Report of the Portfolio Committee on Provincial and Local
Government on an oversight visit to the 2010 FIFA Soccer World Cup host cities
namely Nelspruit, Johannesburg and Port Elizabeth,
dated 25-31 May 2008
The delegation from the Portfolio
Committee on Provincial and Local Government was made up of the following: Mr.
S L Tsenoli (ANC - Chairperson), Mr. R Sonto (ANC), Mr S Mshudulu (ANC),
Mr. B M Solo (ANC), Nkosi M Nonkonyane
(ANC), Mr W Doman, (DA), Ms M Mdlalose
(NADECO), Ms Judy Crowster (Committee Assistant), Mr
S Ngxiza (Parliamentary Researcher), Mr A Macanda (ANC Researcher) and Mr L Nxelewa
(Committee Secretary).
Mbombela
municipality reported that other activities that are construction-related for
the 2010 Soccer World Cup were predominantly work in progress and others are
completed.
The completion programme was scheduled as follows:
·
Appointment of Consultants April
2006
·
Approval of Funding December
2007
·
Appointment of Contractor January
2007
·
Start of Earthworks February
2007
·
Start of Piling April
2007
·
Start of Structure June
2007
·
Start of Roof Installation May
2008
·
Early Finish of Construction March
2009
·
Late Finish of Construction May
2009
·
Current Projected Completion May
2009
The progress in
preparation for 2010 Soccer World cup was being hindered by the following
factors:
Observations and recommendations made by the Delegation
The major concern of the
delegation was the lack of implementation of the Disaster Management Act. The
delegation discovered that the intentions of the Act were misconstrued. The
delegation applauded the large-scale involvement and collaboration of
government structures and stakeholders but was concerned about insufficient
communication and cooperation resulting in delays in some projects. The
delegation recommended that, it would be significant to engage the House of
Traditional Leaders in preparations so as to ensure that 2010 FIFA Soccer World
Cup was a true reflection of
D. Meeting
and Oversight Visit to Disaster Management at Nelspruit
Fire Station
Pursuing what was presented in the
meeting with Municipal Manager; Administrator and stakeholders involved in Mbombela Civil Centre, the delegation visited the Disaster
Management Centre. Owing to the information that the establishment visited was
an interim Disaster Management Centre; it was reported that a site has been
handed over to the municipality where a permanent Disaster Management Centre
would be built. It was further reported that the municipality had undertaken
wholesale awareness campaign aimed at educating members of the community about
possible disaster occurrences. District volunteers were trained in terms of
risk assessment. There was cooperation
with SANDAF where the community was being capacitated on the technical side.
The following were challenges faced
by the disaster management centre:
Recommendations
E. Visit to
Mbombela stadium
The delegation visited the stadium
in
Questions
of the delegation were around the following issues:
Construction
of the stadium
It was reported that the plan was to
work night shifts in order to fast track the construction of the stadium.
Other materials were produced on the
site e.g. concrete. Forty six thousand people (46000) would be carried by the
stadium after completion. The target for completion was May 2009. Every week
meetings were being held in order to ensure that employees were working under
safe conditions. It woudl take 3 to 4 months to grow
grass that would be rolled-over to the pitch. There were currently four student
engineers on the site. There are eight
independent exits to ensure quick evacuation in cases of emergencies.
Owing to the number of exits, it would
take approximately took 4 to 5 minutes to evacuate people from the stadium.
Wide concrete walls were designed for people with disabilities. It was a FIFA
requirement to have generators in the stadium as an alternative source of
power. One fifty hundred Million Rand project was in place to resolve water
problems. Supply water pipeline would be built kilometers
from the stadium. That water will be adequate for the community use as well as
other development plans for the area. Fifty to sixty women were employed out of
850 male employees. In order to balance gender in the workplace, there were
training centers in the stadium that offer different
skills. Most of the material utilized was sourced locally specifically from Mbombela. LOC (Local Organizing Committee) had complemented
the construction company as one having 90% material sourced locally.
F. Meeting
in K’shani Game Reserve at
The questions of the delegation were
around the following issues:
Successes
and challenges in preparations for 2010
It was reported that there was
progress regarding construction of the Mbombela
stadium.
Disaster management framework had
been finalized and it would help address some of the challenges experienced.
The framework was also looking at
the man-made risks e.g. xenophobia.
Five officials had been appointed to
look at disaster management issues.
Political and technical forums were
in a position to address issues of integration and coordination.
Challenges
Observations
and recommendations made by the Delegation
The delegation observed that there
was generally lack of communication among the structures of government and
stakeholders involved. The delegation was alarmed by the apparent slow pace of
implementing the Disaster Management Act since it was promulgated. The
committee explained that people’s lives were being placed at risk by not prioritizing Disaster Management Act and by providing
disaster management a conservative budget. The delegation emphasized the
recognition of indigenous languages in preparation for 2010.
Partnership should be enjoyed by all
stakeholders and structures of government involved. All those involved must
guard against after event consequences. There should be cooperation among
structures of government starting from national, provincial and local level
within the spirit of cooperative governance. The Disaster Management Act must
be implemented immediately and effectively. This legislation should be given a
place it deserves in the interests of the communities.
Renewable energy should be prioritized at local level and this must be placed high on the
agenda.
The water issue was critical. The
Portfolio Committee would make recommendations and provide a feedback to the
If that can be done:
In this regard DPLG (Department of
Provincial and Local Government) had been requested by the Portfolio Committee
on Provincial and Local Government to set up a multilingualism conference which
would deal with language issues.
G. Meeting with Johannesburg 2010
Project Office and Disaster Unit (
The Municipal Manager Ms Nandi Mayathula Khoza welcomed the
delegation. She informed the delegation that the City of
·
To
fulfill the FIFA contractual requirements.
·
To
deliver an outstanding fan experience.
·
To
create a long lasting legacy for the benefit of the City of
Afterwards she gave an opportunity to Sibongile,
Mazibuko, and Executive Director of 2010 to make a
presentation.
Success and challenges
in preparation for 2010
To ease implementation of the plans, the Mayor had appointed
officials who would work together to come up with consolidated and coherent
method for the City of
In terms of stadium construction:
·
The
roof in Arlando stadium was 92% completed.
·
Target
of the completion is April 2009.
·
Orlando
Stadium is 81% completed
·
There
was a major upgrade on this Dobsonville stadium.
·
In
·
Gautrain project was moving at an alarming pace.
In terms of marketing:
·
Municipality
identified several fan parks.
·
Marketing
strategy was finalized and signed.
In addition the municipality has developed its own website
and appointed members who were updating it on a regular basis. Regarding
accommodation, 8 New Hotels have been constructed and contracting with those
hotels has been finalized. The City has approved tourism and beautification
strategy. Implementation of the Disaster Management Act was reported as being
challenge. Issue of personnel was attributed to this problem. There was no full
operational centre. The city was targeting 2009 to
have a full operational centre.
The questions of the delegation were around the following
concerns:
·
Local
content;
·
Economic
opportunities;
·
Relationship
with institutions of learning;
·
Language;
·
Intergovernmental
relations;
·
Whether
stadiums have conducive sitting arrangements;
·
Participation
of youth in the townships;
·
Xenophobia
issue;
·
Transport;
·
Showcasing;
·
Volunteers;
·
Maintenance
of facilities beyond 2010;
·
Interaction
with other countries hosted world cup;
The delegation was promised a memorandum that would be responding to these questions.
H. Oversight visit to
sporting facilities (including, Soccer City/Orlando stadium)
The construction of this stadium was at an advance stages.
Most of the employees on the site were from
There was a new tunnel that led to facilities for teams and
VIP’s. A second tunnel has been added for vehicle utility. There were 1500 women and men staff on the site.
Recommendations and
observations made by delegation.
·
The
Committee recommends that integration plans must be clear;
·
There
should be communication among stakeholders involved;
·
The
Disaster Management Act must be implemented immediately and effectively;
·
Intergovernmental
relations needed to be emphasized on;
·
2010
FIFA Soccer World Cup should be linked to past and current events;
I. Meeting with SALGA
at Braampark (
Mrs. Kwazi Mazibuko,
Municipal Service Manager welcomed and thanked the delegation for the visit and
allowed the chairperson of the Portfolio Committee to give a brief about the
objectives of the oversight visit. Afterwards she gave an opportunity to Ms Masuluke to make a presentation.
Success and challenges
in preparation for 2010
There was coordination and cooperation with the non-hosting
municipalities. In this regard the municipality was working with non-hosting
municipalities in terms of showcasing. SALGA has developed a framework which
endeavored to ensure that hosting 2010 FIFA Soccer World Cup would leave a
lasting legacy for the country and
In terms of disaster management, an Emergency Centre was launched in November 2007 and the municipality
is in a process of launching a communication number. All 40 municipalities in
The following were disaster
management figures provided to Municipal Demarcation Board for 2008-2009:
·
·
Braamfontein municipality -
141000 in 1 staff member.
·
Mitswedimbe municipality -1,
9 million in the staff of 2
·
Kungwini municipality
-347 000, 48 staff but it was debatable because it included fire
fighting.
Challenges in respect of the disaster management:
·
Shortage
of personnel;
·
Institutional
arrangements;
·
People
driving disaster management issues are juniors thus have no decision making
authority;
·
Financial
allocations need to be taken into serious consideration;
·
IGR
structures need to be functional and operative;
·
Poor
implementation of Know Your Municipality Project;
Observations and
recommendations made by the delegation
There should be no confusion between emergency services and
disaster management. Disaster Management Act needs to be implemented
consistently and effectively. Institutional arrangement was clear in the
legislation in terms of where it should be, and how it should be structured. To
avoid conflicts, one should look at sectoral forums
in which stakeholders are involved. The delegation mentioned that, through-out the provinces
visited; local communities were not part of the proceedings. Lack of access to
information has contributed to the delays. Local communities should be engaged
in the process. If the communities and stakeholders were not handled properly
there was a high risk of challenges. Public participation needed to be enhanced
in what ever means necessary. The xenophobia issue needs to be put on the top
of the agenda.
J.
Breakfast with SALGA at Kings Beach Hotel (
Mr. Mlungisi
Mvoko, Deputy Chair of SALGA welcomed and thanked the
delegation for the oversight visit. He gave an opportunity to Mr. Magwanqgana, Deputy CEO of SALGA, to make a presentation.
Success and
challenges
Within the
Challenges that are facing SALGA in
the
Observations
and recommendations made by the delegation
The delegation was very much
concerned about the following issues:
There should be a cooperation to
ascertain what needed to be done to address these challenges
K. Meeting with Nelson Mandela 2010
Project (inc. Mayor/Municipal Manager/stakeholder)
Mr. Mike Kwanaite,
Counselor, welcomed and thanked the delegation for
their oversight visit and gave an opportunity to the Chairperson of the
Portfolio Committee on Provincial and Local Government to outline the
objectives of the oversight visit. Thereafter Mr. E Heyns,
Executive Director for 2010 project took the committee through a presentation.
Success and
challenges in preparation for 2010
At the national and local level, there
were monthly meetings in which structures involved report to.
The main focus was on the
construction of the stadium to meet the time frames. Construction programme
showed that, the stadium would be completed by December 2008. By the same month
all construction work would be completed. Concrete was produced on the site and
was of high quality. Roof would be completed by the end of December 2008 and
middle of January 2009. City regeneration, disaster management, and enforcement
of rights, volunteer programme, infrastructure and environmental impact
assessment are the main focus areas. In relation to intergovernmental
relations, at a provincial level there was a Provincial Coordinating Committee
(PCC) in which all stakeholders are involved. There was a political forum in
which Mayors, officials and political leaders met to engage on critical
matters.
The challenges that were facing Nelson Mandela Metro were around the
following issues:
Observations
and recommendations made by the delegation
The delegation was much concerned
about the following issues:
The delegation recommended that intergovernmental
relations were very important for the success of 2010. That it must be
maintained and be prioritized beyond 2010. There was
a need for the municipality to develop an internal communication system.
L. Meeting
with Disaster Unit and Tour of Facility
Mr. Shadrack
Sibiya, Assistant Director of Safety and Security,
welcomed and thanked the delegation for the oversight visit mentioning that it
would bring some improvement in prepare for 2010. He then handed over to Henry Lansdown to make a presentation.
Success and
challenges in preparations for 2010
There were 6 satellite disaster
management facilities responsible for the whole metro in cases of disasters.
There was satellite Control Centre operating 24 hours and provides a back up to
Disaster Management Centre in cases of huge disasters. There was a policy
framework that has been developed. Its first draft has been distributed for
public comment. It served as a guideline for the development, uniform
implementation and integrated disaster management plan and policy. There was a
Disaster Management Advisory Forum. Mobile communication would be completed by
June 2008.
Challenges:
Observations
and recommendations made by the delegation
Through out the entire presentation
the delegation was concerned about the following issues:
The delegation recommends as
follows:
M. Visit to sporting facility (PE stadium)
Success and
challenges
N. TOWARDS MORE EFFECTIVE OVERSIGHT
In
all sections of this report, the Portfolio Committee has identified issues that
it believes should be acted on by different role-players. The major tasks
identified are for DPLG and respective municipalities to attend to. The
Portfolio Committee recognizes that DPLG has a wide range of responsibilities,
and limitations of funds, resources and staff. Moreover, local government was a
sphere of government in its own right, and there were limits to how far DPLG
could intervene. The Portfolio Committee is not suggesting that all the many tasks
identified in this report should be attended to immediately. However, over
time, with due recognition of the constraints, the Committee believes that
action should be taken on these issues. We will discuss with the department
what is practically possible, and we will, over time, actively monitor
developments in this regard and as and when appropriate conduct follow-up
meetings.
Other
national departments, provincial departments of local government, and other
provincial departments, SALGA, community organizations, trade unions, the
private sector and other stakeholders have a crucial role to play as well. So
too, do parliament and the legislatures, and in particularly Portfolio
Committee. We, in fact, need to do more. But so too do the municipalities, they
simply cannot become over-reliant on other spheres of government and other
role-players.
We would send copies of
the report to all the affected municipalities in the country and seek to ensure
that all those we interacted with during the oversight visit receive a copy of
the report. We would also send the report to other stakeholders.
The
Committee conveys its appreciation to the Ministry, Department and all the
statutory bodies and respective municipalities that participated in the oversight
for their co-operation. Almost all municipalities were extremely co-operative
and received us very warmly. We convey our sincere appreciation to them.
The
organizational details of our oversight were dealt with by our outstanding
committee secretariat and to them we express our gratitude.
We
also like to thank the researchers who accompanied the delegation on the
oversight visit for their research support and background work which was useful
in drafting this final report.
Report
to be considered