MPUMALANGA PROVINCIAL GOVERNMENT
DEPARTMENT OF AGRICULTURE AND LAND ADMINISTRATION
SIX MONTHS CAPITAL PROJECTS REPORT

JULY – SEPTEMBER
2006/07

 CASP EHLANZENI

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

Horticulture

 

TAAMF CPA

 

Steelpoort

 

78

 

Fencing

 

118,000

 

118,000

0

Implementation to start in Quarter 3.

 

 

Rietfontein Homeless People Trust

Ohrigstad

 

560

 

Earth Dam (2)

 

600,000

 

475,000

0

Commitments already made

 

 

Kuyasa Agri-processing and Pre-Packing

Tonga

 

6

 

Bore Hole & Water Supply

90,000

 

90,000

0

Implementation to start in Quarter 3.

 

 

Bambanani Multi-Purpose Centre (5 Villages)

Malekutu

 

28

 

Irrigation Infrastructure & Fencing

475,000

 

185,000

155,000

Implementation to start in Quarter 3.

 

 

Siyabuyela Farmers Association

Malekutu

 

10

 

Fence and Store Room

288,000

 

140,000

0

Implementation to start in Quarter 3.

 

 

Jabulane F/A

 

Sibange

 

350

 

Irrigation Infrastructure (Phase 2)

1,677,220

 

650,000

 

0

Commitments already made

 

Livestock

 

Ardwick CPA

 

Ohrigstad

 

115

 

Centre Pivot (2) and Irrigation Infrastructure

900,000

 

400,000

 

1,919

Project ion track.

 

 

J.D.P. Piggery Project

Burgersfort

 

7

 

Piggery & Fencing Project

120,000

 

100,000

 

0

Commitments already made

 

 

Majakathatha Multi Project

Steelpoort

 

12

 

Poultry & Fencing

160,000

 

135,000

 

0

Implementation to start in Quarter 3.

 

 

Jerusalem Poultry Youth Project

Jerusalem

 

12

 

Broiler Production (5 Units) & Borehole

230,000

 

170,000

 

0

Commitments already made.

 

Macadamia

 

Legogote Trust

 

Hazyview

 

22

 

Fencing, Engine, Irrigation

273,500

 

208,000

 

0

Implementation to start in Quarter 3.

 

 

Express Model Trading 261 (PTY) Ltd

Noord Kaap

 

69

 

Irrigation

 

1,021,590

 

620,590

 

334,000

Project on track

 

 

Bengu Trust

Ngodwane

8

Weir and Pipeline (1.2km) /irrigation

375,000

200,000

0

Project implementation to start in Quarter 3.

 

 

Abundant Life Skills cc

Nelspruit

 

11

 

Borehole / Broiler Houses / Fencing

318,461

 

151,000

 

0

Project implementation to start in Quarter 3.

 

 

Sitama Impilo CPA

 

White River

 

 

Upgrading Irrigation / Fencing

235,000

 

145,000

 

0

Project implementation to start in Quarter 3.

 

 

Mathebula Family CPA

Rocky's Drift

 

37

 

Fence / Micro Drip / cool room  

276,000

 

236,000

 

0

Implementation to start in Quarter 3.

 

 

Sabie River Farmers Association

Hazyview

 

75

 

Irrigation Infrastructure (Phase 2)

1,000,000

 

370,000

 

0

Project on track.

 

 

E Mahommed

 

Mara(Croc Gorge)

1

 

Borehole

 

85,229

 

85,279

0

Implementation to start in Quarter 3.

 

Sugarcane

 

Porpax Investments (Pty) Ltd

Komatipoort

 

14

 

Water rights & Drip Irrigation

 

950,000

 

550,000

 

207,000

Project implementation started.

 

 

Khiphulwazi Sugar Cane Project

Mawewe

 

22

 

Fencing - 15 Km

 

127,000

 

77,000

0

Project implementation to start in Quarter 3.

 

 

Driekoppies Combine Sugar-Cane Forum

Driekoppies

 

214

 

Fencing - 22 Km

 

190,000

 

130,000

0

Implementation to start in Quarter 3.

 

TOTALS   

 

 

1,651  

 

9,510,000

 

5,235,869

2,615,000

 

 

 

 

 

 

 

 

 

 

 

 

CASP GERT SIBANDE

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

Project Harvest

 

Amersfoort Apple

 

Amersfoort

 

25

 

Establish apple orchard

 

801, 000

 

250,000

 

6,000

Project on implementation started.

 

 

Land Reform farms

 

Msukaligwa

 

270

 

Social mob & BP dev

 

210,000

 

210,000

0

Project implementation to start in Quarter 3.

 

Apple Cluster

 

Hlanganani

 

Daggakraal

 

560

 

Establish apple orchard

 

4,832,990

 

1,490,571

0

Project on track

 

Upper Komati

 

Mantjolo Trust

 

Roux's farm

 

200

 

Develop irrigation system

 

1,700,000

 

501,792

19,000

Project implementation started.

 

 

Sukuma Mswati

 

Vygeboom

 

130

 

Develop irrigation system

 

800,000

 

468,982

0

Project implementation to start in Quarter 3.

 

Food Security

 

Khuphukani

 

Ngodini

 

13

 

Fencing & irrig material

 

140,000

 

110,000

60,000

Project implementation started.

 

 

Buhle Buyeza

 

Robinsdale

 

7

 

Fencing

 

30,000

 

30,000

20,000

Project implementation started

 

 

Zamukuzakha

 

Bettysgoed

 

16

 

Fencing

 

35,000

 

35,000

15,000

Project implementation started

 

 

Zwelisha

 

Hartebeeskop

 

9

 

Fencing

 

25,000

 

0

15.000

Project implementation started

 

 

Thuthukani

 

Avontuur

 

24

 

Fencing & irrigation  material

 

120,000

 

97,664

60,000

Project implementation started

 

 

Khutsalani 2

 

Oshoek

 

7

 

Layer house & water provision

 

200,000

 

66,000

10,000

Project implementation started

 

 

Yinhle Lento

 

Mayflower

 

10

 

Fencing & irrigation material

 

60,000

 

60,000

0

Project implementation to start in Quarter 3.

 

 

Vukabasha

 

Tjakastad

 

18

 

Fencing & irrigation material

 

263,535

 

148,141

24,000

Project implementation started.

 

 

Ekulindeni Hydroponics

 

Ekulindeni

 

12

 

Improve irrigation & coolant system

 

270,571

 

150,571

0

Project implementation to start in Quarter 3.

 

 

Inhlansi Youth

 

Bethal

 

12

 

Fencing

 

22,904

 

653

0

Project implementation to start in Quarter 3.

 

TOTALS  

 

 

1,313

 

 

9,511,000

3,619,374

451,000

 

 

 

 

 

 

 

 

 

 

 

CASP NKANGALA

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

Biodiesel (Soybeans Project)

 

Manzi - Mahle Trust 

 

Blaaupoort, Rietkuil & Mooiwater

 

   150

 

Fencing, resources survey, soil preparations, harvesting, mechanization units, storage facility,

662,500

 

218,000

75,000

Project implementation started.

 

 

Rietkuil Farmer Association

 

Rietkuil

 

   253

 

capacity building and training, Drilling and equipping boreholes, waterways & contouring & Production inputs

662,500

 

218,000

0

Project implementation to start in Quarter 3.

 

Beef Production

 

KwaMaQhuze Farming Trust

 

KwaMaqhuze

 

     15

 

Construction of fence, dipping tanks, Livestock handling facilities, Drilling and equipping boreholes, Purchasing of livestock

1,400,000

 

486,000

31,000

Project implementation started.

 

 

Siza Goat Production Project

 

Siza (Hlakaniphani) - Draaihoek

 

       8

 

Abattoir/cold storage facilities, Upgrading road infrastructure, Hide & skin processing plant, Transportation facilities

 

1,300,000

 

468,000

0

Project implementation to start in Quarter 3.

 

Broiler production (including food security projects)

 

Sinamuva Kwezolimo

 

Groenfontein

 

     11

 

Construction of complete broiler houses, Security fencing, Provision of automated standby generator,

 

2,251,332

 

426,666

0

Project implementation to start in Quarter 3.

 

 

Itireleng Layer Project 

 

Maganagobushwa

 

11

 

Electricity connection, Drilling and equipping boreholes, Fence erection, water supply systems

610,459

 

208,555

19,000

Project implementation started.

 

 

Ntshatlala Vegetable project

 

Tshikanoshi

 

     17

 

Borehole drilling, casing and quantity testing

43,125

 

11,000

0

Project implementation to start in Quarter 3.

 

 

Tshwaraganang Vegetable Project

 

Lefisoane

 

       8

 

Borehole drilling, casing and quantity testing

 

43,125

 

11,0000

0

Project implementation to start in Quarter 3.

 

 

Ramokgeletsane Youth Poultry (Broiler) Project

 

Ramokgeletsane

 

       8

 

Four litre water fount, regulators, cheek feeds trays,infrared-lamp+holder, Automatic feeders, water boots, brooms,

125,881

 

100,000

0

Project implementation to start in Quarter 3.

 

 

Zivuseni Poultry (Broiler) Project

 

Vriesgewaght

 

     14

 

electric+ tubing,tabs,20mmPipe & Elbow, stand pipe1m,T. pipe hemp, Feeds, medication, litter material, chicks

126,200

 

100,000

0

Project implementation to start in Quarter 3.

 

 

Simunye Farmers (Broiler)

 

Kwaggafontein industrial site

 

       7

 

Tube feeders, Anti-waste ring, Chick feed tray,4L water fount, Anti drown ring, fount heightener, broiler drinker mk 6

123,400

 

96,000

0

Project implementation to start in Quarter 3.

 

 

Sidlakhona Poultry Project (Broiler)

 

Troya Trust

 

       6

 

Tube feeders, Anti-waste ring, Chick feed tray,4L water fount, Anti drown ring, fount heightener, broiler drinker mk 6

162,000

 

115,000

0

Project implementation to start in Quarter 3.

 

 

Amogelang Poultry (Broiler) Project

 

Lefisoane

 

     10

 

Tube feeders, Anti-waste ring, Chick feed tray,4L water fount, Anti drown ring, fount heightener, broiler drinker mk 6

104,478

 

79,478

0

Project implementation to start in Quarter 3.

 

Continuing projects

 

Alkebu-Lan cc

 

Portion 24, Rietkuil 491 JS

 

   121

 

Fencing 2km; planning, designing & construction of cattle kraals, installation of neck clamp and scale

200,000

 

119,500

0

Project implementation to start in Quarter 3.

 

 

Completing Outstanding projects items 2004/05

 

Various areas in Nkangala District

 

     89

 

Broiler feeders and drinkers, Broiler houses and equipment Eskom Electricity connection, Drilling and equipping of boreholes

1,518,333

 

300,000

0

Project implementation to start in Quarter 3.

 

TOTALS   

 

 

728

 

9,333,333

2,957,199

125,000

 

 

 

 

 

 

 

 

LANDCARE PROJECTS

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

EHLANZENI

Thaba Tlou LandCare Project

 

Thaba Chweu

 

 

Soil Conservation for Agricultural Production

134,547

 

35,000

13,000

Project implementation started.

 

 

Langeloop LandCare Project

 

Nkomazi

 

 

Veld Improvement for Animal Production

116,450

 

30,000

87,200

Project on track

 

 

Lomshiyo LandCare Project

Nkomazi

 

Soil Conservation for Agricultural Production

92,260

11,071

0

Project implementation to start in Quarter 3.

 

 

Mdladla  LandCare Project

 

Nkomazi

 

 

Soil Conservation for Agricultural Production

136,800

25,000

83,000

Project on track

 

 

Nkomazi Through LandCare Project (111)

 

Nkomazi

 

 

Veld Improvement for Animal Production

600,000

90,000

600,000

Project complete

 

 

Tsembanani LandCare Project

 

Nkomazi

 

 

Veld Improvement for Animal Production

34,000

12,000

0

Project implementation to start in Quarter 3.

 

 

Mlilo LandCare Project

 

Nkomazi

 

 

Veld Improvement for Animal Production

27,000

10,000

0

Project implementation to start in Quarter 3.

 

 

Ehlanzeni & Nkangala Awareness Program

Nkomazi

 

LandCare awareness

200,000

25,000

29,000

Project on track

 

DISTRICT TOTAL

 

 

 

 

1,219,467

238,071

812,200

 

 

GERT SIBANDE

Inhlansi Yothando LandCare Project

 

Govan Mbeki

 

 

Soil Conservation for Crop Production

100,000

 

30,000

1,000

Project implementation to start in Quarter 3.

 

 

Isibane LandCare Project

 

Albert Luthuli

 

 

Soil Conservation for Crop Production

84,060

 

20,000

47,890

Project on track.

 

 

Zendelingspost LandCare Project

 

Mkhondo

 

 

Soil Conservation for Crop Production

800,000

 

70,000

0

Project implementation to start in Quarter 3.

 

 

Injabulo LandCare Project

 

G Sibande

 

Soil Conservation for Crop Production

31,000

10,000

0

Project implementation to start in Quarter 3.

 

 

Shukuma LandCare Project

 

G Sibande

 

Soil Conservation for Crop Production

 

32,000

10,000

0

Project implementation to start in Quarter 3.

 

 

Gert Sibande Awareness Program

G Sibande

 

LandCare Awareness

100,000

25,000

9,000

Project implementation to start in Quarter 3.

 

 

Inkanyezi Traditional Healers

 

Mkhondo

 

 

Nursery of Indigenous Medicinal Plants

70,000

 

20,000

 

Project implementation to start in Quarter 3.

 

DISTRICT TOTAL

 

 

 

 

1,217,060

185,000

57,890

 

 

 

 

 

 

 

 

 

 

 

 

NKANGALA

Enhancing Agricultural Production

 

 

Soil Conservation for crop production

449,243

53,909

18,747

Project implementation started.

 

 

Mkobola LandCare Project

Mkobola

 

Soil Conservation for Crop Production

 

420,156

50,419

0

Project implementation to start in Quarter 3.

 

 

Mmaduma Moloto LandCare

Moloto

 

JuniorCare Awareness & greening

65,000

7,800

0

Project implementation to start in Quarter 3.

 

 

Bareki LandCare

Dr JS Moroka

 

Veld Improvement for Animal Production

164,200

19,704

67,000

Project implementation started.

 

 

Mloyisane LandCare

Dr JS Moroka

 

Soil Conservation for Crop Production

 

64,197

7,704

0

Project implementation to start in Quarter 3.

 

 

MmaPhake LandCare Project

 

Dr JS Moroka

 

 

Soil Conservation for Crop Production

 

529,087

90,000

 

Project implementation to start in Quarter 3.

 

DISTRICT TOTALS

 

 

 

 

1,691,883

229,536

85,747

 

 

TOTALS   

 

 

 

 

4,005,000

 

955,837

 

 

 

 

 

 

 

 

 

INFRASTRUCTURE PROJECTS

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

 

Irrigation Repairs Tonga B & C

 

Block B & C

 

 

Repairs and replacement of irrigation components that were vandalized, stolen and burnt

1,500,000

 

375,000

0

Project implementation to start in Quarter 3.

 

 

Dam Safety Inspections

 

 

 

Dam inspection and maintenance

 

1,000,000

 

250,000

0

Project implementation to start in Quarter 3.

 

 

Fencing 3 dams

 

 

 

Fencing of 3 dams  :  Lundi, Khumbula 1 and 2

 

1,200,000

 

300,000

0

Project implementation to start in Quarter 3.

 

 

Compensation for Lundi Dam

 

Lundi

 

 

Compensation for land/property taken up by the dam

 

300,000

 

75,000

0

Project implementation to start in Quarter 3.

 

 

Lundi Irrigation (30 ha)

 

Lundi

 

 

Designing and installation of irrigation system

 

1,200,000

 

300,000

0

Project implementation to start in Quarter 3.

 

 

Sibange Irrigation

 

Sibange

 

 

Installation of 87ha of mains and laterals

 

2,000,000

 

500,000

0

Project implementation to start in Quarter 3.

 

 

Ngwenya Dam

 

 

 

Construction of Mgwenya earth dam

 

1,500,000

 

375,000

0

Project implementation to start in Quarter 3.

 

 

Professional Fees

 

 

 

Retention funds.

 

1,500,000

 

375,000

0

Project implementation to start in Quarter 3.

 

TOTALS   

 

 

 

 

10,200,000

 

2,550,0000

0

 

 

 

 

 

 

 

AGRICULTURAL RURAL DEVELOPMENT FUND PROJECTS

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

 

Mathebula CPA

 

Rocky's Drift

 

37

 

Poultry abattoir

 

250,000

 

 

0

Project implementation to start in Quarter 3.

 

 

Cairn Lemon

 

Mataffin

 

74

 

Lemon production

 

417,400

 

417,000

417,000

Project on track.

 

 

Hhoyi Maize Milling Phase 2

 

Hhoyi Trust

 

17

 

Maize milling

 

1,092,800

 

600,000

0

Project implementation to start in Quarter 3.

 

 

Vukuzenzele Bee Project

 

Vaalbank

 

8

Bee keeping

 

750,000

 

450,000

510,000

Project on track 65% of project funds transferred

 

 

Pankop Fruit Processing Phase 2

 

Pankop

 

107

Fruit drying

 

1,250,000

 

1,250.000

1,200,

Project complete

 

 

Hlakaniphani Goat Project

 

Middelburg

 

15

Goat production

 

2,300,000

 

400,000

0

Project implementation to start in Quarter 3.

 

 

Morholo Maize Milling

 

Vaalbank

 

11

Maize milling

 

150,000

 

150,000

 

150,000

 

Project complete

 

 

Mphatlhalatsane Co-op

 

Grootvlei

 

15

Cooking oil producing 

 

2,230,000

 

500,000

0

Project implementation to start in Quarter 3.

 

 

Siyathemba Fruit Processing

 

Piet Retief

 

10

Fruit processing for juice making

 

850,000

 

250,000

0

Project implementation to start in Quarter 3.

 

 

Daggakraal maize Milling

 

Daggakraal

 

30

Maize milling

 

1,006,800

 

300,000

378,000

Project implementation started.

 

PROVINCIAL  TOTALS

 

 

 

 

10,297,000

3,300,000

2,655

 

 

 

 

 

 

 

 

 

 

 

 

MASIBUYELE EMASIMINI PROJECTS

 

Anchor

Project Name

Location

Beneficiaries

Project Description

Total budget 2006/07

Quarter 2 Projection

Quarter 2 Actual

Remarks

Measures

Masibuyele Emasimini

 

Ehlanzeni

Gert Sibande

Nkangala

 

Land tillage and acquisition of farming equipment

21,000,000

15,000,000

16,792

Project implementation started in Quarter 2.

 

PPROVINCIAL TOTAL

 

 

 

 

21.000.000

5,597,000

16,792

 

 

 

 

 



Building No 6 Second Floor, No 7 Government Boulevard, Riverside Park X 2, NELSPRUIT, 1200
Private Bag X 11219, NELSPRUIT 1200, SOUTH AFRICA
Tel: 013-7666020
Fax: 013-7668429