Report of the Select Committee on Co-operative Governance and Traditional
Affairs on Intervention in
1. Background
and Overview
1.1 The
Select Committee on Co-operative Governance and Traditional Affairs, having considered the request made by the National Council of
Provinces (NCOP) on 30 April 2010 to consider and report on the intervention
notice invoked in terms of section 139 (1)(b) of the Constitution at Mafikeng Local
Municipality by the North-West Provincial Executive Council (PEC), reports as
follows:
1.2 In terms of
section 139(1)(b), when a municipality cannot or does not fulfil an executive
obligation in terms of the Constitution or legislation, the relevant provincial
executive may intervene by taking any appropriate steps to ensure the fulfilment
of that obligation, including assuming responsibility for the relevant
obligation in that municipality.
1.3 The Office of the Chairperson of the NCOP referred the notice
of intervention in the affairs of
2. Purpose and Objectives
2.1 The main
objectives of the oversight visit was to determine whether procedural
requirements had been met and to verify
whether the PEC had used its discretion appropriately, before the
Committee could approve/disapprove the intervention. Through the deliberations and interaction with internal and external
stakeholders, the Committee wanted to determine how the PEC was intending to
restore the fulfilment of the relevant obligations and ensure fulfilment in the
long term. The aim was to ensure intergovernmental checks and balances aimed at
guarding the integrity and efficiency of the intervention process.
3. Delegation
3.1 The delegation of the Committee was composed
of the following Members of Parliament and Officials: Hon MH Mokgobi, Limpopo
(ANC); Hon AG Matila, Gauteng (ANC); Hon DV Bloem, Free State (COPE); Hon A Watson, Mpumalanga (DA); Mr NA Mfuku,
Content Adviser (Committee Section) and Mr V Mfuniselwa, Administration
Assistant (Committee Section).
4. Introduction
4.1
On 21 July 2010, the
North-West Premier tabled a notice of intervention in
4.2 In terms of section 139 (2)(b)(ii)
of the Constitution, the intervention must end if the NCOP does not positively
approve the intervention within 180 days since the intervention began, in this
case before the end of 27 December 2010.
5. Problems Identified by the Provincial Executive
Council (PEC)
5.1 On 30 June 2010, the Provincial Executive decided to invoke
section 139 1(b) of the Constitution in
·
governance and
administration, which was characterized by Council instability due to a lack of
decisive political and administrative leadership;
·
service delivery
challenges with regard to the provision of water, refuse removal, storm water
systems and electricity;
·
a dysfunctional Local
Labour Forum (LLF) as a result of strained relations between management and
labour, and poor attendance by management, with resolutions not implemented.
The Municipality was not financially viable and there was a
lack of political/administrative will in implementing credit control policy
6. Appointment and Functions of the
Administrator
6.1 The
intervention was presented to a Mafikeng Local Municipality Council meeting on
15 July 2010 and the Administrator, Mr J Motlogelwa, was seconded and
effectively appointed on the same date.
He was presented by MEC for Provincial Treasury, Hon L Mabe. Mr Motlogelwa was appointed to:
·
appoint an Acting
Municipal Manager outside the current municipal personnel with immediate
effect;
·
improve service
delivery in
·
improve the
financial controls in the Municipality, expenditure management, procurement
processes, revenue management and collection, as well as addressing issues
raised by the Auditor-General in his reports (MFMA compliance);
·
analyse and
implement past and current investigations, commissions of enquiry, forensic
audits, SIU, etc;
·
attend to labour
matters in the Municipality (outstanding disciplinary cases, labour disputes,
functionality of LLF and instil a culture of work and discipline amongst staff
members;
·
facilitate the
improvement of governance within Council (oversight role), including relations
between Council and administration;
·
conclude the
outstanding disciplinary case of suspended Municipal Manager (develop charges
and commence with disciplinary process);
·
investigate all
recently awarded contracts, in order to establish validity and legitimacy
thereof; and.
·
perform all other
applicable executive obligations as stipulated in various legislations and
prescripts.
7. Oversight Visit to
7.1
On 19 August 2010 the delegation of the Committee had interactive and
robust engagements with the internal and external stakeholders of the
Municipality. The main internal stakeholders the delegation interacted with in
the Municipality included the Speaker, Executive Mayor, Chief Whip, Councillors,
Ward Committee Members, Administrator and the South African Local Government
Association (SALGA). The main external stakeholders the delegation interacted with
included members of the community, the business forum and non-governmental
organizations.
7.2 For the purpose of this report, the
submissions made by both internal and external stakeholders are structured on
the basis of the five key strategic performance areas of the Local Government Strategic
Agenda which are: Municipal Transformation; Basic Service Delivery; Local
Economic Development; Municipal Financial Viability and Management, as well as
Good Governance and Public Participation.
(A). Municipal Transformation
and Organisational Development
7.3 Municipal Council: There have been serious challenges facing the
Municipality, involving service delivery. There have also been challenges
between Council and administration that have led to the Provincial Executive intervening
in the Municipality. During the past intervention, the Administrator did a good
job and systems were put in place. However, after his departure, the
administration started to collapse. Labour relations are a serious concern in
the Municipality. Until they are
resolved, there will always be disruption of services in the Municipality.
7.4 The current Executive Mayor, Cllr. Moreetsi Desmond
Jabanyane, assumed responsibility for his position on the 1st February
2010. It was reported that the previous Executive
Mayor, Cllr. Mosa Sejosingwe, took employment with the Presidency. The current
Acting Municipal Manager was appointed on 12 August 2010. The Administrator
will assist the Council in appointing a full-time Municipal Manager.
7.5 Administrator: Governance and administration has been characterized
by Council instability due to lack of decisive political and administrative
leadership. This has been due to persistent Council interference in the
administration and irregular appointment of contract workers which were not
required. Equally the Council failed to conclude disciplinary processes of the
suspended Municipal Manager. There were
no performance assessments or evaluation conducted for the past three financial
years, and the administration
was on the brink of collapse, with lack of staff discipline and absence of
ethical leadership. In addition, the Municipal Manager has been on suspension
for more than 12 months, and disciplinary hearings have been unnecessarily elongated.
7.6 MEC
for Provincial Treasury: The MEC, Ms Mabe, described
the circumstances that led to the decision of intervening in the Municipality
and how she was the subject of attacks by the Municipal Council. According to her, they felt that the MEC was
unfair, based on the reasons identified for the intervention. As a result, the
majority party did not accept the intervention, but promised to support the
Administrator, while the opposition welcomed the intervention. The MEC is of
the opinion that an audit of skills needs to be done to verify skills capacity
in the Municipality.
7.7 Provincial
Department: The Acting Head of Department of Local Government and
Traditional Affairs, Mr Themba Fosi, reported that both
the Municipal Council and Organized Labour approached the Department about a
request on invoking a section 139 intervention in the Municipality. However, although
the Department instituted a section 106 investigation, the Municipal Council
also appointed the Fivaz-Ramathe Commission of Enquiry to conduct an investigation.
In the Department’s opinion, this was very strange. In terms of the turnaround
areas, the Administrator would look at the key areas of operation and
maintenance, revenue and management, the Integrated Development Plan (IDP),
governance and administration. The invoking of a section 139 intervention at
7.8 Organized
Labour: Councillors in the Municipality persistently interfered with the
administration. About 20 people were reportedly being employed as contract
workers in the Community Services Directorate, and all of them were allegedly
being brought in by Cllr Vuyisile Tambam. The same Councillor was paid an
amount of R5, 134.18 (cheque no. 900010758) to attend the ELMA Training at the
7.9 It was reported that a Mr Martin
Sebakwane’s fixed-term contract of employment expired since it was linked with
that of the former Executive Mayor. Since the former Executive Mayor had been
re-called in January 2010, Mr Sebakwane was given a letter that automatically
terminated his contract in March 2010. However, evidence suggested that this
official was still on the municipal pay-roll system and was still receiving a
monthly salary of R38, 241.44.
7.10 Another irregularity reported by Organized
Labour was with regard to the irregular issuing of clearance certificates to
the buyers of the formerly North-West Housing Corporation which was sold
recently. It was reported that the Municipality issued clearance certificates without
settling outstanding debts to Council as required by policy. This transaction
was for an amount of around R30 million, and this writing-off of debts and the
awarding of discounts warrants a thorough investigation.
(B). Basic Service Delivery
7.11 Municipal Council: A claim was made that workers generally in
the Municipality reneged on their responsibilities. Some Councillors were also not
servicing their communities. Another challenge that was identified was with
regard to the finalisation and appointment of Bid Committee members. This
contributed to service delivery challenges and delays of projects for
communities.
7.12 Administrator: There are basic service challenges in terms of
provision of water, refuse removal, storm water systems and electricity as
result of lack of operations and maintenance of infrastructure due to
insufficient budget. Presently there are high mast lights in eight villages
installed in 2007, which have not been energized to date. In summary, service
delivery in the Municipality is on the brink of total collapse. The Municipality
is the capital town of the Province, but the image of the town does not reflect
this.
7.13 A plan for engagement of affected stakeholders such as Business Chambers
and Organised Labour will be unfolded, and this will include the assessment of
the efficiency of personnel management and optimum utilization of municipal
equipment and/or resources. Mr Andre Du
Plessis, a DBSA engineering expert, was appointed. A plan cutting across all
service delivery areas will be finalised by 25th August 2010, and a project
team will commence work immediately.
7.14 Ward Committees: Service
delivery is a major problem in the whole municipal jurisdiction. In addition, municipal
workers are not properly supervised in discharging their responsibilities. As a
result, the community is suffering due to poor service delivery. Furthermore,
it has been observed that there is a lot of in-fighting between Council and
administration, which results in undue delays of projects and basic services.
(C). Local Economic
Development (LED)
7.15 Business Forum: The National African Federated Chamber of Commerce (NAFCOC)
raised concerns about the municipality’s inability to see business as a
strategic partner in development at
(D). Municipal
Financial Viability and Management
7.16 Municipal Council: There
is a serious challenge of collecting revenue due to the Municipality. Government
institutions owing the Municipality a lot of money that could have been used
for service delivery. The Provincial Government departments owe the Municipality
around R190 million. Parliament should assist the Municipality in recouping all
the money owed to it by the state departments. Equally, there are serious
capacity challenges in the Finance Directorate, and this has led the
Municipality to receive disclaimers in four consecutive years.
7.17 Administrator:
7.18
The DBSA seconded municipal finance
expert, Mr Eduard Le Roux, who will lead the Finance Section to
deal mainly with management issues, revenue enhancement and Auditor-General matters.
Efforts are already afoot to ensure that matters such as payment of government
debts (mainly property rates), are brought to finality without delay. This will
enhance the cash flow of the Municipality and realise a cash-funded budget,
which is an issue at the moment.
7.19
Furthermore, an Audit Recovery Plan with responsible officials and
target dates will be implemented and consultants have been appointed to assist
with fixed asset register and debtors database cleansing. The Municipality has
decided to leave the Shared Service for Internal Audit and the Shared Audit
Committee rendered by the
(E). Good Governance and
Public Participation
7.20 Administrator:
The LLF is not functional as a result of strained
relations between management and labour. There are serious tensions and
conflicts between management and workers, as a result of disagreements over
labour-related matters. There are reported allegations of corrupt activities in
the Municipality which are not acted upon by management and Council. In order
to rescue the Municipality from total collapse and to salvage whatever is left
in the institution, there is a need to decisively intervene in the Municipality,
both at political and administrative level.
7.21
Members of Community Forums:
Public participation and consultation is extremely poor in the Municipality. There
are Imbizo’s held by the Municipality every six months, where false hopes are
raised by the Council. When delivery on the issues raised by the communities is
not met, the Council attributes this to insufficient funding or budget constraints.
7.22
Ward Committees: It
has been indicated that the work of Ward Committees seems not to be appreciated
by the Municipality, although they are the communication link between
communities and the Municipality. Hence it has been suggested that stipends for
Ward Committee members should be awarded. In addition, it has been reported
that there are conflicting roles between Ward Committees and Traditional
Leaders.
8. Committee Observations
and Opinion
8.1
It was observed that most of the interventions undertaken in the
8.2
In
8.3
The Committee acknowledged the partnership requested by NAFCOC in
contributing to local economic development in
10. Recommendations
10.1 Having conducted the oversight visit to
10.1.1
The NCOP approves the intervention in
10.1.2
The Minister for Co-operative Governance and Traditional Affairs should
approach the Hawks to pursue criminal investigation in all cases of financial
irregularities and fraud in
10.1.3
The Administrator should investigate the matter regarding the Council
vehicle in
10.1.4
The Administrator should investigate the alleged improper appointment of
20 contract workers in the Municipality,
and take the necessary corrective measures in rectifying these appointments.
10.1.5
The Administrator should immediately investigate and take corrective
steps with respect to the Director of Community Services, who is alleged to
have refused servicing the community.
10.1.6
The Administrator should fast-track the process of appointing the
Municipal Manager, in order to facilitate the transfer of skills and to ensure
continuity.
10.1.7
The North-West MEC for Provincial Treasury should table quarterly
progress reports to the NCOP and the Provincial Legislature on the status of the
intervention in the Municipality, including challenges encountered.
Report to be considered.