Report of the Portfolio Committee on Public Enterprises on the Oversight visit to State Owned Enterprises (16 – 19 November 2009), dated 2 March 2010

 

1.  Background

 

The Portfolio Committee on Public Enterprises undertook oversight visits to State Owned Enterprises as part of executing its oversight mandate as promulgated by the Constitution of South Africa.  The visits were also aimed at familiarising the Committee with operational sites and challenges faced by the entities.

 

The delegation of the committee consisted of the following: Ms M. P. Mentor (ANC, Chairperson of the Committee), Dr S. Pillay (ANC), Ms G Borman (ANC), Mr C Gololo (ANC), Dr GW Koornhof (ANC), Ms F Hajaig (ANC), Mr Pieter van Dalen (DA),  Mr M. Nhanha (Cope), Dr M. Mangena (Azapo), Mr D. Mocumi (Committee Secretary), Mr M. Erasmus (Committee Assistant) and Mr E. Boskati (Researcher)

 

2. Entities visited

 

                      Transnet pipeline (Freight rail) in Johannesburg, South African

           Airways and Airports Company South Africa - date of visit was  

on the 16 November 2009.

                      Pebble Bed Modular Reactor site and Transnet Rail Engineering Warehouse (Pretoria) - date of visit was on the 17 November 2009

                Eskom’s Medupi and Matimba power stations in Limpopo - date of visit was on the 18 November 2009. The Committee also met with the Board and Management of Eskom in Johannesburg.

                Port of Nqgura and the Port Elizaberth Harbour - date of visit was on the 19 November 2009.  

 

3.       Visit to Transnet Freight Rail, Rail Engineering Warehouse and Port of Ngqura

 

3.1  Background

 

The visit revolved around the following key issues: complaints received by the Port Elizaberth Regional Chamber of Commerce regarding the oil leakages from the tank farm and the adverse effects on the environment; the environmental risks caused by the manganese terminal, and the effects on the immediate communities and businesses in particular; progress on plans to move the manganese terminal from the PE harbour to an alternative site; the issue of high cargo dues at the harbours and ports and the infrastructure program of Transnet.

 

3.2 Site visit to the Transnet Pipeline in Johannesburg

 

On arrival at the Transnet Oil Refinery in Johannesburg, the Committee was welcomed by the Group Executive in the Office of the Group Chief Executive Officer, Mr Vuyo Kahla, accompanied by the Management of Transnet.  Mr Kahla welcomed the Committee and explained to members that the Group CEO, Mr Chris Wells and the board would not be available during the visits due to prior commitments.

 

The Project Manager responsible for the Pipeline construction made a presentation to the Committee in which he highlighted the following:

                The challenge for most industry players, such as Engen, BP and Chevron is that they need to transport oil from the coast into inland areas.

                Regarding the Infrastructure Plan of Transnet, the only project that is planned by Transnet Freight Rail is to build a Multi-Purpose Pipeline which is nearing completion. There were no build programs that Transnet do not honour, as alleged by ACSA in their presentation to the Portfolio Committee in Parliament. The main reason there is no dedicated jet fuel pipeline for the aiports, is because ACSA did not upgrade capacity that was needed for a dedicated jet fuel supply pipeline.

                There is a National Task Team which comprises of representatives from the Department of Energy, Transnet Freight Rail and other stakeholders who are responsible for ensuring there is security of fuel supply for 2010.

                There is an Energy Security Master plan that sought to maintain that there is sufficient local and indigenous production levels of fuel.

                The usage of Transnet pipelines as storage facilities remains a challenge.

                There is a National Infrastructure Plan to which all layers of government and relevant stakeholders have contributed to.

                The growth in residential areas which moved closer to the tank farm and the harbour, made it difficult for Transnet to expand its operations.

                Transnet has not experienced any fuel theft in the past, and that was mainly due to the difficulty of stealing from a pipeline and security put in place.

 

The Committee visited the construction sites of the pipelines. Security measures were in place to prevent sabotage and theft. The Pipelines are coated with concrete cement. The 16 inch pipes are manufactured in South Africa and the  24 inch pipes are manufactured in China.

 

3.3 Recommendations

 

A report should be forwarded to the Portfolio Committee on Public Enterprises regarding the progress made on the implementation of the bridging plan for fuel supply. There is a request to develop underutilised ports such as Port Nollorth, in order to stimulate the economy. Transnet must plan to procure locally, especially locally manufactured Steel. The Committee will meet with NERSA to look into the Transnet Pipeline tariff increase which was identified as a challenge by Transnet Freight Rail. The Committee would invite Transnet to present the National Infrastructure Plan to Parliament.

 

3.4 Visit to Transnet Rail Engineering Warehouse (Koedoespoort)

 

The Portfolio Committee members were welcomed by the Chief Executive of Transnet Rail Engineering, Mr Richard Vallihu and Executive Committee members, the group executive of Transnet, Mr Pradeep Maharaj, Mr Vuyo Kahla, as well as the management team of the Koedoespoort plant.  

 

The chairperson of the Portfolio Committee, Ms Mentor, briefly outlined the reason for the visit and thanked Transnet for affording them the opportunity to visit the site.

 

Due to time constraints, only a limited number of businesses were visited during the day. These were: Coach Business, School of Engineering, Rotating Machines business and the Locomotive Business (New Builds).

 

The Committee toured the Rail Engineering Warehouse of Transnet. The warehouse has the following capabilities:

                      Body Assembly of locomotives, production of small parts of the locomotives and is the fastest setup production plant in the world

                      Capacity of manufacturing 150 coaches per year

                      Transnet School of Engineering has an intake of 269 learners trained on different trades for the year 2008/09, and the program is funded by the SETA

                      There are 6 rail engineering plants and 130 depots spread over the country

                      The first new diesel locomotive (Class 39-200), was built  in South Africa by Transnet Rail Engineering

 

The Portfolio Committee noted with concern the low levels of orders received by the plant, that have led to retrenchments of more than 650 contract employees. The engineering site has a capacity for manufacturing 150 coaches per year, but is being underutilised with an order of only 80 locomotives for the current year, and 100 for the year 2010. There are orders from neighbouring countries such as Angola and Mozambique but that was not enough to keep the plant operating at optimal levels.

 

3.5 Recommendations

 

The Committee recommends that a detailed report be forwarded to it outlining the legislative impediments that exist, and a status report on production at Koedespoort. The report should further outline the interventions that Transnet Rail Engineering would require from the Portfolio Committee.  Transnet should consider embarking on a national skills campaign, conducting training for other SOE’s and ensuring that young people are self employed and become entrepreneurs.  

 

3.6 Visit to Port of Nqgura and the harbour

 

The Committee visited the harbour and port of Nqgura, and observed the following:

      The Port has a 500 000 container capacity, and is in optimal use,       with 8 cranes at the PE terminal.

      There is capacity for 100 000 cars at the terminal, and it is being used by VW and General Motors.

       R600m was spent on the refurbishment of the manganese terminal, which was still being revamped.

      In terms of the loading and offloading of containers, it took an hour to  move 26 containers by crane, depending on the size of the ship.

 

3.7 Committee Observations

        

           The Committee raised concern at the health hazards that the community might get exposed to. The Committee was informed that the Manganese terminal housed unprocessed manganese, which was less harmful in that form. There were pre-tests done on employees, and on a quarterly basis to asses the contamination on workers. There have been no cases of manganese infection on the employees thus far and measures were taken to address the levels of dust and impact on communities.

 

 

       Regarding the complaints on oil leakages on the tank farm, the Committee was informed that all avenues have been exploited to determine which tank farm had leaked the oil. An Isotope test was  undertaken to get a breakdown of the oil particles from the contaminated water, and results were due in December 2009. A test done in the USA showed that the contamination was as a result of multiple oil particles making it difficult to know which tank farm leaked the oil.

 

        Regarding the removal of the manganese terminal, the Committee was informed that there were feasibility studies commissioned and plans in place to move the manganese terminal out of the PE terminal by 2016.  There was a steering Committee that comprised of the Regional Chamber of Commerce, the Municipality, safety and environment lobby groups, and Transnet that met regularly to ensure that there was progress on plans to move the manganese terminal and address all problems.

 

3.8 Conclusion and recommendations

 

The Committee would receive a detailed progress report by end of November 2009 from the steering committee, on the plans to move the manganese terminal out of Port Elizabeth. The Committee commended the steering Committee for the commitment displayed in resolving the complaint by the Regional Chamber of Commerce, and urged the parties to continue reporting quarterly to the Portfolio Committee on progress. The Department of Public Enterprises should convene a meeting with the Department of Trade and Industry to discuss the issue of cargo dues, which were identified by DTI as being very high in South African ports, compared to international counterparts. A report should be forwarded to the Committee on the outcome of the deliberations by end of February 2010.  

 

4.  Visit to South African Airways (SAA) and Airports Company of South  

     Africa (ACSA)

 

4.1 Introduction

 

On arrival at SAA Headquarters in Eiselen Park, the committee was welcomed by both SAA and SAA Technical (SAAT) executive staff, including the Chairperson of the SAA Board, Ms Cheryl Carolus. She  welcomed the Committee  and explained to members that the board was prepared and willing to work with Parliament (through the Committee) and to keep the latter informed about everything that was happening in SAA, and not limit interactions to annual report meetings.

 

The Chairperson confirmed that the appointment of the SAA Chief Executive Officer would be made by the end of December 2009.

 

She indicated that in terms of the Articles of Association, the Board would have to meet at least 4 times a year, and that there would be a need to draft a questionnaire, or hold discussions with Chairpersons of Committees and Members of Parliament, to iron out differences and attend to their concerns, especially those who do not fly SAA.

 

Mr Chris Smyth, acting CEO of SAA, informed the Committee that the issue of increasing air ticket fares during the FIFA World Cup was an international norm practiced by airlines around the globe and was based mainly on demand. 

 

4.2 Presentation by ACSA

 

In its presentation, ACSA explained how customers’ baggage was handled for both departure and arrivals, and the sites on which cameras were located for security purposes.

 

ACSA explained that the number of reported baggage thefts had been reduced to 8% from 28% a few years ago. They also explained that most reported cases of baggage theft were not necessarily committed in their airports but merely discovered there.

 

ACSA’s presentation involved two main issues namely, fuel shortages as well as airport taxes. On airport tax, ACSA explained that the figures reflected on the tickets as airport tax did not mean that all the money went to ACSA. ACSA acknowledged that there were other charges in the airport tax bracket that had nothing to do with them. The airports company gave an explanation on the money they received in the airport tax bracket as follows:

 

  • On domestic flights they receive R49.
  • On regional flights such as Botswana, Lesotho, Namibia and Swaziland (BLNS) they receive R102.
  • On international flights they receive R135.

 

4.3 Presentation by SAA Technical (SAAT)

 

SAAT’s presentation was mainly about what the division does on a day to day basis, which was full-service maintenance, repair and overhaul of aircrafts. SAAT is recognised world over and overseas companies always recruit some of their staff. The division is the most advanced in the continent.

 

SAAT has received licences and certified by EASA of the European Union as well as FAA of America.

 

SAAT has a complement of 2600 staff members. In their presentation SAAT showed the Committee the aircraft Black Box and explained that it was one of the most important equipments during air-crashes as it contained most of the information about what might have led to an accident.

 

They also showed the committee a piece of an aircraft wing component that was hit by a bird, which they called a ‘bird-strike.’ The point was to demonstrate the impact a bird could have on aircraft especially during take-off which might lead to accidents.

 

On the possibility of SAA selling its technical division, the Chief Executive Officer, Mr Chris Smyth said that, if that happened SAA would either have 51% or 25% of shareholding whichever the shareholder found suitable, but it would not be wholesale.

 

4.4 Site visit to the SAA Technical workshop

 

The Committee was taken to the SAAT workshop site to see SAAT’s staff at work and the repairs and refurbishments made on some of the aircraft. The work included working on the engines, wires, etc.

 

Among the aircrafts that were on site was a Boeing 340-600, the biggest aircraft on SAA’s fleet. Members of the Committee had the opportunity to go inside the aircraft which was at that moment given a full service. Once SAAT finished working on an aircraft what follows is test flying before it is ready for commercial flights.

 

4.5 Site visit to the baggage handling facilities

 

The Committee was taken to SAA’s baggage handling system. ACSA has a R24 million baggage handling facility where staff members are screened as they enter the facility. The company also has a Baggage Reactive Team linked to the baggage control room that advises on baggage pilfering based on statistics from all airlines.

 

ACSA’s Project Manager explained that some of the causes of broken locks on bags and suitcases was as a result of bags or suitcases getting stuck on the corners of conveyer belts.

 

ACSA also has 17 machines which process baggage and if a bag is pilfered or opened the machine rejects it and if it is not rejected it goes to the next level. Once it reaches ground level it becomes SwissPort’s responsibility and ACSA has no further control over bags.

 

All staff members handling baggage for ACSA are vetted. Nonetheless, pilfer age of customers’ baggage continues. This includes drug trafficking. There is also a Baggage Pilferage Committee involving the following stakeholders – the police, ACSA and the airline’s representatives.

 

The Portfolio Committee went through the baggage handling process to see for themselves how baggage was handled through the cameras and the baggage control room. In the process, members of the committee observed at what stage the opportunity for pilfering arises. The likelihood of baggage pilfering, according to the Committee’s observations was either at ground level inside the building or when handled by the luggage handling companies appointed by airlines, during loading or off-loading of baggage from aircraft.

 

4.6 Recommendations

 

ACSA is requested to forward to the Committee a breakdown of all the taxes that are charged on a ticket, with a comparative analysis of all airlines. The Committee further recommends that security vetting be done periodically for staff working for SAA and ACSA. SAA Technical should table a plan regarding its future within SAA to the Committee by end of March 2010. 

 

5. Oversight visit to Eskom’s power stations and headquarters

 

5.1 Background

 

The visits focused on Eskom’s Headquarters at Megawatt park and the Medupi and Matimba powerstations in Lephalale in the Limpopo province. The purpose of the visit was for the Committee to familiarise itself with Eskom’s infrastructure build programme as well as Eskom managerial issues such as the resignation of the CEO and the Chairman of the board.

 

5.2 Matimba Power station 

 

On arrival at Matimba Power Station, the Portfolio Committee was welcomed by the Acting Chairman of the Eskom board, Mr Mpho Makwana, and some of the management team members. In welcoming the Committee, Mr Makwana gave a brief history of Lephalale, saying that it started in 1916 as a farm and in 1929 rail was built. The area is surrounded by coal and iron ore which made it attractive to mining companies and Eskom.

 

5.3 Presentation on the Matimba Power station by Christo van Niekerk, Power Station Manager

 

In his presentation, Mr Van Niekerk highlighted the following key aspects of the projects:

                      The Matimba Power Station produces nearly more than 8% in terms of Eskom’s total capacity.

                      The power station is designed to generate 4000MW of power, large enough to light-up the whole of the Western Cape including Cape Town. Matimba produces 8.55% of the annual electricity demand in South Africa.

                      Coal is stocked for thirty-three and a half days in the plant.

                      Matimba employs a workforce of about 594 with 74 learnerships.

 

5.4 Presentation on the Medupi Power station

 

The presentation highlighted the following key issues:

                Medupi will be the fourth largest coal-fired power plant in the world.

                      Medupi electricity represents 16% of current South Africa’s current consumption, and will cater for 7,5 million households.

                      The power station will have economic spinoffs for the local population in terms of skills development, employment opportunities, economic growth of the area and infrastructure development etc.

                      The Medupi Power Station would cost about R125 billion to complete. Of this amount, R49 billion would be locally spent while R86 billion would be spent on contracted work from outside.

                      The first unit would be commissioned in 2012 and the final unit in 2017 contributing about 40 000 Megawatts to the national grid. 

 

5.5 Committee Observations and Opinions

 

The Committee raised concerns about coal stock reserves, asking whether the stock was in line with the recommendations made by the National Electricity Regulator of South Africa of 40 days of stock in reserves.

 

Eskom’s management team indicated that the intention was to increase current stock levels and possibly meet the 40 days recommended by NERSA.

 

On the presentation it was shown that one of the coal power plants situated at Kriel in Mpumalanga, was not performing to its optimum (at 69%) while all the other power stations were at performance levels of 80% and above. The Committee urged Eskom’s management to improve the situation at Kriel.

 

When asked why Eskom is not part of the PBMR project, Eskom’s management team responded by saying that the project was too costly.

 

The Committee also raised concerns about the rate of water usage by the Power Stations in the area in light of reports that there will not be enough water to supply both Power Stations. Eskom managers responded by saying that the two power stations would draw water from the Mokolo dam, the Crocodile river and also make use of ground water whilst also practicing water conservation. 

 

5.6 Site tour to Matimba and Medupi power stations

 

The Committee was then taken on a site tour of the Matimba Plant where the Committee was shown the Turbine Steam Engine. From the steam engine the Committee was taken to the control room where it was shown how the controller detects and identifies mechanical faults in the Turbine Steam Engine.

 

From the Matimba Power Station the Committee departed for the Medupi Power Station which is still under construction. This was after a power-point presentation on the Medupi Power Station.

 

Eskom would make provision for its workers to stay with their families not far from the construction site instead of them commuting or travelling long distances to and from the construction site.

 

5.6 Committee Observations

 

The Committee raised concerns about the absence of timeframes for the finalisation of the Medupi project. Eskom promised to furnish the Committee with the timeframes as soon as they were available.

 

Eskom management team stated that some of the funding came from France and Germany through credit agencies especially where most of the equipment is bought.

 

Eskom’s management highlighted some of the challenges they were experiencing, one of which was working on servitude areas through farms owned by foreigners. They asked the Committee to help them through legislation (e.g Expropriation Bill) to resolve the matter.

 

Cable theft in the Lephalale region was at least under control and over the past 5 years there were only 4 reported cases and a Joint Committee of Eskom and the police is looking at this situation. In general, cable theft cost Eskom nearly R400 million per year.

 

Another challenge Eskom’s management highlighted was the problem of the supply of coal, maintaining that there were not enough coal mines. Currently the utility is supplied by Exxaro, BHP Billiton, Anglo-Coal as well as smaller mining companies such as Shanduka and Extrata.

 

The high volume of 400 tonnes heavy duty trucks that transport equipment to Medupi have led to the deterioration of roads, and caused delays in the delivery of materials and equipment to the construction site. Unless the roads are upgraded, they will cause unnecessary delays in the construction of the plant.

 

5.7 Conclusion and Recommendations

 

The Committee will in future arrange to meet jointly with the Portfolio Committee on Energy to look at issues of coal supply and the quality thereof. The Committee recommends that a study be commissioned by the Department of Public Enterprises to look at the effectiveness of the strategies put in place to cushion the poor against Eskom’s tariff increases.

 

 The Committee further recommends that conflicts that may exist at the level of the board and executive management of Eskom be resolved speedily in order to ensure that the corporate image of Eskom is positively reconstructed.

 

6. Oversight visit to the Pebble Bed Modular Reactor (PBMR) in Phelindaba, Pretoria.

 

6.1 Introduction

 

The committee was welcomed by the PBMR executive team including the Chief Executive Officer, Mr Jaco Kriek and NECSA CEO, Dr Rob Adam. After a few words of welcome, the Committee was taken to the boardroom for a presentation on PBMR Technology and Nuclear Licensing.

 

The purpose of the visit included familiarising members of the Committee with the PBMR project as a renewable source of energy. The visit was also meant to make members of the Committee understand why PBMR postponed the tabling of its annual report for the 2008/09 financial year.

 

6.2  Presentation on PBMR Technology programme by Dr Jörg Lalk  Preng, Manager: PBMR Technology Development & Fuel Design

 

 The presentation was based on the Technology Development programs and   University collaborations. The following were the key highlights of the presentation:

                      PBMR has signed a $10bn contract with a US based company.

                      The Department of Energy has led bilateral talks with Algeria, because they would like to use the technology and would like to partner with SA.

                      The International Atomic Association permits every country to possess nuclear for peaceful intent.

                      South Africa was used for international demonstrations because of the capabilities it possessed.

 

6.3 Presentation on Nuclear Licensing by Dr Alex Tsela

 

In his presentation, Dr Tsela highlighted the following key issues:

                      The main challenge facing PBMR was the wrong perception regarding the safety of nuclear energy

                      A need for regulatory reforms for the high temperature reactor, especially regarding roles & responsibilities of operator, owner, designer, etc.

                      The structural and institutional requirements to ensure the licensing of PBMR

 

6.4               Problems and concerns raised by Members

 

                      What were the risks involved in the project and its safety both to humans and the environment, something similar to Chernobyl.

                      What were the advantages and prospects of partnering with Algeria

                      What were the advantages of the Pebble Bed Modular Reactor in comparison to other renewable energy sources.

                      Whether there were any interactions with Iran, and whether bi-laterals were complying with South Africa’s foreign policy.

                      Which countries have successfully implemented the Pebble Bed technology, and what were the main reasons countries like Germany abandoned that program.

                      Concern regarding South Africa being used as a demonstration plant, and foreign countries exploiting PBMR and bringing no investments.

 

6.5               Responses from PBMR team

 

                      The PBMR team explained that safety measures were systematically automated and that the Chernobyl case was a human error which was eliminated in the PBMR through self-regulation.

                      The Committee was informed that Algeria was rich in oil and gas that would benefit the PBMR program.

                      PBMR was much more reliable and safer, notwithstanding the fact that the PBMR was much more expensive and took longer to produce and most countries did not view it as a viable option. This explained why countries like Germany abandoned it.

                      The countries that were using the technology included the USA and China.

                      South Africa was used as a demonstration plant because of its outstanding capabilities, and PBMR was a model for most developing countries that intended using the technology.

                      There had been no collaborations with Iran and all international collaborations were informed by South Africa’s foreign policy.

 

6.6 Site Visit to the Fuel Development Laboratory

 

After the presentation, the members of the Portfolio Committee were taken to the Fuel Development Laboratory where they were shown how the pebbles were made. The process started with graphite powder which was mixed with chemicals such as alumine and phenolic and was processed through the machines until it became a shiny solid pebble ready to be put into the reactor.

 

From there the Committee was taken to a simulation reactor where it was explained how the pebbles move and how energy was produced. The PBMR team explained that they have so far met all the safety requirements for the continuation of the PBMR project.       

 

The Committee was then taken to the Helium Test Facility, also known as the control room. Here all the methods and techniques used were tested and validated. As for the pebbles, their diameter density and resistance to corrosion are tested.

 

The PBMR executive team could not provide reasons for postponing the tabling of their annual report for the 2008/09 financial year. Despite the fact that the postponement was due to a review of PBMR’s business plan, which in itself did not clarify whether the PBMR business plan had indeed been changed.

 

6.7 Recommendations

 

The Committee recommends that the Department of Public Enterprises should embark on a public education campaign, in order to address the misconception about the dangers of Pebble Bed technology and to inform society about the broader objective of PBMR apart from nuclear energy.

 

Report to be considered