Office of the Public Protector

(OPP)

 

Three-Year Strategic Plan

01 April 2006 – 31 March 2009

 

 


June 2006


 

About the Office of the Public Protector

 

The South African Office of the Public Protector (OPP) was established in 1995 in terms of Chapter Nine of the Republic of South Africa Act, No. 108 of 1996. Its additional mandate is further provided for in the Public Protector Act, No. 23 of 1994, as amended. The primary objective of Chapter Nine institutions, including the OPP, is to strengthen constitutional democracy. The OPP fulfils its mandate by investigating, either at its own initiative or on receipt of complaints from aggrieved persons, allegations of improper conduct by organs of the State. The OPP has the power to report and recommend remedial action.

 

The core business of the OPP is:

1.       To investigate any conduct in State affairs or in the public administration in any sphere of government that is alleged or suspected to be improper or to result in impropriety or prejudice.

2.       To mediate, negotiate, conciliate, report and recommend remedial actions.


 


CONTENTS

 

 

Page

Acronyms

4

Definitions and Terms

5

 

 

PART ONE: INTRODUCTION

6

1.1 The Public Protector’s Overview

7

 

PART TWO: STRATEGIC OVERVIEW

10

2.1 Vision

11

2.2 Mission

12

2.3 Core Values

12

2.4 Legislative Framework and Mandate

13

2.5 The OPP Core Business Model

14

2.6 High-level Organisational Structure

15

2.7. SWOT Analysis

16

2.8 Key Stakeholders and their Needs

20

 

PART THREE: ORGANISATIONAL STRATEGY

24

3.1 Outline of Programmes and Sub-Programmes

25

3.2 Programme 1: Investigations and Reporting

26

3.3 Programme 2: Communication Services

32

3.4 Programme 3: Corporate Support Services

35

3.5 Programme 4: Knowledge Management and Information Technology

41

 

PART FOUR: PROPOSED ORGANISATIONAL STRUCTURE

44

 

PART FIVE: CONCLUSION

54

 


 

ACRONYMS

AORC

-

African Ombudsman Research Centre

CMS

-

Case Management System

CSAP

-

Civil Society Advocacy Programme

EE

-

Employment Equity

EWP

-

Employee Wellness Programme

GEPF

-

Government Employee Pension Fund

HRC

-

Human Rights Commission

HRMIS

-

Human Resources Management Information System

ICT

-

Information and Communications Technology

ICD

-

Independent Complaints Directorate

IT

-

Information Technology

KM

-

Knowledge Management

KPI

-

Key Performance Indicators

MP

-

Member of Parliament

MPL

-

Member of Provincial Legislature

NDPP

-

National Directorate of Public Prosecutions

NHBRC

-

National Home Building Regulatory Council

NT

-

National Treasury

OPP

-

Office of the Public Protector

PAJA

-

Promotion of Administrative Justice Act

PDA

-

Protected Disclosure Act

PFMA

-

Public Finance Management Act

PMS

-

Performance Management System

PP

-

Public Protector

PPA

-

Public Protector Act

PSC

-

Public Service Commission

PRO

-

Public Relations Officer

PSCA

-

Public Service Commission Act

SAPS

-

South African Police Service

SCM

-

Supply Chain Management

SDI

-

Service Delivery Indicators

SDS

-

Service Delivery Standards

SLA

-

Service Level Agreement

 

 

DEFINITIONS AND TERMS

 

 

 

Core Values:

Principles that guide the OPP to deliver quantitative services.

 

 

Key Performance Indicator:

Indicates the extent to which objectives have been achieved.

 

Impact:

The final effect realized by stakeholders upon delivery of the programme.

 

 

Mission Statement:

A statement that answers questions about why OPP exists, whom it serves and what value it delivers.

 

 

 

Objective:

Defines what needs to be achieved in order to fulfil the Programme. Must be SMART (Simple, Measurable, Achievable, Relevant, Time-Based).

 

 

Outcome:

Defines the overall impact after achieving the objectives defined for the Programme.

 

 

Output:

Defines the end results, i.e. Tangible Deliverable expected from the objectives.

 

 

 

Programme:

What needs to be achieved In order to achieve our mission and vision. Also referred to as Key Focus Areas, Strategic Result Areas, Goal. Programme is a term used by the National Treasury and is linked to Budgeting.

 

 

 

Targets:

Defines the quantitative or qualitative level of measuring and should be expressed in terms of time, cost, percentage, quality, quantity, rates or benchmark.

 

 

Vision Statement:

The statement that reflects future intent, referring to the level of growth and success.

 

 

 

 

 

 

PART 1:

 


INTRODUCTION

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.              THE PUBLIC PROTECTOR’S OVERVIEW

 

1.1.       The Office of the Public Protector adopted a five-year strategic plan in the financial year 2005/2006. The new medium-term expenditure framework (MTEF) requires a planning horizon of three years. This strategic plan therefore covers years 2006 – 2009 as per the guidelines provided by the National Treasury.

 

1.2.       In our annual report for 2005/2006, we shall outline our achievements, based on the targets set for the past financial year. We have certainly achieved most of our goals, and this strategic plan aims at defining improved targets for the next three years. Below are the highlights of the achievements from the previous year’s strategy:

 

1.2.1.          The OPP has moved from an emphasis in getting redress for complaints to identifying the root causes and thus contributing to good governance as the probability of recurrence of similar cases is being minimised.

1.2.2.          The OPP has formulated, adopted and implemented the most important internal policies.

1.2.3.          The investigators have improved their investigative skills and processes by conducting physical investigations instead of  just writing letters.

1.2.4.          The OPP’s offices have extended to other towns and additional clinics have been established, thus improving the accessibility of  OPP services.

1.2.5.          The OPP outreach programme includes road shows presented to  government bodies, etc. and an improved advocacy strategy is used to ensure awareness. This has resulted in increased awareness and, in some of the provincial offices of the OPP, in an increase in the number of cases received.

1.2.6.          The internal business processes and information technology have improved and the OPP now has a website.

12.7.           Issues about the discrepancy of salaries between employees who were deployed from the Department of Justice and those directly employed by the OPP have been resolved and staff morale has generally improved (hybrid employment).

1.2.8.          Most staff members are now full members of the Government Employee Pension Fund (GEPF) and have an option to join the GEPF or Provident Fund.

1.2.9.          We have started the process of identifying areas of collaboration with Chapter 9 institutions.

1.2.10.        We are jointly (HRC, CGE and OPP) implementing the Civil Society Advocacy Programme funded by the European Union.

1.2.11.        The OPP has conducted several systemic investigations as projects aimed at  addressing operational deficiencies.

1.2.12.        The OPP has reviewed relevant pieces of legislation and suggested amendments for areas of improvement, e.g. the Protected Disclosures Act, 2000.

 

1.3.       It is important to note that the mandate of the OPP, as defined in the Act, remains the same, and that therefore the strategy does not deviate much from  previous strategies.

 

1.4.       Over the next three years, we shall continue to assist Parliament in strengthening constitutional democracy through the following four key strategic goals:

 

1.4.1.          Efficient and effective investigations

1.4.2.          Corporate support services

1.4.3.          Communications, including the Outreach Programme

1.4.4.          Knowledge management and information technology

 

1.5.       In implementing our strategy, we will also continue to harness our relationships with key stakeholders to ensure that we reach out to the people of South Africa and make a significant difference to their lives.


 

1.6.       I wish to thank the OPP management team and staff for showing their commitment to the strategic process by providing their well-considered input for the development of the strategic plan.  I therefore commit myself and the entire OPP staff to delivering the strategic plan for 2006 to 2011.

 

 

 

 

Adv. M.L. Mushwana

Public Protector

 

 

                                                                                                    


 

 

 

                                                       

 

 

 

 

 

 

 

 

PART 2:

 


STRATEGIC OVERVIEW

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.              STRATEGIC OVERVIEW

 

2.1               VISION

 

The Office of the Public Protector strives to be efficient, effective, accessible, known by all, and with its impartiality accepted,

 thereby strengthening constitutional democracy in

all organs of State.

 

2.1.1.    The vision underwrites the following:

 

2.1.1.1. To be efficient: (Internal focus within the OPP). Services that are:

 

2.1.1.1.1. Informed;

2.1.1.1.2. Timeous; and

2.1.1.1.3. Of the highest quality standards

 

2.1.1.2. To be effective: Achieve the integrated impact by:

 

2.1.1.2.1. Ensuring that recommendations proposed by the OPP are accepted and implemented by organs of State.

2.1.1.2.2. Reducing the recurrence of maladministration.

 

2.1.1.3. To be accessible:

 

2.1.1.3.1. All South Africans should know about the OPP;

2.1.1.3.2. Visibility; and

2.1.1.3.3. Reaching out to the poorest of the poor

 

 

 

2.2 MISSION

 

The Office of the Public Protector is an independent and impartial constitutional institution established to strengthen constitutional democracy by conducting investigations into alleged improper

 conduct by organs of State, facilitating resolution of disputes,

reporting and recommending remedial action and enhancing

awareness about the role and functions of the office.

 

2.3 CORE VALUES

 

2.3.1.    Impartiality

2.3.1.1.             We ensure impartiality in our interactions with our stakeholders. We perform our duties without fear or favour, mindful of the independence of our office.

 

2.3.2     Courtesy

2.3.2.1. We display courtesy to all and treat people with dignity and respect.

 

2.3.3. Empathy

2.3.3.1.             We are sensitive towards and understand our stakeholders’ needs and feelings.

 

2.3.4. Integrity

2.3.4.1.             We strive to maintain high standards of trustworthiness.

 

2.3.5. Accountability

2.3.5.1. We always give an account of our actions and decisions.

 

2.3.6. Service Oriented

2.3.6.1.             We strive to execute our responsibilities timeously, fairly and consistently, with due regard given to the facts of each matter before us.

2.4 LEGISLATIVE FRAMEWORK AND MANDATE

 

2.4.1.    The enabling legislations governing and guiding the functioning of the OPP are outlined below:

 

2.4.1.1.                          Chapter Nine of the Constitution of the Republic of South Africa Act, No. 108 of 1996

Provides the mandate of the Public Protector

 

2.4.2.    The following acts provide for an additional mandate for the OPP:

 

2.4.2.1.                          The Public Protector Act, No. 23 of 1994, as amended

 

2.4.2.2.                          Executive Members Ethics Act, 1998

 

2.4.2.3.                          The Promotion of Access to Information Act, 2000

 

2.4.2.4. The Protected Disclosure Act, 2000

 

2.4.2.5.                          The Housing Consumer Measures Protection Act 95 of 1998

 

2.4.3.    The mandate of the OPP is:

 

To assist Parliament to strengthen constitutional democracy by investigating matters such as maladministration, undue delay,

abuse of power and/or any conduct resulting in improper

prejudice by an organ of State in order to enhance

fairness and efficiency in public administration.


 

2.5 THE OPP CORE BUSINESS MODEL

 

 

 

 

 

 

 

 

 

 

 

 



2.6 HIGH-LEVEL ORGANISATIONAL STRUCTURE

 

2.6.1.    Below is the proposed high-level  organisational structure of the OPP. The detailed organisational structure is given in  Part Four.


2.7 SWOT ANALYSIS

 

2.7.1          STRENGTHS AND WEAKNESSES

STRENGTHS

WEAKNESSES

2.7.1.1. Organisational strategy

2.7.1.1.1. Strategic planning culture is in place.

2.7.1.1.2. The strategic planning process is not clearly documented and understood.

2.7.1.1.3.  Internal strategic performance reporting and monitoring process not in place.

2.7.1.2. Organisational structure

2.7.1.2.1. Security function established.

2.7.1.2.2. Not able to implement the organisational structure due to budgetary limitations.

2.7.1.3. Processes

2.7.1.3.1. Outreach programme is extending the reach of the organisation.

2.7.1.3.5. Operational procedures of the committees, e.g. think tank not fully documented.

2.7.1.3.2. Committees established within the OPP for operational efficiency.

2.7.1.3.6. Lack of sufficient advanced investigation techniques for enhanced quality service and ease of reference.

2.7.1.3.3.  Almost all OPP policies documented.

 

2.7.1.3.4. The file inspection process started within OPP.

 

2.7.1.4. People and Performance Management

2.7.1.4.1. OPP has highly skilled and experienced personnel in the legal field.

2.7.1.4.3. Lack of diverse skills in investigations, e.g. accounting and auditing, etc.

2.7.1.4.2. Performance management system implemented.

2.7.1.4.4. Not yet geared for the impact of HIV/AIDS on the OPP.

 

2.7.1.4.3. There is no clearly documented staff development plan.

2.7.1.5. Communication

2.7.1.5.1. A solid foundation created for external communication through the Outreach Programme.

2.7.1.5.2. Internal communication and media relations strategies not adopted.

 

2.7.1.5.3. Outreach programme initiatives not co-ordinated  with the Communications Unit.

2.7.1.6. Information and Communications Technology

2.7.1.6.1. A plan for the implementation of the integrated system has been developed.

2.7.1.6.2. Lack of optimal utilization of ICT to improve the services of the OPP, e.g. lack of case management system, etc.

 


2.7.2          OPPORTUNITIES AND THREATS

 

OPPORTUNITIES

THREATS

2.7.2.1. Political

2.7.2.1.1. The OPP has a strong relationship with Parliament, as is accountable it.

2.7.2.1.3. Some political parties often use the OPP as a tool to fight their own political battles.

2.7.2.1.2. The OPP receives excellent political support as an independent constitutional institution with a high profile

2.7.2.1.4. MPs and MPLs do not utilize the OPP effectively.

 

2.7.2.1.5. The PP is perceived to be partisan about findings in high-profile cases.

2.7.2.2. Economical

2.7.2.2.1. The ability to obtain funding from external donors for specific programmes, e.g. the Outreach Programme.

2.7.2.2.2. Funding for the OPP received from the National Treasury is inadequate.

2.7.2.3. Social

2.7.2.3.1. Cultural diversity of the OPP staff presents opportunities to broaden its services.

 

2.7.2.4. Technological

2.7.2.4.1. Technological infrastructure in South Africa is well advanced.

2.7.2.4.2. Current information technology service provision and infrastructure inadequate to serve the needs of the OPP.

 

2.7.2.5. Environmental

2.7.2.5.1. Location of OPP offices allows for easy access by the public.

2.7.2.5.2. Lack of personal safety due to  threats or intimidation from people being investigated

2.7.2.6. Legal

2.7.2.6.1. The legal framework in South Africa sufficiently enables the OPP to perform its functions; i.e. Public Protector Act, Constitution, PFMA, EE Act, PAJA, PDA, etc.

2.7.2.6.2. Overlap of functions between Chapter 9 institutions.

 

2.7.2.6.3. Constraints and bureaucracy within organs of State.

 


 

2.8 KEY STAKEHOLDERS AND THEIR NEEDS

 

2.8.1.       The OPP’s primary functions are performed to enhance constitutional democracy through  investigation, mediation, negotiation and conciliation  triggered by external parties or at its own initiative. The PP is the protector of the public interest, as opposed to protecting the public only. Therefore the OPP does not have customers like other organisations that focus  on delivering services directly to the end customers. The stakeholders of the OPP are listed below.

2.8.2.       Initiators

 

2.8.2.1.             These are the bodies or parties that trigger the OPP’s services. Although the OPP does not deliver a service on behalf of these stakeholders, they are kept informed of the progress of the case. These initiators include the following:

 

2.3.2.1.1.          Organs of state

2.3.2.1.2.          The public

2.3.2.1.3.          Parliament

2.3.2.1.4.          Public servants

2.3.2.1.5.          The private sector

2.3.2.1.6.          Political parties

2.3.2.1.7.          The media

 

2.8.2.2.             The main reasons for these stakeholders to approach the OPP are the following:

 

2.3.2.2.1.          The need for efficient, proper and fair administration by organs of state.

2.3.2.2.2.          Speedy resolution of problems.

2.3.2.2.3.          To succeed where everyone else has failed.

 

2.8.2.3.             The OPP has an obligation to report its findings to Parliament or to the organs of state, as the case may be, and where necessary to mediate, negotiate, conciliate and recommend remedial action.

2.8.3.       Partners

 

2.8.3.1. The OPP has defined the following as its partners:

 

2.8.3.1.1.          The Human Rights Commission

2.8.3.1.2.          The Commission for the Promotion and Protection of the Rights of Cultural, Religious and Linguistic Communities

2.8.3.1.3.          The Commission for Gender Equality

2.8.3.1.4.          The Auditor-General

2.8.3.1.5.          The Independent Electoral Commission

2.8.3.1.6.          The Public Service Commission

2.8.3.1.7.          Organs of state

2.8.3.1.8.          The Independent Complaints Directorate

2.8.3.1.9.          The National Prosecuting Authority

2.8.3.1.10.         Consumer Affairs

2.8.3.1.11.         Complaint-handling institutions

2.8.3.1.12.         The House of Traditional Leaders

 

 

 

2.8.3.2.             The first five in the above list of organisations are institutions created under Chapter 9 of the Constitution, with their  primary focus on protecting and promoting constitutional democracy. The OPP has signed a memorandum of understanding with the Human Rights Commission and the Public Service Commission to ensure that there is no duplication of their functions.

              

2.8.3.3. These organisations expect the following from the OPP:

 

2.8.3.3.1.          Understanding  the respective mandates

2.8.3.3.2.          Building  co-operative relations (contextual)

2.8.3.3.3.          Co-operative investigations (operational)

2.8.3.3.4.          Efficient referrals and feedback

2.8.4.    Facilitators

 

2.8.4.1.             The OPP has defined the following as organisations that  refer people to their offices and facilitate the rendering of services:

 

2.8.4.1.1.          Non-governmental organisations

2.8.4.1.2.          Legal aid clinics

2.8.4.1.3.          Lawyers

2.8.4.1.4.          Politicians

2.8.4.1.5.          Public servants

2.8.4.1.6.          The media

2.8.4.1.7.          Community-based organisations

2.8.4.1.8.          The House of Traditional Leaders

 

2.8.4.2.             These organisations expect the OPP to be impartial and to conduct proper investigations. There are tendencies, however, for improper use of the OPP in the following areas:

 

2.8.4.3.             Some lawyers tend to use the OPP to transfer their workload or relieve their failures; and

 

2.8.4.4.             Some politicians expect the OPP to take their side, i.e. be biased in their favour.

 

2.8.4.5.             The media will in most instances look for stories that are newsworthy and tend to sensationalise some matters.


2.8.5.       Influencers

2.8.5.1.             The OPP has defined the following as being able to influence the organisation either positively or negatively:

 

2.8.5.1.1.          Parliament

2.8.5.1.2.          The public

2.8.5.1.3.          The media

 

2.8.5.2. The influencers expect the following from the OPP:

 

2.8.5.2.1.          Prompt, timely and adequate reports

2.8.5.2.2.          The implementation of recommendations that are realistic, achievable and accurate

2.8.5.2.3.          Prompt investigations and remedial action

2.8.5.2.4.          Transparency and fairness of investigations

2.8.5.2.5.          Co-operative issuing of unqualified reports

2.8.5.2.6.          Negotiation, mediation and conciliation

 

2.8.5.3. The needs of the influencers are as follows:

 

2.8.5.3.1.          Feedback on the effectiveness of governance

2.8.5.3.2.          Ensuring that justice is done

2.8.5.3.3.          Obtaining  full details to ensure responsible reporting

2.8.5.3.4.          Fairness

 

 

 


 

 

 

                                                       

 

 

 

 

 

 

 

 

PART 3:

 


ORGANISATIONAL STRATEGY

 

 

 

 

 

 

 

 

 

                                                                                       

 

 

 

 

3.              ORGANISATIONAL STRATEGY

 

3.1 OUTLINE OF PROGRAMMES AND SUB-PROGRAMMES

 

3.1.1.    Reporting to the National Treasury by OPP  currently takes place for only two  programmes, i.e.:

 

3.1.1.1. Administration and Investigations

3.1.1.2. The Outreach Programme

 

3.1.2.    This strategy suggests  revisiting the programmes and structuring them in accordance with the operations of the OPP. The suggested programmes are:

 

Programme

Sub-Programme

3.1.2.1.  Investigations and Reporting

3.1.2.1.1. National Investigations

3.1.2.1.2. Provincial Investigations

3.1.2.1.3. Special Investigations

 

 

 

3.1.2.2.  Communication Services

3.1.2.2.1. Outreach Programme

3.1.2.2.2. Marketing and Communications

 

 

 

3.1.2.3.  Corporate Support Services

3.1.2.3.1. Human Capital

3.1.2.3.2. Finance and Supply Chain Management

3.1.2.3.3  Administration Support

3.1.2.3.4  Security Management

 

 

3.1.2.4.  Knowledge Management and Information Technology

3.1.2.4.1.  Knowledge Management

3.1.2.4.2.  Information Technology

 

3.2 PROGRAMME 1: INVESTIGATIONS AND REPORTING

 

3.2.1          Objective of the programme:

 

3.2.1.1        To conduct national, special and provincial investigations that are effective, efficient, informed, timeous and of high quality.

 

3.2.2          Outcome of the programme:

 

3.2.2.1        Improved service delivery to stakeholders.

 

3.2.3          Strategic objectives for the programme:

 

Sub-Programmes: ALL (National, Provincial and Special Investigations)

Responsibilities

3.2.3.1. To conduct investigations with adherence to SDIs.

 

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.2. To identify and conduct systemic investigations.

 

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.3. To conduct own-initiative investigations.

 

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.4. To develop investigative techniques, processes and training.

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.5. To reduce the turnaround time to a maximum of two years to finalize all cases.

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.6. To conduct file inspections.

 

Public Protector

Deputy Public Protector

3.2.3.7. To ensure effective, relevant reporting in all finalized investigations.

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.8. To monitor and report on remedial actions recommended to organs of state.

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.9. To improve on think-tank committee procedures and processes.

Executive Manager: Provincial Investigations

3.2.3.10. To improve on strategic performance reporting.

Control Investigator: National Investigations

Control Investigator: Special Investigations

Executive Manager: Provincial Investigations

3.2.3.11. To improve the effective and efficient coordination of provincial offices.

Executive Manager: Provincial Investigations


3.2.4          Sub – Programmes: ALL (National, Special and Provincial Investigations)

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.2.4.1. To conduct investigations with adherence to service delivery indicators (SDIs)

Approved project plans for appropriate investigations / investigation plans for all other cases

% of project plans for appropriate cases

Project plans defined for 80% of appropriate cases

Project plans defined for 90% of appropriate cases

Project plans defined for 100% of appropriate cases

Adherence to approved SDIs aligned with individual performance in accordance with the defined work plans

% of adherence to SDIs

80 % of adherence to SDIs

80 % of adherence to SDIs

80 % of adherence to SDIs

3.2.4.2. To identify and conduct systemic investigations

Systemic investigation reports

Number of systemic investigations undertaken per annum

 

Five (5) systemic investigations

Five (5) systemic investigations

Five (5) systemic investigations

3.2.4.3. To conduct own-initiative investigations

Own-initiative investigation reports

Number of own initiative investigations undertaken per annum

Five (5) own initiative investigations

Five (5) own initiative investigations

Five (5) own initiative investigations

3.2.4.4. To develop investigative techniques, processes and training

Process manual reflecting

investigation techniques, remedial action guidelines, checklists, and report writing and procedures

% manual completion

 

 

Process manual completed 100%

 

Process manual 100% reviewed

 

Process manual 100% reviewed

 

Investigators trained on process manual

Number of investigators trained

 

60% of investigators trained.

70% of investigators trained.

3.2.4.5. To reduce the turnaround time to a maximum of 2 years for finalizing all cases

Regular statistical report on relevant cases

%  compliance

60%  compliance

70%  compliance

100%  compliance

3.2.4.6. To conduct file inspections

File inspection report

Number of file inspections

1 per national and provincial organisation

1 per national and provincial organisation

1 per national and provincial organisation

3.2.4.7. To ensure effective, relevant reporting on all finalized investigations

Quality report for every finalized case.

% of reports produced

 

80% of reporting on all finalized cases

90% of reporting on all finalized cases

100% of reporting on all finalized cases

3.2.4.8. To monitor and report on remedial actions recommended to organs of state

Remedial action and monitoring Report

 

% of implemented recommendations by organs of state

50% of recommendations implemented

70% of recommendations implemented

90% of recommendations implemented

3.2.4.9. Improve on Think Tank Committee procedures and processes

Full participation by all Think-Tank Committee members

%  participation

 

 

 

100% participation

 

 

 

100% participation

 

 

 

100% participation

 

 

 

Think Tank reports submitted

“Think Tank Reports[1] submitted to Think Tank

40%  ““Think Tank Reports” submitted to Think Tank

60% “Think Tank Reports” submitted to Think Tank

80% “Think Tank Reports” submitted to Think Tank

Documented Think Tank Operational Process Manual

% Completion of Operational Process Manual

 

60% Process Operational Manual completed

100% Process Operational Manual completed

100% Process Operational Manual completed

3.2.4.10. Improve on strategic   performance reporting

Strategy Performance and

Statistical Reports

 

Number of meetings and reports

Quarterly performance meeting and reporting

Quarterly performance meeting and reporting

Quarterly performance meeting and reporting

Number of meetings and reports

Annual strategy review meeting and reporting

Annual strategy review meeting and reporting

Annual strategy review meeting and reporting

Number of meetings and reports

Annual reporting to Parliament

 

Annual reporting to Parliament

Annual reporting to Parliament

3.2.4.11. Improve the effective and efficient coordination of provincial offices

Executive Manager: Provincial Investigations appointed

Appointment of Executive Manager: Provincial Investigations

100% Appointment of Executive Manager: Provincial Investigations

 

 

Provincial Coordination Process Manual

% Provincial Process Manual completed and implemented

60 % Provincial Process Manual completed

100 % Provincial Process Manual completed

Implement Provincial Process Manual

 

 


3.3 PROGRAMME 2: COMMUNICATION SERVICES

 

3.3.1          Objective of the programme:

 

3.3.1.1. To improve internal and external communication to inculcate a common vision  and improved profile for the OPP.

 

3.3.2          Outcome of the programme:

 

3.3.2.1. Improved stakeholder perception, co-operation and accessibility of OPP services.

3.3.2.2. Smooth, timeous flow of accurate information to all OPP staff.

 

3.3.3          Strategic objectives for the programme:

 

Sub-Programme: Outreach Programme

Responsibility

3.3.3.1  Increase accessibility to OPP services

3.3.3.2. Increase public awareness

3.3.3.3. Enhance collaboration with stakeholders

Communications Manager

Executive Manager: Provincial Investigations

Sub-Programme: Marketing and Communications

 

3.3.3.4. Improve communication and routing of information to stakeholders

3.3.3.5. Effective communication to internal staff

3.3.3.6. Improve media relations

3.3.3.7. Develop the branding of the OPP

3.3.3.8. Inculcate protocol knowledge within the OPP

Communications Manager

 

 

 


3.3.4          Sub – Programme: OUTREACH PROGRAMME

 

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.3.4.1. Increase accessibility to OPP services

Outreach strategy

%  Outreach strategy development and implementation

80%  Outreach strategy development and implementation

100%  Outreach strategy development and implementation

Review Outreach strategy and implementation

Clinics conducted

Clinics conducted

Four clinics per province

Five clinics per province

Six clinics per province

Additional regional office established

Additional offices established

Two additional regional offices established

Two additional regional offices established

Two additional regional offices established

3.3.4.2. Increase public awareness

Information sessions with stakeholders

Number of Information Sessions / Workshops

Five information sessions per province

Five information sessions per province

Five information sessions per province

3.3.4.3. Enhance collaboration with stakeholders

Chapter 9 Collaboration Plan

% Completion of Chapter 9 Collaboration Plan

100% Collaboration Plan completed

Review and implementation

Review and implementation


3.3.5          Sub – Programme: MARKETING AND COMMUNICATIONS

 

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.3.5.1. Improve communication and routing of information to stakeholders

External communication strategy development and implementation

%  external communications development and implementation

100% of external communication strategy developed

Implement

 

Implement

 

3.3.5.2. Effective  communication to internal staff

Internal communication strategy development

%  internal communications development and implementation

100% of communication strategy developed

Implement

 

Implement

 

3.3.5.3. Improve media relations

Media strategy development

%  communications development and implementation

100% of media strategy developed

 

Implement

 

Implement

 

3.3.5.4. To enhance the image of the OPP

Identifiable branding of the OPP

%  branding achievement

100% of branding strategy developed

Implement

 

Implement

 

3.3.5.5. Inculcate protocol knowledge within the OPP

Staff trained on protocol

% training achievement

40% of staff trained

60% of staff trained

80% of staff trained

 


3.4 PROGRAMME 3: CORPORATE SUPPORT SERVICES

 

3.4.1          Objective of the programme:

 

3.4.1.1.             To achieve and sustain an efficient and effective corporate support service that is compliant with legislation.

 

3.4.2          Outcome of the programme:

3.4.2.2. Improved service delivery.

 

3.4.3          Strategic objectives for the programme:

Sub-Programme: Human Resources Management and Development

Responsibility

3.4.3.1. Attraction, maintenance and retention of high-quality staff.

3.4.3.2. To improve and sustain HR performance management system.

3.4.3.3. Training and development of staff according to needs.

3.4.3.4. Facilitating the design utilization of an EWP and achieving transformation, equity and diversity.

Human Resources Manager

Sub-Programme: Finance and Supply Chain Management

Responsibility

3.4.3.5. To develop a costing model for investigations

3.4.3.6. Improve OPP financial management and reporting

3.4.3.7. Ensure compliance of OPP with financial prescripts

3.4.3.8. Develop and implement  cost-effective procurement processes

 

Accounting Officer

CFO

Control Investigator: National Investigations (Only for 3.4.3.5)

Control Investigator: Special Investigations (Only for 3.4.3.5)

Executive Manager: Provincial Investigations(Only for 3.4.3.5)

Supply Chain Manager

Sub-Programme: Administration Support

 

3.4.3.9. To enable the optimum application and utilization of resources

3.4.3.10. To promote the effective and efficient functioning of the registry

3.4.3.11. To establish and maintain suitable office accommodation

Accounting Officer

Sub-Programme: Security Management

 

3.4.3.12. To establish and implement processes for the protection of OPP information and assets

Security Manager

3.4.3.13. To provide secure premises and a safe working environment for staff.

 

 


3.4.4          Sub – Programme 3.1: HUMAN RESOURCES MANAGEMENT AND DEVELOPMENT

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.4.4.1. Attraction, maintenance and retention of high-quality staff

Human Capital Sourcing Strategy and implementation

%  Human Capital Sourcing Strategy development and implementation

100% of Human Capital Strategy developed

 

Implement Strategy

80% human capital requirements recruited, maintained and retained

Remuneration strategy / policy and implementation

%  remuneration strategy/policy development and implementation

100% of remuneration strategy/policy developed

Implement Strategy/Policy

Implement performance incentives in accordance with new policy

3.4.4.2. To improve and sustain the HR performance management system

Outcome-based Performance Management System

% Implementation of Outcome-based Performance Management System

Review system and recommend an instrument for  outcome-based performance

50% implementation of outcome-based system

80% implementation of outcome-based system

3.4.4.3. Training and development of staff according to needs

Human Resources Development (HRD) Strategy developed and implemented

% HRD Strategy development and implementation

100% of HRD strategy developed and implemented

100% Implementation of strategy

100% Implementation of strategy

3.4.4.4. Facilitate the design and utilization of an EWP and achieve transformation, equity and diversity

Accessible, functional and utilized EWP

% of staff utilizing EWP

0% - Design of strategy and wellness programme

60% staff utilizing EWP

80% staff utilizing EWP

 

3.4.5          Sub – Programme 3.2: FINANCE AND SUPPLY CHAIN MANAGEMENT

 

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.4.5.1. To develop a costing model for investigations

Costing model developed

% of costing model developed and implemented

Costing model partly developed

Costing model developed

Implementation

3.4.5.2. Improve financial management  and reporting

Financial management policies developed and implemented

% of financial policies implemented

80%of financial policies implemented

100% of financial policies implemented

Review

Divisional budgets

% of divisional budget implemented

30 % of divisional budget implemented

60 % of divisional budget implemented

100 % of divisional budget implemented

3.4.5.3.  Ensure compliance with financial  prescripts

Unqualified audit reports

% compliance

100% compliance

100% compliance

100% compliance

3.4.5.4. Develop and implement  cost-effective procurement processes

Cost-effective procurement processes implemented

% implemented

100 % of implementation

Review and implementation

Review and implementation

 


3.4.6          Sub – Programme 3.3: ADMINISTRATION SUPPORT

 

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.4.6.1. To enable the optimum application and utilization resources

Vehicle monitoring system

% implementation of vehicle monitoring system

100% implementation

100% operational – review monitoring measures

100% operational - review monitoring measures

 

Telephone management system

% implementation of telephone management system

100% implementation

100% operational – review monitoring measures

100% operational – review monitoring measures and 10% cost reduction

3.4.6.2. To promote the effective and efficient functioning of the registry

Records management system

% implementation of records management system

60% implementation

100% operational – review

100% operational – review

3.4.6.3. To establish and maintain suitable office accommodation

 

Office established

Number of offices established

Two additional regional offices

2 additional regional offices

2 additional regional offices

Office relocated

Office to be relocated

Mafikeng and Western Cape

-

-

Storerooms established

Storerooms to be established

Storerooms established – Northern Cape and Eastern Cape

-

-

 


3.4.7          Sub – Programme 3.4: SECURITY MANAGEMENT

 

Strategic Objective

Outputs

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.4.7.1. To establish and implement processes for the protection of OPP information and assets

Strategy, policies and procedures

% development and implementation

60% development of policies and procedures

100% development of policies and procedures

Implementation

3.4.7.2. To provide secure premises and a safe working environment for staff

Strategy, policies and procedures

% development and implementation

60% development of policies and procedures

 

100% development of policies and procedures

Implementation


3.5 PROGRAMME 4: KNOWLEDGE MANAGEMENT AND INFORMATION TECHNOLOGY

 

3.5.1          Objective of the programme:

 

3.5.1.1.              To introduce and maintain efficient and effective knowledge management and information and communications Technology within the OPP.

 

3.5.2          Outcome of the programme:

 

3.5.1.2        Efficient and effective service delivery to stakeholders.

 

3.5.3          Strategic objectives for the programme:

 

Sub-Programme: Knowledge Management

Responsibility

3.5.3.1. Create Knowledge Management Institution of the OPP

Researcher

Deputy Public Protector (Interim)

3.5.3.2. Establish and Migrate AORC

3.5.3.3. Implement Exchange Programme

Sub-Programme: Information and Community Technology

 

3.5.3.4. To implement and enhance integrated information management systems.

ICT Manager

3.5.3.5. Building and enhancing ICT infrastructure that is reliable, secured and interoperable

3.5.3.6. Improving and implementing ICT best practices

 


3.5.4          Sub-Programme: Knowledge Management

 

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.5.4.1. Create a knowledge management institution for the OPP

Knowledge and Research Manager appointed

Appointment of Knowledge and Research Manager

Appointment of Knowledge and Research Manager

 

 

Knowledge audit conducted

% of audit conducted

100% of audit conducted

Align corporate policies and strategies to ensure compliance with KM requirements

Expand and replicate and institutionalize KM within OPP

Knowledge management strategy implemented

% of KM strategy developed and implemented

100% of strategy developed

30% of KM interventions implemented

50% of  KM interventions implemented

Research conducted

Continuous research

Continuous research performed

Continuous research performed

Continuous research performed

3.5.4.2. Establish and migrate AORC

AORC established

% of AORC established and migrated

100% of AORC established

100% migration of AORC

Conduct teaching and research at AORC centre

3.5.4.3. Implement exchange programme

Information being shared with other ombudsman offices

% of exchange programme implemented

50% of exchange programme implemented

100% of exchange programme implemented

Review effectiveness of exchange programme

3.5.5          Sub-Programme: Information and Communications Technology:

Strategic Objective

Output

Measure

2006/7 Target

2007/8 Target

2008/9 Target

3.5.5.1 To implement and enhance integrated information management systems.

Case management system

% implementation

50% implementation

100% implementation

Review and improve

Dictaphone interpretation system

% implementation

20% implementation

40% implementation

60% implementation

e-Procurement system

% implementation

100% implementation

Review and improve

Review and improve

Precedent system

% implementation

Review of the researcher post

50% implementation

100% implementation

Enhanced security system

% implementation

50% implementation

70% implementation

100% implementation

Enhanced HRMIS

% implementation

Audit of HRMIS

100% implementation

Review

3.5.5.2. Build and enhance ICT infrastructure that is reliable, secured and interoperable

Network availability

% availability

100% availability

Maintain

Maintain

Upgrade of servers and software

% upgrade

100% upgrade

Maintain

Maintain

Remote connection to the office network

% implementation

50% implementation

100% implementation

Maintenance and upgrade

Intranet

% implementation

20% implementation

40% implementation

80% implementation

3.5.5.3 Improve and implement ICT best practices

Policies, standards and procedures

% development and implementation

100% development

Implement

Implement

Business Continuity Plan

% development and implementation

50% development

80% development

100% development


 

 

 

                                                       

 

 

 

 

 

 

 

 

PART 4:

 


ORGANISATIONAL STRUCTURE

 

 

 

 

 

 

 

 

 

                                                                                       

 


4.              PROPOSED ORGANISATIONAL STRUCTURE

4.         OVERALL ORGANISATIONAL STRUCTURE

 


 

PROPOSED BRANCHES: NATIONAL AND SPECIAL INVESTIGATIONS - 2005

 
 

Text Box: PUBLIC PROTECTOR OF SOUTH AFRICA

Text Box: PROPOSED BRANCHES: 
NATIONAL AND SPECIAL INVESTIGATIONS
Text Box: DIVISION
INVESTIGATIONS 
NO I
1 Chief Investigator (SM)
1 Secretary
10 Senior Investigators
3 Investigator Assistant
2 Administrative Assistant

DIVISION

INVESTIGATIONS

NO II

1 Chief Investigator (SM)

1 Secretary

10 Senior Investigators

3 Investigator Assistant

2 Administrative Assistant

 

 

 

 
Text Box: DIVISION
INVESTIGATIONS
NO III
1 Chief Investigator (SM)
1 Secretary
10 Senior Investigators
3 Investigator Assistant
2 Administrative Assistant

 




Text Box: PROPOSED BRANCH: CORPORATE SERVICES
2005
Text Box: CHIEF ADMIN. OFFICER (CEO)

SEE PAGE 57

 

SEE PAGE 56

 

SEE PAGE 55

 

SEE PAGE 54

 

SEE PAGE 53

 
Text Box: DEPUTY PUBLIC PROTECTOR

SENIOR MANAGER:

HUMAN RESOURCE MANAGEMENT/ DEVELOPMENT AND LABOUR RELATIONS

 

SENIOR MANAGER:

ADMIN SUPPORT SERVICES AND CO-ORDINATION

 

SENIOR MANAGER: (CFO)

FINANCIAL MANAGEMENT SERVICES

 

 
Text Box: PUBLIC PROTECTOR OF SOUTH AFRICA

 

 

 



 

SENIOR MANAGER

ADMIN SUPPORT SERVICES AND

CO-ORDINATION

 

 

 

FACILITIES MANAGEMENT, TRANSPORT MANAGEMENT AND SECURITY SERVICES

 

 

OFFICE MANAGEMENT SERVICES

 

1 Assistant Manager

1 Chief Admin. Clerk

1 Admin Officer

1 Admin Clerk

 

 

 

1 Assistant Manager

1 Chief Admin. Clerk

5 Admin. Clerk

1 Messenger/ Driver

1 Food Services Aid

 

Secretary

 

BRANCH; CORPORATE SERVICES

(FROM PAGE 50)

 

 

 

 

 

 

 

 

 

 


 

 

 

                                                       

 

 

 

 

 

 

 

 

PART 5:

 


CONCLUSION

 

 

 

 

 

 

 

 

5.              CONCLUSION

 

5.1. The OPP is on track in transforming itself to become more efficient and effective in delivering its mandate of strengthening constitutional democracy in all organs of State. There is now a culture of integrated strategic planning to ensure much greater coherence and synergy in the execution of the key programmes. This three-year strategic plan sets the baseline for rapid improvements in the way the OPP conducts its operations.

 

5.2. The investigation and reporting process is being enhanced by aligning the investigations to the defined service delivery indicators (SDIs) and by ensuring that own initiatives and systemic investigations are identified and conducted.  New investigation techniques are being introduced and processes for strategic performance reporting, the think-tank committee and provincial coordination are being refined. The turnaround time for finalisation of all cases has been reduced to a maximum of two years, and monitoring and reporting on remedial actions recommended to organs of state will be improved.

 

5.3. The OPP is  actively continuing with the Outreach Programme to improve co-operation and the accessibility of services. Communication strategies are being developed to facilitate a smooth, timeous flow of accurate information to all stakeholders and OPP staff.

 

5.4. There are initiatives for a further improvement of the human capital, finance, supply chain management and administration support functions. The newly established security services unit will ensure protection of OPP information and assets and provide a safe working environment for all staff.

 

5.5. Information and communications technologies are being leveraged to improve service delivery and knowledge management. These include case management, library management, records management and corporate support systems.

 

5.6. Overall, there is general buy-in and commitment from management and staff of the OPP to achieve this three-year strategic plan.



[1] Think Tank reports include special reports, formal reports with recommendations, and formal reports without recommendations.