REPORT TO PORTFOLIO COMMITTEE ON SPORT AND RECREATION

 

NELSON MANDELA BAY MUNICIPALITY ("NMBM")

 

 

1.         Introduction

 

In its motivation for inclusion as a Host City, submitted as part of the South African Bid to host the 2010 World Cup, it was proposed that NMBM would construct a new stadium.

 

A comprehensive business case was prepared, assessing availability and suitability of sites, the nature and size of the stadium and its long term sustainability. A stadium suitable for multi purpose use was mooted.

 

After the announcement that South Africa would host the World Cup, NMBM reacted rapidly to build on the considerable body of work which had already been done in preparing for the bid. It appointed a local professional team to drive site preparation, preliminary design, specification and tender process and to project manage construction.

 

The site identification process resulted in the selection of the Prince Alfred's Park precinct, adjacent to the North End Lake, as the most suitable site. This site is centrally located, its situation integrates foursquare with transportation infrastructure and transportation planning as reflected in NMBM's IDP and its existing primary use being for sport and recreation purposes, resulted in the EIA process being rapidly concluded. A record of decision (ROD) was obtained during March 2006.

 

Thereafter, a design consortium was appointed to develop preliminary designs (which included a firm which had experience of FIFA stadium requirements) and preliminary designs were prepared and completed by July 2006. These were sufficiently detailed to allow tender specification to be prepared and to enable tenders to be issued for detailed design work.

 

NMBM was in a position to issue invitations to tenderers in July 2006, but was unable to do so, due to the fact that at that time, availability of funding had not yet been confirmed. It is possible, that had we been able to do so, the tendered prices would be considerably reduced.

 

2.         Tender process

 

The tender process for the acquisition of contractors to construct the stadium has occurred in four stages:

 

·         Demolition, bulk earthworks and stormwater

·         Bulk sewer works

·         Bulk water

·         Piling

·         Stadium main contract


 

Earthworks, stormwater, sewer and water contracts will all be complete by the end of March.

 

The piling contract was awarded in December 2006, the contractor is establishing on site and will be completed by May 2007 (overlapping in a planned way with the main construction contract).

 

The main construction contract will be awarded during the second week of February 2007.

 

3.         Approach to design and cost effectiveness

 

Design of a stadium requires a number of factors to be balanced, including what will be sustainable in the long term, what FIFA's requirements are, aesthetics and practicality. The approach adopted by NMBM was to be as modest as possible, to meet FIFA specifications without grandiose designs, but to provide for adequate quality and standards to ensure durability and minimise the demand for maintenance in years to come as well as to be as practical as possible.

 

An example of an issue affecting the design approach, is the size of the stadium. The business case developed by NMBM, suggests that in the long term, NMBM can only support a 30 000 seater multi-purpose stadium. FIFA however would require a 48 000 seater stadium. The approach adopted was to balance these two requirements by providing for modular seating which is FIFA compliant but is capable of being removed after the World Cup. This modular seating is available for hire for a stipulated period. The space available after removal, could be used for suites or other additional construction, as a source of income for the stadium. A further example is the roof. Weather records reflect that the time of the World Cup (June) in NMBM produces rain and wind. FIFA requirements make a roof an absolute requirement only for the western stand, but the LOC Technical Team advice was that fully roofed stands are needed at coastal venues. In addition, the business case reflects that the stadium would not be sustainable in the long term without a roof. Given this approach, it follows that the possibilities for limitation of scope of work are reduced, to avoid affecting quality and standards or sustainability of the stadium. The scope and specification for professional and construction work was exhaustively covered by NMBM's Technical Team together with the LOC Technical Committee. The stadium design was signed off by the Technical Team as compliant not only with FIFA requirements, but with its own expectations.

 

4.         Approach to contracting

 

The process used by NMBM for the procurement of tenders was based on an open tender system (JBCC and CIDB documentation). The alternative option of "design and construct" based on a fixed price model was not considered by either NMBM's technical advisers or the LOC Technical Team to be appropriate for a number of reasons, the most important of which is time. Experience gained with the use of "design and construct" in South Africa, for example with major tar roads, other than major sporting facilities in Africa and the Gautrain project has shown conclusively that it is a time consuming process.

 

Further, given the limited number of major contractors who meet CIDB qualification standards for a project of this size, it was decided to include in the specifications, a number of designed and costed components which will be available for local contractors, meeting certain empowerment criteria.


 

5.         Funding

 

As has been stated above, the design and scope of work was finalised with close participation by the LOC Technical Team. In like fashion, the estimated cost of that work was calculated by NMBM's quantity surveying team and separately by the LOC Technical Team. It was based on that calculation that the LOC Technical Team recommended to National Treasury as to the amount of the conditional grant to be allocated to NMBM. NMBM's pre-tender calculated estimate, was R960 m (rounded off) where as the amount approved was just under R890 m (both figures excluding VAT). The reduced amount allocated by National Treasury as a conditional grant, was based on a political decision, not on a calculated estimate. The point is, that the figures and estimates, on the basis of which all parties made their decisions, were the best information available at the time. It was necessary for National Treasury to confirm this allocation before municipalities could proceed to tender, given the requirements of the MFMA. National Treasury however has made it abundantly clear through correspondence with Host Cities that the figure allocated by it is fixed and will not be changed and that any shortfalls are the responsibility of Host Cities.

 

6.         Preliminary outcome of the tender process

 

In terms of the Supply Chain Management regulations under the MFMA, and NMBM's Supply Chain Management Policy, the tenders received must first be evaluated by an Evaluation Committee, which produces a report dealing with all the criteria and conditions in the tender specifications. This report, with recommendations, is submitted to an Adjudication Committee which in turn considers the report and recommends an award to the Accounting Officer (Municipal Manager).

 

NMBM has received three qualifying tenders. Yesterday (22 January 2007), the interview process was concluded, and the evaluation report will be finalised tomorrow (24 January 2007), whereafter it will be submitted to the Adjudication Committee.

 

The matter will be reported to the Council on 7 February 2007 to address possible budget amendments and changes to the scope of the project, whereafter the Accounting Officer (Municipal Manager) will be in a position to award the contract, which is in line with NMBM's planned timetable.

 

The possible shortfall ranges from a maximum of R262 million (rounded off) to R106 m (rounded off) which will require elimination of grand stand roofs. This will of course have an impact on sustainability.

 

7.         National Treasury / Department of Sports and Recreation SA point of view

 

On 13 December 2006, representatives of the Host Cities and the above two Departments met during the course of which it was pointed out that Accounting Officers face a challenge of having to award tenders in the near future, for amounts in excess of the amounts provided by National Treasury. It was requested that National Treasury, acting in terms of Section 170 of the MFMA, grant a departure from the conditions contained in Section 19 of the Act, which would enable Accounting Officers to proceed to award contracts. It was further proposed however that a meeting be held in January involving the Host Cities, Department of Sports and Recreation SA and National Treasury to enable the individual solutions for Host Cities to be examined collectively by Government and a set of solutions arrived at which would meet the needs of Government.

 

Unfortunately, National Treasury thereafter responded that no exemptions to Section 19 would be granted, that no meeting would be held at a Government level but requiring Host Cities to motivate to their Councils options available to address shortfalls.

 

The Director-General of 2010 World Cup has subsequently confirmed that no additional funding will be forthcoming from National Treasury.

 

8.         Possible reasons

 

It should be pointed out that there has not been "an increase" in tender prices. What has happened, is that the tendered prices, which reflect a genuine competitive testing of the markets, are higher than the calculated estimates prior to the issue of tenders.

 

Reasons for this could include the following:

 

  • Timing. The majority of tenders were issued at the same time, immediately after the allocation of funding by National Treasury. If tenders could have been spread (e.g. if NMBM could have invited tenders in July 2006) costs could have been lower.

 

  • Equipment. High rise cranes are in short supply internationally. Each site will need to have between 6 and 12 cranes.

 

  • High level of construction activity. Economic growth nationally and in NMBM particularly (e.g. a number of major projects commencing in the Coega Development Zone) has resulted in contractors becoming more selective as to projects in which they wish to tender. Some major contractors have in fact not tendered for the stadium construction.

 

  • Possible shortage in the supply of critical building material.

 

  • Possible shortage in the supply of skilled labour in the construction industry.

 

  • Wage demands in the unskilled sector.

 

  • Nature of work. Experiences prove that stadium construction is a high risk project for contractors and designers.

 

As a result of the above factors, tenderers have costed in their perception of the risk particularly in their costing of preliminaries and mark ups on provisional sums (ranging from 400% to 765% more than pre-tender estimates).


 

9.         Constraints caused by MFMA

 

From NMBM's point of view, the MFMA has not proved to be a source of procedural difficulty.

 

Section 19 of the MFMA precludes municipalities from spending money on a capital project (which would include the award of a tender) unless the money for the project has been appropriated in the capital budget, the project, including the total cost, has been approved by the Council and the sources of funding to fund the budget provision have been considered and are available.

 

This is prudent provision and provides for a sound management principle. It has proved to be a constraint for some municipalities, where Accounting Officers have not had time to report to Councils on the potential budget amendments needed to provide for the increased cost reflected in tenders, given that existing budgets would have reflected the amounts allocated by National Treasury. In NMBM's case, there will be time to submit a report to Council and obtain the necessary authority, before proceeding to award the contract.

 

 

 

 

23 February 2007