Report of the
Select Committee on Finance on the oversight visit to
Background
On 22 and 23 January 2008, the Select Committee on
Finance held hearings with provincial departments on conditional grants capital
expenditure for the first three quarters of the previous financial year. The Committee had concerns on a number
of issues following the hearings and decided to have further meetings with the
following departments:
Delegation
The meetings were held in the
The Committee observed the following issues:
·
Poor
planning by both the Department and municipalities. Some of the approved
projects were still not ready for implementation.
·
Some of
the emerging contractors lack capacity and there was a small pool of
established contractors attracted to low cost housing resulting in the need to
re-tender. Established contractors were not attracted to rural development
projects due to logistical issues and the additional cost of transporting
material. Established contractors were supposed to mentor emerging contractors.
·
The
slow start of the rectification programme was a cause for concern. There was a
lot of unfinished work that needed to be redone. There was also the issue of
community housing that had been inherited from
·
The
land restitution process did not prevent development but the department needed
to consult with the Land Claims Commissioner to determine whether or not the
development interfered with the claim. It was reported that problems arose in
cases where the development did not benefit the community as a whole.
Communication with the community prior to the development was critical. Road
shows to municipalities regarding this matter had been conducted but it was
reported that changes in the councils might have led to knowledge gaps.
·
There
was a need to provide land for sustainable human livelihoods.
·
There
was some misalignment of the Municipal Infrastructural
Grant (MIG) and the housing grant. Reasons for this included the discrepancy in
percentage growth in the allocation between housing and MIG, the conditions of
the grants and the identification of priorities by the province and the
subsequent allocation of the grants by the Department of Provincial and Local
Government.
·
The
meeting was informed that one could still find cases where houses had been
built without the necessary supporting bulk infrastructure. There was a need
for an integrated approach to development.
·
The
capacity of the provincial Department of Housing remained a challenge and slow
moving projects would be taken back by the Department of Housing.
·
The
department also reported that all contractors were meant to be NHBRC approved
and CIDB compliant but this was taking long owing to lack of capacity at the
NHBRC.
·
The
municipality showed improvement in relation to revenue collection.
·
Electricity
distribution was confined to the Komga area. The
municipality had licences for areas within its municipality but there were
still some problems with Eskom. There was a need for
a smooth handover from Eskom to ensure that there
were no disruptions in service delivery. Eskom
received R500 million from the Department of Minerals and Energy to
re-establish networks in Komga.
·
Refuse
removal was also a big challenge and businesses such as holiday resorts were removing
their own solid waste.
·
The
condition of roads affected service delivery. There was a need for capital
equipment to improve and maintain roads.
·
The
Development Bank of
·
Rural
housing development was engaging Thubelisha to assist
in feasibility study and proposals that would be in line with spatial
development framework.
·
Water
and sanitation were a big challenge for this municipality. There was a need for
assistance in relation to bulk water and water supply projects. There was
almost no information available to determine expenditure and revenue for water
services. The age of water infrastructure reinforced the problem of water
outages.
·
Questions
were raised about the municipality’s ability to spend money. It was said that
the municipality would get support from DBSA in the form of engineers,
technicians & financial advisors.
·
The
district reported that the local municipalities had no records to verify their
asset registers. The municipality had received a disclaimer for the 2006/7
financial year. There was also no proper planning for the refurbishment of
infrastructure.
·
The
Committee undertook to have further discussions with Eskom
regarding electricity distribution.
Recommendation
There should be an ongoing forum where planning issues
are discussed to ensure that stumbling blocks that have a huge impact on
housing are identified and removed early. Each stakeholder should play its role
effectively. All line managers in the forum must attend the meetings.
The Committee resolved that it would convene a meeting
with Department of Water Affairs and Forestry to establish why the Great Kei
Municipality has received only R1 million out of the R3,2 million provided by
the Development Bank of Southern Africa.
Report
to be considered