the financial year under review was recorded under programme 3, where a total of R517.829 million or 64.9 per cent of the total savings for the year was unspent at the end of the 4th quarter. This was mainly due to the non-payment of Expanded Public Works Programme (EPWP) incentive allocations to those public bodies who failed to meet the minimum quarterly performance targets in order to receive payment.  The Department recorded 100 per cent expenditure against the voted appropriation (after taking virements into account) for programme 1 while only 71.8 per cent and 87 per cent of the voted appropriation for programmes 4 and 5 respectively was spent.

3.2        Expenditure Outcome for the 4th Quarter

For the quarter under review, the Department’s expenditure amounted to R1.449 billion or 99.3 per cent of the projected expenditure of R1.459 billion for this quarter. However, over the last 3 quarters, the Department’s average spending against projected expenditure was 87.98 per cent, with significant underspending notable in the 2nd quarter where actual spending against projected expenditure amounted to 78.93 per cent. As such, there seems to have been an accelerated increase in expenditure incurred during the 4th quarter, specifically during the month of March 2011 when comparing the overall expenditure for the quarter to the average spending for the last three quarters. This is thus indicative of a “March spike”, particularly as the bulk of the overspending during this quarter took place in March as the Department accelerated its expenditure on infrastructure and the incentive payments for the EPWP were also effected during this month. During the 4th quarter, the Department experienced both faster and slower than expected spending trends as follows:

3.3               Summary of Expenditure per Programme

a)         Programme 1: Administration

During the 4th quarter, the Department incurred an overspending of 83.5 per cent under this programme. This was largely due to accelerated payments for office accommodation, which was initially slow during the beginning of the financial year, as well as expenditure incurred for consultants due to projects for computer services and immovable assets which were commissioned by the Department during this quarter.

 

b)       Programme 2: Immovable Asset Management

Overspending of 13.6 per cent was recorded for this programme during the quarter under review as a result of accelerated payments for infrastructure, specifically during March 2011. Departmental expenditure on infrastructure generally moved slowly during the course of the financial year and was also the underlying reason for the underspending recorded in previously quarters. There was also slow movement in expenditure for the energy efficiency project which is accounted for under goods and services. 

 

In an attempt to fastrack expenditure for both infrastructure and the energy efficiency project, the Department appointed the Independent Development Trust (IDT), a public entity of the Department, to implement a schools construction project in the Eastern Cape, as well as the energy efficiency project and subsequently transferred R205 million during February 2011 to the IDT to carry out these tasks. The movement of funds to the IDT also contributed to the overspending of this budget during the quarter under review.

 

c)       Programme 3: Expanded Public Works Programme

Underspending of 56.3 per cent was recorded for the Expanded Public Works Programme during the 4th quarter. The bulk of the budget for programme 3, that is about 83 per cent, comprises incentive allocations (including grants) to public bodies. However, while allocations are made against specific public bodies as part of the budget process, public bodies are required to meet certain quarterly performance targets before they can access the allocated funds. As such, during the quarter under review, the majority of public bodies failed to meet the expected quarterly performance targets and consequently no payment was effected to these public bodies, hence the significant underspending notable for the quarter. It is important to note that for the month of March 2011, an overspending of this budget was notable as the aforementioned payments to qualifying public bodies were shifted from February 2011 to March 2011.

d)       Programme 4: Property and Construction Industry Policy Regulations

During the quarter under review, a minimal underspending of 2.2 per cent was recorded for this programme. However, there was notable underspending of 32.2 per cent and 48.5 per cent during the months of January and February 2011 respectively due to the non-payment of border fence payments which were projected for January 2011 as well as slow movement in expenditure for goods and services.

e)       Programme 5: Auxiliary and Associated Services

A minimal overspending of 2.3 per cent was recorded under programme 5 for the quarter under review. The department exhausted the budget for this programme in May 2010 due to higher than expected costs incurred for the funeral of the late Deputy Minister of Health. However, in the Adjusted Estimates of National Expenditure, the department shifted funds amounting to R5 million to this programme in order to offset the shortfall in the budget.

3.4        Summary of spending trends per economic classification

When analysing the expenditure for the 4th quarter per economic classification and following from the analysis of expenditure per programme in the previous section, significant overspending of the budget is notable under current payments and payments for capital assets largely due to the following:

a)       Current Payments: accelerated payments for the Department’s accommodation-related charges and an increase in expenditure incurred for consultants due to the implementation of computer services and immovable assets projects (programme 1) and the payment of R75 million to the IDT during February 2011 for the energy efficiency project (programme 2).

b)       Payments for Capital Assets: the overspending in payments for capital assets is as a result of accelerated payments for infrastructure, which also includes a transfer of R130 million to the IDT, during the quarter under review, specifically under programme 2.

The underspending recorded under transfers and subsidies is due to the non-payment of EPWP incentives to those public bodies who failed to meet the quarterly performance targets.

3.5        Summary of spending against earmarked funds as at the end of the 4th Quarter

Earmarked Item

(R’000)

Total Appropriated

 

Total Spent for the year

% Spent Against Total Appropriated

Devolution of funds from Public Works

351 027

313 133

89.2%

Infrastructure (Public Works, including BCOCC)

1 375 982

1 255 873

91.27%

Construction Industry Development Board (cidb)

63 665

63 665

100%

Council for the Built Environment (CBE)

25665

25 665

100%

Energy efficiency  in government buildings

75 000

75 000

100%

Non-State sector (EPWP)

179 811

179 811

100%

Independent Development Trust (EPWP)

10 515

10 515

100%

EPWP incentive grant to local government for the Infrastructure Sector

622 996

279 642

44.9%

EPWP incentive grant to provinces for the Infrastructure Sector

331 004

182 406

55.1%

Devolution of Property Rate Funds Grant to provinces

1 865 227

1 865 227

100%

Expanded Public Works Programme incentive grant to provinces for the Social Sector

56 637

56 637

100%

 

4.         Analysis of the Department’s Annual Report and Financial Statements

 

The Department received a disclaimer with emphasis of matter and additional matter from the Auditor-General for the period under review. 

 

4.1        Report by the Auditor-General on the performance of the Department

 

The basis for the disclaimer of opinion is as follows:

 

4.1.1     Immovable Tangible Capital Assets

 

a)       The Auditor-General was unable to obtain sufficient and appropriate evidence of the completeness, existence, rights, valuation and allocation of properties recorded in the Immovable Asset Register of the Department stated at R3.49 billon.  

b)       Corresponding figure for immovable assets has been reduced by R6.09 billion to address a prior year misstatement, without any supporting documentation. The Auditor-General was therefore unable to obtain sufficient appropriate audit evidence of the existence, completeness, valuation and allocation of, and rights pertaining to the restated immovable assets corresponding figure of R2.23 billion.  

 

4.1.2     Irregular Expenditure

 

a)       The Department did not have an adequate system in place to identify and recognise all irregular expenditure. The Auditor-General could not obtain reasonable assurances that all irregular expenditure had been properly recorded and the completeness of irregular expenditure related to the current year stated at R1.39 million (2010: R27.4 million).

b)       Payments made in contravention of Supply Chain Management requirements amounted to R16.5 million. The amount was not included in the irregular expenditure disclosed in Note 26 resulting in irregular expenditure understatement of R16.5 million.  

 

4.1.3     Other Expenditure

 

The Auditor-General was unable to:

 

a)       obtain audit evidence for expenditure transactions with an estimated value of R154.6 million.

b)       apply alternative auditing procedures to determine the occurrence, accuracy and compliance of goods and services amounting to R819 million and expenditure for capital assets stated at R1.3 billion.

 

4.1.4     Lease Commitments

 

No supporting evidence or documentation was available to the obligation, valuation and classification for the restatement of R115 million in operating lease commitments to address the prior years’ misstatement.

 

4.1.5     Contingent Liabilities

 

Claims against the Department amounting to R5.09 million not included in the contingent liabilities disclosed. The Department did not perform an assessment of the likely settlement amounts and the Auditor-General could not perform alternative audit procedures to determine reasonable assurance of the completeness of claims against the Department stated as R29.3 million. 

 

Emphasis of Matter

 

4.1.6     Material underspending of the Vote and Conditional Grants

 

a)       The Department materially underspent the budget on the Immovable Asset Management Programme by R235 million and the EPWP by R500.8 million.

b)       The bulk of the under-spending on the EPWP was due to the infrastructure grant to provinces and municipalities not being transferred due to underreporting and poor performance by reporting bodies eligible for the incentive grant.

c)       The Department therefore did not achieve its objectives to fast track the construction of selected schools and the energy efficient interventions.   

 

4.1.7     Material losses

 

Material losses of R54.8 million incurred as a result of the write-off of irrecoverable debt.

 

Additional Matter

 

4.1.8     Predetermined Objectives

 

a)       Reported objectives, indicators and targets are not consistent with the approved Strategic Plan.

b)       The indicators are not well defined and verifiable, and targets are not specific and measurable.

 

4.1.9     Transfer of Funds and Conditional Grants

 

Funds were deposited by the transferring national officer into a bank account which was not designated as the primary bank account of a province or municipality in contravention of the Division of Revenue Act (DoRA) requirements section 10(1)(d).

 

4.1.10   Asset Management

 

The accounting officer did not implement proper control systems for the safeguarding and maintenance of assets to prevent theft, losses, wastage and misuse as required by Treasury Regulation 10.1.  

 

Other Reports

 

4.1.11   Investigation

 

  • Probe alleged abuse of urgent and emergency procurement, as well as the utilisation of sole suppliers.
  • Investigation aimed to establish possible collusion between officials and service providers and to determine any reckless spending of funds.

 

4.2        Report by the Auditor-General on the Performance of the Property Management Trading Entity (PMTE)

 

The PMTE received a disclaimer of opinion from the Auditor-General.

 

4.2.1     Irregular Expenditure

 

a)       The entity did not have an adequate system in place to identify and recognise all irregular expenditure. The Auditor-General could not obtain reasonable assurances that all irregular expenditure had been properly recorded and that the completeness of irregular expenditure related to the current year stated at R138.6 million (2010: R264.1 million).

b)       Payments made in contravention of supply chain management requirements amounted to R291.6 million. The amount was not included in the irregular expenditure disclosed in Note 12 resulting in irregular expenditure understatement of R291.6 million.

 

4.2.2     Fruitless and Wasteful Expenditure

 

a)       The entity did not have an adequate system in place to identify and recognise all fruitless and wasteful expenditure. The Auditor-General could not obtain reasonable assurances that all fruitless and wasteful expenditure had been properly recorded and the completeness of fruitless and wasteful expenditure of R6.7 million.  

 

4.2.3     Trade and Other Receivables

 

a)       The entity could not provide sufficient appropriate audit evidence to support the trade and other receivables balance of R2.03 billion (2010: 2.23 billion; 2009: 2.07 billion).

b)       The impairment of R220 million (2010: 296 million; 2009: 130 million) and the impairment reversal of R76.1 million were not supported by appropriate sufficient audit evidence.

 

4.2.4     Revenue

 

Capital expenditure of R2.0 billion (2010: R1.7 billion) incurred on planned maintenance of state-owned buildings was off-set against revenue.

 

4.2.5     Predetermined Objectives

 

The performance against predetermined objectives is not reported separately by the entity and is included in the report of the Department of Public Works.

 

4.2.6     Strategic Planning

 

The business case for running the Trading Entity was not finalised or approved by the Accounting Officer of the Department of Public Works and no policy or reporting framework was formulated for the head of the Trading Entity in accordance with the requirement of Treasury Regulations (TR) 19.3.1.   

 

4.2.7     Procurement and Contract Management

 

a)       All invitations for competitive bidding were not advertised for a minimum period of 21 days, as per requirement of TR 16A6.3(c).

b)       All extensions or modifications to contracts were not approved by a delegated official, as per Treasury Regulation requirements.

c)       Construction contracts were awarded to contractors who were not registered and did not qualify for the contract in accordance with the prescripts of the Construction Industry Development Board, contrary to TR 16A6.3(a).

 

4.2.8     Banking and Cash Management

 

The main bank account of the entity was overdrawn throughout the reporting period in contravention of TR 19.2.3.

 

4.2.9     Other Reports: Investigations

 

The following investigations were underway at the time of reporting:

 

a)       Probed alleged abuse of urgent and emergency procurement, as well as the utilisation of sole suppliers.

b)       Alleged irregular expenditure in respect of leasing of properties and an irregular awarding of a tender and the incapacity of a contractor to fulfil its duties.

c)       Investigations into the leasing of buildings in Pretoria and Durban by the Department on behalf of the South African Police Service. The reports found that the procurement of the leases was not in accordance with a cost-effective system as required by the Constitution. The Department failed to record the reasons for deviating from a competitive tender process as required by supply chain management prescripts.    

 

5.         Committee Observations

 

a)       The Committee still notes with concern the delays in the reintroduction of the Expropriation Bill and the Built Environment Professions Bill which were withdrawn from Parliament in the 2008/09 financial year due to the need for further consultation. These bills would have been reintroduced in Parliament during the 2009/10 financial year. The Department has subsequently indicated that the bills will only be reintroduced in the 2010/11 financial year, which did not occur.

 

b)       During its oversight visits the Committee observed the challenges in the implementation of the Government Immovable Asset Management Act (No. 19 of 2007), especially as it did not extend to local government level. 

 

c)       The Committee has noted the management challenges that face the Department of Public Works and noted with concern the lack of stable leadership in the department. In the period under review, the department has had three different Directors-General.

 

d)       The Committee notes with concern the progressively worsening audit outcomes received by the department over the past three financial years, leading to a disclaimer in the financial year under review. The matters of emphasis raised in the previous financial year, i.e. 2009/10, were not implemented by the department.

 

e)       The Committee has concerns about the inconsistency of the figures reported by the department. It also raised concerns about the contradictions between the Auditor-General’s report and that of the department on the internal audit unit of the Department of Public Works and the risk management issues.

 

f)         The Committee notes with concern the underspending in the Expanded Public Works Programme and on infrastructure.

 

g)       The Committee notes with concern the shifting of funds from one programme to the other that was made by the Council for the Built Environment without informing the Portfolio Committee. The entity should also inform the Committee when making changes to its measurable objectives. 

6.                   Conclusions

 

6.1               On the Expanded Public Works Programme:

 

The Committee noted with concern the reporting method used on the EPWP II, and the disbursement of the incentive grant to municipalities did not favour the rural municipalities.

 

The Committee observed that the National Youth Service was not being implemented by all the provincial Departments of Public Works.

 

6.2        On the Financial Performance and Audit Outcomes of the Department and the Property Management Trading Entity:

 

The Department of Public Works needs to attend to all the challenges that were raised by the Auditor-General in the 2010/11 Annual Report.

 

7.                   Recommendations

 

7.1               The Committee recommends to the Minister of Public Works that a permanent Director-General be appointed before the end of the 2011/12 financial year after finalising the process of the suspended Director-General.

 

7.2               The Committee recommends that the Department of Public Works engage the National Treasury, SALGA and the Department of Cooperative Governance and Traditional Affairs on a new EPWP model that would be designed to assist all types of municipalities in accessing the incentive grants, including the low-capacity municipalities and rural municipalities.

 

7.3               The Committee recommends that the challenges in the completion of a credible Asset Register should be resolved by the Department through the implementation of a dedicated special project as previously recommended by National Treasury, to ensure the completion of a viable Asset Register. Such project should include the engagement of the national Department of Public Works, Department of Rural Development and Land Reform and the nine provinces, and progress reports should be presented to the Committee on a quarterly basis until 2014.

 

7.4               The Committee recommends that the Internal Audit Unit of the Department of Public Works should be properly resourced in order for it to perform its functions, including the delivery of an updated risk assessment and audit action plan. Minutes of the audit committee should be provided to the Committee on a quarterly basis.

 

7.5               The Committee recommends that the Department of Public Works reports back on findings of the Public Protector relating to the South African Police Service lease investigations, including measures to address the shortcomings identified as well as the disciplinary measurers taken against the staff members concerned.

 

7.6               The Department of Public Works should compile a detailed action plan to respond to all issues raised by the Auditor-General in his report and that a copy of this action plan be provided to the Committee within the next three months.

 

 

Report to be considered.