Report of
the Portfolio Committee on Public Works on the oversight visit to the
1.
Introduction
The
Department of Public Works was tasked by the President of the
A multi
party delegation undertook an oversight visit to the
Hon G G Oliphant
(ANC), Chairperson and leader of the delegation, Hon C D Kekana (ANC), Hon N M
Madlala (ANC), Hon T H Magama (ANC), Hon N D Ngcengwane (ANC), Hon N T November
(ANC), Hon N J Masango (DA), Hon W Rabotapi (DA),
Hon L Gaehler (UDM), Hon P B Mnguni (COPE).
The following
support staff from Parliament accompanied the delegation:
Miss A
Busakwe (Committee Secretary), Miss S Goba (Committee Assistant) and Miss I
Stephney (Committee Researcher).
The
following officials also accompanied the delegation: Mr G Moso: Parliamentary
Liaison Officer in the Office of the Minister, Ms M Motumi: Parliamentary
Liaison Officer in the Office of the Deputy Minister, Ms C Mavi: DPW Intergovernmental
Relations Unit, Mr X Nkwali: Independent Development Trust (IDT) Regional
General Manager, Mr M Makupula: Eastern Cape Programme Portfolio Manager from
the IDT, Mr E Masibi: Contractor Registrations Manager at the Construction
Industry Development Board (CIDB), Mr R Raphiri: Procurement Manager (CIDB), Mr
S Ndamase: Parliamentary Liaison Officer in the Office of the MEC (Eastern Cape
Provincial Department of Public Works), Mr B Makhwabe: Senior Manager EPWP, Mr
K Kostile: EPWP Assistant Manager, Ms N Ndlela: EPWP Assistant Manager, Mr J
Lloyd: Communications Manager, Mr X Mkiwane: EPWP Unit, Mr W Tutani: EPWP Unit
and Ms Y Stengile.
2. Terms of reference
The overall objective of the
oversight visit to the Eastern Cape Province was for the committee to exercise
its oversight mandate over the Department of Public Works with regards to the
performance of the Expanded Public Works Programme phase 2 (EPWP 2); the
eradication of mud schools and other inappropriate structures and thereafter
compile a report with findings and recommendations to Parliament for the
Minister of the Department of Public Works to take the necessary actions in assisting
the Province.
3. Summary
The
Committee met with the MEC for Public Works, Ms P Majodina, the Head of the
Public Works Department in the Province, Mr B Gxilishe and other Senior
Managers in the Eastern Cape Department of Public Works. A presentation on EPWP 2 and a progress
report on the eradication of mud schools were presented.
Members of
the Provincial Standing Committee on Public Works could not be part of the
Portfolio Committee’s oversight visit due to their Provincial Parliament
Programme.
The MEC
announced that as of 1 April 2010 the Department’s name will change to the
Eastern Cape Department of Roads and Public Works. This is in an effort to
group together the infrastructure departments.
Day one of
the oversight visit of the Portfolio Committee coincided with the first day of
training for the National Youth Service (NYS) recruits in the Province. These
young people had an opportunity to meet with the members of the Portfolio
Committee on Public Works who motivated them into working hard in improving
their skills by furthering their studies and by being dedicated in their
jobs. The NYS programme in the
Presentation
on EPWP 2: The Province reported an
achievement of 78% on work opportunities reported against target in the
infrastructure sector. Out of the allocated R83, 551.00 incentives grant only R
22, 889.00 were used by the Province at the time of the visit. Performance at
Public Body level was reported to be uneven both at Municipal and Departmental
levels. The challenges faced by Public Bodies in implementing EPWP 2 were
highlighted and measures to address these challenges were also identified. The
Provincial Department of Public Works will complement the technical staff
provided by the National Department of Public Works in collaboration with the
Development Bank South Africa (DBSA) Siyenza Manje programme in supporting
municipalities technically. Provincial Department of Public Works staff is
deployed to capture information on sites and partnerships are to be created
with the National Department of Public Works to train officials in
labour-intensive methods of construction.
Presentation
on the eradication of mud schools: This programme is responsible for assisting
the Department of Education with the eradication of mud and unsafe structures
on a project basis as allocated to the Department of Public Works by the
Department of Education. The schools built by the Department of Public Works are
EPWP compliant. Challenges faced by the DPW are delays in payment from the
client departments, budget constraints, insufficient resources, late submission
of project list, delays in electricity connection and delays due to weather
conditions.
The
Committee visited various EPWP projects in the Amathole, O R Tambo and Alfred
Nzo District Municipalies. Profiles of these projects will be given in detail
in the report under findings and the challenges which were noted by the
Committee will also be outlined in this report followed by the Committee
recommendations.
4. Findings
4.1
Due to the
ANC Lekgotla in the Province from 1 – 2 February 2010, the Executive Mayor and
team were not available to meet with the Portfolio Committee on Public Works.
4.1.1 Ngcingcinikhwe Access Road
This is an
EPWP Kamoso awards best innovative project in the infrastructure sector for
2009. The road is approximately 2.1 km between Ngcingcinikhwe and
Previously
the only access for the community was a badly eroded track, too steep for
vehicles. Labour intensive construction methods were employed providing
training and local work opportunities for 109 local unemployed people. The
project had six committee members, seeing to the smooth running of the project.
This was a
R3 million project. Road has concrete and paving blocks which guarantees that
it will not wash away easily.
Requests
from the Ngcingcinikhwe Community members:
4.2 O R
Councillor
S Ntuli and the Chief Executive Officer of the O R Tambo Academic Hospital welcomed
the members of the Portfolio Committee on Public Works in the O R Tambo
District Municipality and the Hospital.
4.2.1 Bityi Ventilated Improved Pit
(VIP) Sanitation Project (
The O R
Tambo District Municipality signed the Memorandum of Understanding with the
Department of Public Works in 2006. This project is under the Vukuphile
learnership programme. The project started in June 2009. The initial contract
with the 15 contractors who were awarded the tender by the
The workers
in this project did not have the Personal Protective Clothing and the
contractor the Committee met insisted that in the original tender document, the
requirement to provide the personal protective clothing was not specified and
was later included. The Committee observed that safety standards were not met
on site. The contractor complained about the two months delay in payment. The
community members had a number of complaints and some of the complaints were a
result of poor communication between the District Municipality Officials and
the community members. There were
problems and uncertainty around the standard of the toilets seats used, the
digging of holes and payment for doing that, the type of soil these toilets are
built in and the size of the toilets. Some of the residents claimed that these
toilets were not safe and the toilet pits were shallow. The project facilitator
from the
4.2.2 King Sabata Dalindyebo (KSD)
Clean Up Campaign
The project
has employed 50 people, 18 males and 32 females who are responsible for
cleaning the Umtata CBD and the surrounding areas (Mqanduli and
Some of the
project beneficiaries were working without protective clothing due to
procurement challenges within the Municipality. The Municipality was faced with
a challenge of having an old fleet that was as old as 18 years and the
Municipality budget could not accommodate the three year tender for the lease
of transport. The land fill site used is not a permitted site and a new site
given to the Municipality is under land claims and cannot be used until the
land claim issue is sorted.
The workers
asked for an increase in their stipend, for safety boots, vests, gloves and
overalls and that the project be extended to be over six months.
The
4.2.3
The school
was one of the unsafe structures. It was built of prefabricated material and
had no windows and as a result most parents took their kids to better schools
in the area. The school has 17 teachers and 600 learners. The new structure had
14 classrooms, toilets and a reception room.
The School
Principal mentioned that they still needed furniture in the form of desks,
chairs, tables, cabinets, security clerk and computers.
The
community requested an access road to the T173 road, a traditional council hall
and a resident for the Chief of the area with all the resources needed for the
Chief to carry out his duties.
4.3
The
Councilors in this
4.3.1 Alfred Nzo VIP Sanitation
Project
This Municipality was placed under an
intervention in terms of Section 139 of the
Constitution and after the interventions a new Senior Manager for
Infrastructure Development and Municipal Services was hired in October 2009.
The
district has been divided into seven zone centers where material is produced
for the construction of VIP toilets. Two service providers were awarded the
contracts, one service provider served five municipalities and the other served
two municipalities. This project uses the Municipal Infrastructure Grant (MIG)
funds. The
The project
visited by the Committee employed 150 people and machinery is used to produce
bricks, one machine produces 6000 bricks per day. Slabs and toilet seats are
also produced on site.
The project
beneficiaries earn a stipend of R65.00 per day. There were also labourers who
were paid R14.00 per task and that was viewed by the Committee as problematic
as there were no clear measures in place to measure a task. The labourers on
site did not have protective clothing.
The
contractor building VIP toilets was asked to devise a method of changing the staff
he employs, staff members should know how many months their contracts would be
instead of continuous change which at times would come as a surprise to some of
the people working in this project.
4.3.2 Msukeli Arts and Culture
Centre
The Msukeli
Arts and Culture Centre is a state of the art centre which was built to house
different cooperatives and small businesses in the area. The centre was built
and funded by the
The centre
owed Eskom and their electricity supply was cut. They can no longer afford
diesel to pump the water and as a result most of the facilities in the centre
are closed e.g. the restaurant, internet café, the hydroponics’ project,
pottery, bead work and sewing centre.
The tunnels
used for the planting of tomatoes were destroyed by the storm in 2009. There
are 15 staff members who get paid stipends of R500.00, a caretaker who earns R3
500.00 and a gardener who earns R1000.00 per month.
When the
project was fully functional, their arts and crafts used to be exhibited in
different arts festivals including the Grahamstown arts festival.
On the 17
February 2010 a new board will be elected that will be responsible for the management
of this facility.
The Mayor
of the Alfred Nzo District Municipality together with the Alfred Nzo
Development Agency were asked to assist in the management of the Msukeli Arts
and Culture centre until a new board has been elected. The project must be run
in a manner that would raise funds for the project and make it self sustainable
by reviewing its revenue model from their business plan.
4.3.3
The project
started in October 2008 and will be completed on the 31 March 2010. This was
one of the unsafe structures; the first school building was a mud structure
which was later changed into a prefabricated structure. By the time of its
eradication it was already collapsing and unsafe. The project consisted of 15
classrooms, 26 toilets and an Administration block. Project beneficiaries were
trained in bricklaying, plastering and painting.
5. Conclusion
The
Committee decided that it will do a follow up visit in the Province. The
incentive grants given to Provinces under the EPWP 2 were under utilized by the
Capacity
problems were noted in the Municipalities and in the Provincial Department of
Public Works as this was also proved by the inability to fully utilise the
incentive grants of the EPWP 2 programme. The Committee Chairperson emphasised
government’s commitment in fighting poverty, rural development and ensuring
good education for the children of our Country.
6. Recommendations
Report to
be considered