Office of the Public Protector
(OPP)
Annual Plan
2006/07
June 2006
CONTENTS |
|
Page |
Acronyms |
3 |
|
|
PART ONE. Overview |
4 |
1.1 Programmes Overview |
5 |
PART TWO: Annual Plans |
7 |
2.1 Programme 1: Investigations and Reporting |
8 |
2.2 Programme 2: Communication Services |
14 |
2.3 Programme 3: Corporate Support Services |
18 |
2.4 Programme 4: Knowledge Management and Information Technology |
24 |
ACRONYMS
AORC |
- |
African Ombudsman Research Centre |
CMS |
- |
Case Management System |
CSAP |
- |
Civil Society Advocacy Programme |
EE |
- |
Employment Equity |
EWP |
- |
Employee Wellness Programme |
GEPF |
|
Government Employee Pension Fund |
HRC |
- |
Human Rights Commission |
HRMIS |
- |
Human Resources Management Information System |
ICT |
- |
Information and Communications Technology |
ICD |
- |
Independent Complaints Directorate |
IT |
- |
Information Technology |
KM |
- |
Knowledge Management |
KPI |
- |
Key Performance Indicators |
MP |
- |
Member of Parliament |
MPL |
- |
Member of Provincial Legislature |
NDPP NHBRC |
- - |
National Directorate of Public Prosecutions National Home Building Regulatory Council |
NT |
- |
National Treasury |
OPP |
- |
Office of the Public Protector |
PAJA |
- |
Promotion of Administrative Justice Act |
PDA |
- |
Protected Disclosure Act |
PFMA |
- |
Public Finance Management Act |
PMS |
- |
Performance Management System |
PP |
- |
Public Protector |
PPA |
- |
Public Protector Act |
PSC |
- |
Public Service Commission |
PRO |
- |
Public Relations Officer |
PSCA |
- |
Public Service Commission Act |
SAPS |
- |
South African Police Service |
SCM |
- |
Supply Chain Management |
SDI |
- |
Service Delivery Indicators |
SDS |
- |
Service Delivery Standards |
SLA |
- |
Service Level Agreement
|
|
|
|
PART ONE:
OVERVIEW
1.1. The document outlines the Annual Plan as translated from the 5 year Strategic Plan. It is intensely influenced by the Parliamentary requirements and needs noted during the annual budget reviews and hearings gaps and necessary improvements during the previous year.
1.2. The following questions / queries were raised by Parliament during the 2004/05 budget report hearing held 17 February 2006:
1.2.1. Previous challenges must be clearly addressed by the new strategies / objectives in the new financial year plans
1.2.2. Address how OPP deals with report on cases that are carried forward
1.2.3. OPP should break up the ages of cases and provide statistical data which clearly indicate the turnaround time of each case.
1.2.4. Database of staff compliment should be annexed to the report
1.2.5. Categorization of cases needed
1.2.6. Case/File management system of OPP need to be outlined
1.2.7. Report on Spending on programmes is necessary to enable understanding of financial reporting and improve on systems of financial accountability.
1.3. The 3-year Strategic Plan defines the following programmes for OPP:
Programme |
Sub-Programme |
1.3.1. Investigations and Reporting |
1.4.1.1. National Investigations 1.4.1.2. Provincial Investigations 1.4.1.3. Special Investigations |
|
|
1.3.2. Communication Services |
1.4.2.1. Outreach Programme 1.4.2.2. Marketing and Communications |
|
|
1.3.3. Corporate Support Services |
1.4.3.1. Human Capital 1.4.3.2. Finance and Supply Chain Management 1.4.2.3. Administration Support 1.4.2.4. Security Management |
|
|
1.3.4. Knowledge Management and Information Technology |
1.4.4.1. Knowledge Management 1.4.4.2. Information Technology |
PART TWO:
Annual Plan
2006/07
2.1.1.1 To conduct national, special and provincial investigations that are effective, efficient, informed, timeous and of high quality.
2.1.2.1 Improved service delivery to stakeholders.
Sub-Programmes: ALL (National, Provincial and Special Investigations) |
Responsibilities |
2.1.3.1. To conduct investigations with adherence to SDIs.
|
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.2. To identify and conduct systemic investigations.
|
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.3. To conduct own-initiative investigations.
|
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.4. To develop investigative techniques, processes and training. |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.5. To reduce the turnaround time to a maximum of two years to finalize all cases. |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.6. To conduct file inspections.
|
Public Protector Deputy Public Protector |
2.1.3.7. To ensure effective, relevant reporting in all finalized investigations. |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.8. To monitor and report on remedial actions recommended to organs of state. |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.9. To improve on think-tank committee procedures and processes. |
Executive Manager: Provincial Investigations |
2.1.3.10. To improve on strategic performance reporting. |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
2.1.3.11. To improve the effective and efficient coordination of provincial offices. |
Executive Manager: Provincial Investigations |
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.1.4.1. To Conduct Investigations with adherence to Service Delivery Indicators (SDIs) |
Approved project plans for appropriate investigations / investigation plans for all other cases |
% of project plans for appropriate cases |
Project plans defined for 80% of appropriate cases |
Identify Appropriate investigations , Draft project plan and obtain approval. Draft investigation plan for all other cases. |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
April 2006 to March 2007 |
|
Adherence to approved SDIs aligned with individual performance in accordance with the defined work plans |
% of adherence to SDIs |
80 % of adherence to SDIs |
Review existing SDI’s, align with annual plan and draft new performance agreements |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
June 2006 |
|
|
2.1.4.2. To identify and Conduct Systemic Investigations |
Systemic investigation reports |
Number of systemic investigations undertaken per annum
|
Five (5) systemic investigations |
Identify, compile project plan , obtain approval and undertake systemic investigations |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
April 2006 to March 2007 |
|
2.1.4.3. To conduct own-initiative Investigations |
Own-initiative investigation reports |
Number of own initiative investigations undertaken per annum |
Five (5) own initiative investigations |
Identify, compile project plan , obtain approval and undertake Own initiative investigations |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
April 2006 to March 2007 |
|
2.1.4.4. To develop investigative techniques, processes and training |
Process manual reflecting investigation techniques, remedial action guidelines, checklists, and report writing and procedures |
% manual completion
|
Process manual completed 100%
|
Compile a manual |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
31st March 2007 |
|
2.1.4.5. To reduce the turnaround time to a maximum of two years for finalization of all cases |
Regular statistical report on relevant cases |
% compliance |
60% compliance |
Compile and submit quarterly reports |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
Not later than 2 weeks after the end of the quarter |
|
2.1.4.6. To Conduct File Inspections |
File inspection report |
Number of file inspections |
1 per national and provincial organisation |
Do file inspection and report |
Public Protector Deputy Public Protector |
November 2006 |
|
2.1.4.7. To ensure effective, relevant reporting in all finalized investigations |
Quality report for every finalized case. |
% of reports produced
|
80% of reporting on all finalized cases |
Submit quality reports |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
April 2006 to March 2007 |
|
2.1.4.8. To monitor and report on remedial actions recommended to organs of state |
Remedial action and monitoring Report
|
% of implemented recommendations by organs of state |
50% of recommendations implemented |
Monitor implementations of recommendations and submit quarterly reports |
Control Investigator: National Investigations Control Investigator: Special Investigations Executive Manager: Provincial Investigations |
No later than two weeks after the end of the quarter |
|
2.1.4.9. To improve on Think Tank Committee Procedures and processes |
Full participation by all Think-Tank Committee members |
% participation
|
100% participation
|
Allocations of Think Tank cases to individuals for debates |
Secretariat to the TT (Executive Manager: Provincial Investigations)
|
March 2007 |
|
Think Tank reports submitted |
% “Think Tank Reports[1]” submitted to Think Tank |
40% ““Think Tank Reports” submitted to Think Tank |
Facilitate the process of submitting Think Tank reports. |
Secretariat to the TT (Executive Manager: Provincial Investigations)
|
March 2007 |
|
|
Documented Think Tank Operational Process Manual |
% Completion of Operational Process Manual
|
60% Process Operational Manual completed |
Compile procedure manual for Think Tank |
Secretariat to the TT (Executive Manager: Provincial Investigations) |
March 2007 |
|
|
2.1.4.10. To improve on Strategic Performance Reporting |
Strategy Performance and Statistical Reports
|
Number of meetings and reports |
Quarterly performance meeting and reporting |
Submit Quarterly Reports and attend meeting |
Deputy Public Protector |
4 weeks after the end of the Quarter |
|
Number of meetings and reports |
Annual strategy review meeting and reporting |
Meeting to review strategic plan |
Deputy Public Protector |
November 2006 |
|
||
Number of meetings and reports |
Annual reporting to Parliament
|
Submit Annual Reports and attend meeting |
Deputy Public Protector |
July 2006 |
|
||
2.1.4.11. To improve the effective and efficient coordination of Provincial Offices |
Executive Manager: Provincial Investigations appointed |
Appointment of Executive Manager: Provincial Investigations |
100% Appointment of Executive Manager: Provincial Investigations |
Interview process Appointment of Executive Manager |
Public Protector |
July 2006 |
|
Provincial Coordination Process Manual |
% Provincial Process Manual completed and implemented |
60 % Provincial Process Manual completed |
Compile a manual |
Executive Manager: Provincial Investigations |
March 2007 |
|
2.2.1.1. To improve internal and external communication to inculcate a common vision and improved profile for the OPP.
2.2.2.1. Improved Stakeholder perception, co-operation and accessibility of OPP services.
2.2.2.2. Smooth, timeous flow of accurate information to all OPP staff.
Sub-Programme: Outreach Programme |
Responsibility |
2.2.3.1 Increase accessibility to OPP services 2.2.3.2. Increase Public Awareness 2.2.3.3. Enhance collaboration with stakeholders |
Communications Manager Executive Manager: Provincial Investigations |
Sub-Programme: Marketing and Communications |
|
2.2.3.4. Improve communication and routing of information to stakeholders 2.2.3.5. Effective Communication to internal staff 2.2.3.6. Improve Media Relations 2.2.3.7. Develop the branding of the OPP 2.2.3.8. Inculcate Protocol knowledge within OPP |
Communications Manager |
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.2.4.1. Increase accessibility to OPP services |
Outreach strategy |
% Outreach strategy development and implementation |
80% Outreach strategy development and implementation |
1. Draft Outreach Strategy; 2. Consult; 3. Finalise & adopt; 4. Co-ordinate Implementation Plan |
Communications Manager Executive Manager: Provincial Investigations |
Mar 2007 |
|
Clinics conducted |
Clinics conducted |
Four clinics per province |
1. Identify areas / MPCC’s; 2. Publicize dates & venues; 3. Conduct clinics; 4. Evaluation |
Communications Manager Executive Manager: Provincial Investigations |
Monthly
|
|
|
Additional regional office established |
Additional offices established |
Two additional regional offices established |
1. Needs analysis; 2. Facilitate approval process. 3. Establish 2 regional offices |
Communications Manager Executive Manager: Provincial Investigations |
Mar 2007 |
|
|
2.2.4.2. Increase public awareness |
Information sessions with stakeholders |
Number of Information Sessions / Workshops |
Five information sessions per province |
1. Identify the need for information sessions; 2. Identify audience; 3. Conduct information sessions |
Communications Manager Executive Manager: Provincial Investigations |
June 2006 – March 2007 |
|
2.2.4.3. Enhance collaboration with stakeholders |
Chapter 9 Collaboration Plan |
% Completion of Chapter 9 Collaboration Plan |
100% Collaboration Plan completed |
1. Draft Collaboration Plan; 2. Consult; 3. Finalise and adopt;
|
Communications Manager Executive Manager: Provincial Investigations |
Mar 2007 |
|
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.2.5.1. Improve communication and routing of information to stakeholders |
External communication strategy development and implementation |
% external communications development and implementation |
100% of external communication strategy developed |
1. Draft Communication Strategy; 2. Consult; 3. Finalise & adopt; |
Communications Manager |
December 2006 |
|
2.2.5.2. Effective communication to internal staff |
Internal communication strategy development |
% internal communications development and implementation |
100% of communication strategy developed |
1. Draft Communication Strategy; 2. Consult; 3. Finalise & adopt; |
Communications Manager |
December 2006 |
|
2.2.5.3. Improve media relations |
Media strategy development |
% communications development and implementation |
100% of media strategy developed
|
1. Draft Media Strategy; 2. Consult; 3. Finalise & adopt; |
Communications Manager |
December 2006 |
|
2.2.5.4. To enhance the image of the OPP |
Identifiable branding of the OPP |
% branding achievement |
100% of branding strategy developed |
1. Draft branding strategy; 2. Consult; 3. Finalise & adopt; |
Communications Manager |
December 2006 |
|
2.2.5.5. Inculcate protocol knowledge within the OPP |
Staff trained on protocol |
% training achievement |
40% of staff trained |
1. Identify staff; 2. Identify service provider; 3. Facilitate training |
Communications Manager |
Mar 2007 |
|
2.3.1.1. To achieve and sustain an efficient and effective corporate support service that is compliant with legislation.
2.3.2.2. Improved service delivery.
Sub-Programme: Human Resources Management and Development |
Responsibility |
2.3.3.1. Attraction, maintenance and retention of high-quality staff. 2.3.3.2. To improve and sustain HR performance management system. 2.3.3.3. Training and development of staff according to needs. 2.3.3.4. Facilitating the design utilization of an EWP and achieving transformation, equity and diversity. |
Human Resources Manager |
Sub-Programme: Finance and Supply Chain Management |
Responsibility |
2.3.3.5. To develop a costing model for investigations 2.3.3.6. Improve OPP financial management and reporting 2.3.3.7. Ensure compliance of OPP with financial prescripts 2.3.3.8. Develop and implement cost-effective procurement processes
|
Accounting Officer CFO Control Investigator: National Investigations (Only for 3.4.3.5) Control Investigator: Special Investigations (Only for 3.4.3.5) Executive Manager: Provincial Investigations(Only for 3.4.3.5) Supply Chain Manager |
Sub-Programme: Administration Support |
|
2.3.3.9. To enable the optimum application and utilization of resources 2.3.3.10. To promote the effective and efficient functioning of the registry 2.3.3.11. To establish and maintain suitable office accommodation |
Accounting Officer |
Sub-Programme: Security Management |
|
2.3.3.12. To establish and implement processes for the protection of OPP information and assets |
Security Manager |
2.3.3.13. To provide secure premises and a safe working environment for staff. |
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.3.4.1. Attraction, maintenance and retention of high-quality staff |
Human Capital Sourcing Strategy and implementation |
% Human Capital Sourcing Strategy development and implementation |
100% of Human Capital Strategy developed
|
Undertake human capital sourcing forecast
Review OPP service conditions and benefits
|
Human Resources Manager |
August 2006 |
R60 000 |
Remuneration strategy / policy and implementation |
% remuneration strategy/policy development and implementation |
100% of remuneration strategy/policy developed |
Finalase JD’s and JE’s
Submission of report to the Minister of Finance and Parliament |
Human Resources Manager |
July 2006
October 2006
|
R60 000
R10 000 |
|
2.3.4.2. To improve and sustain the HR performance management system |
Outcome-based Performance Management System |
% Implementation of Outcome-based Performance Management System |
Review system and recommend an instrument for outcome-based performance |
Review the existing system
Monitor the system |
Human Resources Manager |
August 2006 |
|
2.3.4.3. Training and development of staff according to needs |
Human Resources Development (HRD) Strategy developed and implemented |
% HRD Strategy development and implementation |
100% of HRD strategy developed and implemented |
Complete and submit skills audit report
Develop and implement training plan |
Human Resources Manager |
March 2007 |
|
2.3.4.4. Facilitate the design and utilization of an EWP and achieve transformation, equity and diversity |
Accessible, functional and utilized EWP |
% of staff utilizing EWP |
0% - Design of strategy and wellness programme |
To research design, consult and implement an EWP strategy
To research design, consult and implement a transformation strategy |
Human Resources Manager |
October 2006 |
|
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.3.5.1. To develop a costing model for investigations |
Costing model developed |
% of costing model developed and implemented |
Costing model partly developed |
Define levels of complexity for cases received
Identify investigative staff to be used for each level |
Head: National Investigations Head: Special Investigations Provincial Co-ordinator CFO |
March 2007 |
|
2.3.5.2. Improve financial management and reporting |
Financial management policies developed and implemented |
% of financial policies implemented |
80%of financial policies implemented |
Develop and implement financial manuals |
CFO
|
September 2006 |
|
Divisional budgets |
% of divisional budget implemented |
30 % of divisional budget implemented |
To implement and monitor divisional budget processes |
CFO
|
March 2007 |
|
|
2.3.5.3. Ensure compliance with financial prescripts |
Unqualified audit reports |
% compliance |
100% compliance |
Review of internal controls and risk management plan |
CFO |
March 2007 |
|
2.3.5.4. Develop and implement cost-effective procurement processes |
Cost-effective procurement processes implemented |
% implemented |
100 % of implementation |
Review and improve current procurement processes |
SCM |
September 2006 |
|
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.3.6.1. To enable the optimum application and utilization resources |
Vehicle monitoring system |
% implementation of vehicle monitoring system |
100% implementation |
Review operational monitoring measures |
Senior Manager: Administration |
March 2007 |
|
Telephone management system |
% implementation of telephone management system |
100% implementation |
Review operational monitoring measures |
Senior Manager: Administration |
March 2007 |
|
|
2.3.6.2. To promote the effective and efficient functioning of the registry |
Records management system |
% implementation of records management system |
60% implementation |
Implement CMS
Compliance with National Archives Act |
Senior Manager: Administration |
March 2007 |
|
2.3.6.3. To establish and maintain suitable office accommodation
|
Office established |
Number of offices established |
Two additional regional offices |
2 additional Regional Offices |
Senior Manager: Administration |
March 2007 |
|
Office relocated |
Office to be relocated |
Mafikeng and Western Cape |
Identify suitable office space |
Senior Manager: Administration |
March 2007 |
|
|
Storerooms established |
Storerooms to be established |
Storerooms established – Northern Cape and Eastern Cape |
Engage Public Work to amend the lease |
Senior Manager: Administration |
March 2007 |
|
Strategic Objective |
Outputs |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.3.7.1. To establish and implement processes for the protection of OPP information and assets |
Strategy, policies and procedures |
% development and implementation |
60% development of policies and procedures |
To develop a security management strategy, policies and procedures
Consult and visits to offices to assess needs and gaps
|
Manger: Security |
March 2007 |
|
2.3.7.2. To provide secure premises and a safe working environment for staff |
Strategy, policies and procedures |
% development and implementation |
60% development of policies and procedures
|
To develop a security management strategy, policies and procedures Consult and visits to offices to assess needs and gaps
|
Manger: Security |
Mar 2007 |
|
2.4.1.1 To introduce and maintain efficient and effective knowledge management and information and communications Technology within the OPP.
2.4.1.2 Efficient and effective service delivery to stakeholders.
Sub-Programme: Knowledge Management |
Responsibility |
2.4.3.1. Create Knowledge Management Institution of the OPP |
Researcher Deputy Public Protector (Interim) |
2.4.3.2. Establish and Migrate AORC |
|
2.4.3.3. Implement Exchange Programme |
|
Sub-Programme: Information and Community Technology |
|
2.4.3.4. To implement and enhance integrated information management systems. |
ICT Manager |
2.4.3.5. Building and enhancing ICT infrastructure that is reliable, secured and interoperable |
|
2.4.3.6. Improving and implementing ICT best practices |
Strategic Objective |
Output |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.4.4.1. Create a knowledge management institution for the OPP |
Knowledge and Research Manager appointed |
Appointment of Knowledge and Research Manager |
Appointment of Knowledge and Research Manager |
Review the post |
HR Manager |
March 2007 |
|
Knowledge audit conducted |
% of audit conducted |
100% of audit conducted |
Questionnaires |
Deputy Public Protector |
March 2007 |
|
|
Knowledge management strategy implemented |
% of KM strategy developed and implemented |
100% of strategy developed |
Development of strategy |
Deputy Public Protector |
March 2007 |
|
|
Research conducted |
Continuous research |
Continuous research performed |
Continuous research |
Deputy Public Protector |
March 2007 |
|
|
2.4.4.2. Establish and migrate AORC |
AORC established |
% of AORC established and migrated |
100% of AORC established |
Launch AORC |
Public Protector |
March 2007 |
|
2.4.4.3. Implement exchange programme |
Information being shared with other ombudsman offices |
% of exchange programme implemented |
50% of exchange programme implemented |
Needs Analysis Draft Programme Implement |
Deputy Public Protector |
March 2007 |
|
Strategic Objective |
Outputs |
Measure |
2006/7 Target |
Activities |
Responsibility |
Due Date |
Cost |
2.4.5.1 To implement and enhance Integrated Information management Systems. |
Case Management System |
% Implementation |
50% Implementation |
· Mapping of processes and system deliverables · System development · User training · Data conversion and migration · Implementation of a system · Maintenance and user support |
ICT Manager |
March 2007 |
R1M |
Dictaphone Interpretation System
|
% Implementation |
20% Implementation |
Procurement of hardware and Software Setup of workstations Training of the user |
ICT Manager |
December 2006 |
|
|
e-Procurement System
|
% Implementation |
100% implementation |
Customization of software for OPP needs Upgrade of server |
ICT Manager |
March 2007 |
|
|
Precedent System
|
% Implementation |
Review of the Researcher post |
Review of the Researcher post |
HR Manager |
March 2007 |
|
|
Enhanced Security System |
% Implementation |
50% implementation |
Upgrade of security software |
ICT Manager |
December 2006 |
|
|
Library management system |
% Implementation |
Needs Analysis |
Conduct Needs Analysis Develop recommendations |
ICT Manager |
March 2007 |
|
|
Enhanced HRMIS
|
% Implementation |
Audit of HRMIS |
Auditing of HRMIS |
ICT Manager |
December 2006 |
|
|
2.4.5.2. Build and enhance ICT infrastructure that is reliable, secured and interoperable |
Network Availability |
% Availability |
100% availability |
Installation of network hardware in new offices |
ICT Manager |
December 2006 |
|
Upgrade of Servers and Software, including Jutastats |
% Upgrade |
100% upgrade |
Assessment of servers Upgrade of hardware software and setup |
ICT Manager |
December 2006 |
|
|
Remote Connection to the office Network |
% implementation |
50% implementation |
Develop policies and procedures Implementation |
ICT Manager |
December 2006 |
|
|
Intranet |
% implementation |
20% Implementation |
Assess different intranet options |
ICT Manager |
September 2006 |
|
|
2.4.5.3 Improve and implement ICT best practices |
Policies, standards and procedures |
% Development and Implementation |
100% Development |
Appointment Senior IT Manager Draft approval and publication |
ICT Manager |
November 2006 |
|
Business Continuity Plan |
% Development and Implementation |
50% Development |
Implementation |
IT Manager |
December 2006 |
|