EHLANZENI DISTRICT MUNICIPALITY, MPUMALANGA PROVINCE

FINANCIAL VIABILITY AND FINANCIAL MANAGEMENT AS AT

4 AUGUST 2006

 

 

CONTENT

A. Introduction

B. Analysis of 2004/05 Budget

C. Operating and infrastructure grants for 2006/07

D. Municipal Infrastructure Grant

E. Amounts Owed to Municipalities

F. External Audit Results and Financial Management Capacity

G. Conclusion

 

A. INTRODUCTION

The analysis of the viability of Ehlanzeni District Municipality and its local municipalities focus on the following four areas:

This analysis concludes with the overall findings and an indication of the possible strategies that may be needed to improve the viability of the District Municipality and its local municipalities.

B. ANALYSIS OF THE 2004/05 BUDGETS

The District Municipality and its local municipalities budgeted for a total expenditure of R1,094 billion for the 2004/05 financial year. Of this amount R221 million (20.2%) was for capital expenditure and R873 million (78%) for operating expenditure. Total budgeted operating revenue of R968 million resulted in an operating surplus of R95 million.

The operating and capital budgets of the District Municipality and its local municipalities for the 2004/05 financial year are summarised in the table below.

Operating income, operational and capital expenditure: 2004/05

Municipality

Operating revenue

 

(R’000)

Operating Expenditure

(R’000)

Capital Expenditure

(R’000)

Total Expendi-ture Budget

(R’000)

Capital as % of total

Expenditure

Capital grant funding as % of capital

Thaba Chweu

106 311

104 585

107

104 692

-

0

Mbombela

423 032

422 585

107 743

530 328

20

52

Umjindi

67 186

66 763

29 850

96 613

31

88

Nkomazi

122 361

121 431

56 250

177 681

32

52

Bushbuckridge

105 170

105 170

12 776

117 946

19

100

Ehlanzeni

144 355

52 374

14 098

66 472

21

0

Total

968 415

872 908

220 824

1 093 732

20

57

(Source: National Treasury Local Government Database: September 2005)

Although it appears as if Ehlanzeni District Municipality had budgeted for an operating surplus of more than R95 million, it is not a true reflection. The correct situation is that the District Municipality included the operational intergovernmental grants of R64 million under revenue but excluded the spending of the grants from operating expenditure. The local municipalities have all budgeted for a small operating surplus. This indicates that planned expenditure will be financed by budgeted revenue and there should not be an adverse impact on the overall financial position of the municipalities if there is adherence to their budgets.

The budgeted operating revenue that is used to finance salaries and wages, repairs and maintenance, interest and redemption and the provision for bad debt is summarised in the table below.

Expenditure categories as percentage of operating revenue

Operating Budget Component

Amounts budgeted (R’000)

Percentage of total revenue (%)

Total operating revenue

968 340

100.0

Salaries and wages

334 564

34.1

Repairs and maintenance

73 344

8.5

Interest and redemption

82 324

9.5

Provision for bad debt

4 396

0.5

(Source: National Treasury Local Government Database, September 2005)

The expenditure on salaries and wages as a percentage of total operating revenue for the District and its local municipalities was 34%, which is higher than the norm of 30% of operating revenue determined by National Treasury. Repairs and maintenance at 7.5% of total operating revenue was slightly lower than the norm of 10-12% of operating revenue, also determined by National Treasury.

Interest and redemption was well below the norm of 15 – 20% of total operating revenue. This was due to more than 50% of infrastructural capital expenditure being financed from capital grants rather than other interest bearing and repayable forms of financing (see comments on budgeted capital expenditure below).

Hardly any provision was made in the budgets of the local municipalities within the District for bad debt. The less than a percentage of the annual operating revenue that are set aside by the District as a whole for the writing off of bad debt indicate that the collection of rates and service charges included in budgeted annual revenue was almost 100%. The Auditor General qualified the audit reports of one of the municipalities for inadequate provision being made for bad debt over the last three financial years (see table in section on audit findings). Three of the municipalities have not received audit reports for the three years under review, so the opinion of the Auditor-General on this matter in these municipalities is not known.

Capital expenditure as a percentage of total expenditure (consisting of operating and capital expenditure) was approximately 20% for the District Municipality and its local municipalities. Sustainable capital expenditure levels were deemed to be between 10 – 15% of operating expenditure. It should be noted that 54% of capital expenditure was financed through capital grants, which accounted for the relatively higher spending on this category of expenditure.

The budgeted capital expenditure by nature of asset for the District as a whole is summarised as follows:

Budgeted capital expenditure per asset category: 2003/04 and 2004/05

Asset category

Budget 2004/05

(R’000)

% of total capital expenditure (%)

Budget 2003/04

(R’000)

% of total capital expenditure (%)

Land and buildings

17 092

8

21 708

10

Roads and Storm water

36 654

17

69 748

31

Water infrastructure

102 732

46

46 015

20

Electricity infrastructure

17 133

8

16 730

7

Sewerage infrastructure

11 582

5

19 382

9

Housing

0

0

0

0

Other infrastructure

10 807

5

32 824

15

Community assets

6 747

3

4 170

2

Movable assets

12 897

6

10 064

5

Other

5 200

2

1 739

1

Total Capital Budget

220 824

100

224 659

100

(Source: National Treasury Local Government Database, 2004 – 2005)

The majority of capital expenditure was on infrastructure for the provision of water, roads and storm water. The spending on water infrastructure is supported by the information provided in the section on service delivery and infrastructure.

Grants and Intergovernmental Transfers

The following table shows the dependence on operating grants by the District Municipality and its local municipalities for the 2004/05 budgeted year.

Subsidies and grants as percentage of operating revenue: 2004/05

Municipality

Subsidies and grants

(R’000)

Total Operating Revenue

(R’000)

Subsidies and grants as a percentage of total revenue (%)

Thaba Chweu

18 600

106 311

17

Mbombela

72 433

423 032

17

Umjindi

10 690

67 186

16

Nkomazi

30 721

122 361

25

Bushbuckridge

105 170

105 170

100

Ehlanzeni

64 037

144 355

44

Total

301 651

968 415

31

(Source: National Treasury Local Government Database, September 2005)

The operating grants were relatively higher in relation to total operating revenue and supported the provision of free basic services to communities within the District Municipality and its local municipalities. The benchmark for grant dependency is 5% of operating revenue. Operating grants were 31% of the total operating income of the District as a whole and indicate the need to develop the own revenue bases of the municipalities in the District.

The table below indicates the operating as well as the infrastructure grants funding for Ehlanzeni District Municipality and its local municipalities (including Bushbuckridge) in terms of the intergovernmental transfers for the 2006/07 financial year.

C. OPERATING AND INFRASTRUCTURE GRANTS FOR 2006/07 (R’000)

 

Grant

 

Municipality

Equitable Share

Financial Management

Systems Improvement

Water Services Operating

Total Operating Grants

Infra-structure

Total Grants

Thaba Chweu

24 749

500

734

 

25 983

9 140

35 123

Mbombela

102 361

500

734

 

103 595

66 580

170 175

Umjindi

15 378

500

3 000

 

18 878

7 247

26 125

Nkomazi

81 926

500

1 484

28 615

112 525

45 981

158 506

Bushbuckridge

113 530

500

884

 

114 914

92 951

207 865

Ehlanzeni

94 771

500

1 000

39 504

135 775

18 497

154 272

Total

432 714

3 000

7 836

68 119

509 669

240 397

752 066

(Source: Division of Revenue Act, 2006.)

These levels of operating grants should ensure that the relatively high level of expenditure on infrastructure for the provision of water, roads and storm water included in the capital budget is sustainable given the under-developed own revenue base of the District. Included in the equitable share of Ehlanzeni District Municipality is a grant of R88 million to replace the RSC levies in 2006/07 financial year. This will make the District as a whole slightly more dependent on operating grants.

 

D. MUNICIPAL INFRASTRUCTURE GRANT (MIG)

MIG Allocations from 2004/05 to 2008/9

(Indicative figures published in the Division of Revenue Act 2006)

2004/05

The Ehlanzeni District Municipality received a total of R100, 250 million in the 2004/2005 financial year. The municipality managed to spend 99 percent of their budget by 30 June 2005. The reason for the 1% under-spending was that the Mbombela projects were registered late due to the lack of information on project registration. The Bushbuckridge projects were implemented by the Bohlabela district.

2005/2006

Ehlanzeni District’s total allocation for 2005/06 was R121,458 million. Umjindi and Nkomazi local municipalities received MIG funding for the first time in this financial year. Thaba Chweu Local Municipality’s allocation was channelled through the District Municipality. By June 2006 the District had spent 95% of its MIG allocations. The following factors contributed to the remaining 5% under-expenditure:

(Ehlanzeni District Municipality, Report: Presidential Imbizo: 04-05 August 2006).

2006/07

For the current financial year Ehlanzeni District Municipality received a total of R234,841 million. All of the local municipalities received their allocations directly with the resulting consequence of the District Municipality’s allocation being reduced significantly from the previous two financial years. Thaba Chweu received MIG funding for the first time in this financial year. As table 14 reflects, Ehlanzeni will get a MIG allocation in the 2007/08 and 2008/09 financial years.

Project Management Units (PMUs)

The Project Management Unit (PMU) is a ring-fenced unit within a municipality responsible for the management of (MIG) infrastructure (capital) projects. However, should a municipality have adequate capacity to fulfil project management functions, it is not necessary to establish a PMU. A receiving municipality may utilize from 0.5 – 5% from its MIG allocation, as determined on a sliding scale, for project management functions.

The following table reflect the maximum amounts allowed for PMUs per the municipalities, as well as the dates on which the PMUs were approved:

PMU’s Allocation

Municipality

Allocation 2004/05 & Date Approved

Allocation 2005/06 & Date Approved

Allocation 2006/07 & Date Approved

Thaba Chweu LM

-

-

R443,000

29/03/2006

Mbombela LM

R1,997,000

09/11/2004

R2,173,000

R2,151,000

Umjindi LM

-

R402,000

10/08/05

R351,000

Nkomazi LM

-

R873,000

11/07/05

R1,784,000

Bushbuckridge LM

-

-

R2,463,000

Ehlanzeni DM

R1,883,000

01/11/04

R1,489,000

12/08/05

R897,000

11/05/06

Unlike the previous financial years, all the Local Municipalities including the District have been allocated PMU funds for the 2006/07 financial year. Of these municipalities, only two (i.e. Thaba Chweu LM and Ehlanzeni DM) have submitted business plans for their PMUs for approval.

Commitments on projects

The table below presents the MIG allocations commitments for the 2006/07 and 2007/08 financial years per municipality as at 30 June 2006:

Commitments on MIG Allocation of 2006/07 and 2007/08

Municipality

2006/07 (R'000)

2007/08 (R'000)

 

Allocation

Commitment

Allocation

Commitment

Thaba Chweu

8 866

8 866

9 963

3 081

Mbombela

65 189

65 189

70 754

47 203

Umjindi

7 030

7 030

7 899

7 899

Nkomazi

44 601

18 567

50 119

Bushbuckridge

91 212

91 212

98 167

34 890

Ehlanzeni DM

17 942

15 061

20 162

 

234 841

205 924 (88%)

257 065

93 073 (36.2%)

(Source: MIG June 2006)

2006/07 Commitments

All municipalities including the district have committed a total of R205,92 million (i.e. 88%) of the MIG funds allocated for 2006/07 financial year. Thaba Chweu, Mbombela, Umjindi and Bushbuckridge Local Municipalities have committed 100% of their allocations and are thus able to commit their 2007/2008 allocations. Ehlanzeni DM and Nkomazi LM have committed 84% and 42% of their allocation for the 2006/07 financial year.

2007/08 Commitments

All municipalities including the district have committed a total of R93,07 million (i.e. 36%) of the MIG funds allocated for 2006/07 financial year.

Projects registered per category since the inception of MIG April 2004

Project Category

MIG Funds (R'000)

Number of Households to benefit

Libraries

R 2,271

8,982

Multi Purpose Community Halls

R 8,550

24,000

Multi Purpose Sport Centre

R 1,000

Municipal Roads

R 24,309

1,362

PMU

R 4,458

Roads

R 120,497

187,708

Sanitation

R 98,573

76,461

Sidewalks

R 8,237

11,323

SMIF

R 1,952

Solid Waste Disposal Site

R 1,414

4,887

Stormwater

R 10,052

4,040

Taxi Ranks

R 1,560

Water

R 272,601

186,494

Total

R 555,474

505,257

(Source: dplg MIG, July 2006)

Of a total of R555.5m utilised for infrastructure development in the District, 49% of MIG funds were utilised on water related projects. Roads projects made use of 22% of the funds. Sanitation projects made use of 18% of the funds.

Interventions by the MIG Unit

The National MIG Unit and the Provincial MIG Unit have engaged with Ehlanzeni District Municipality and the local municipalities to discuss challenges faced and how assistance can be provided. The Provincial MIG Unit provided hands on training to the MIG representative of Ehlanzeni District Municipality. It has been agreed that monthly meetings will be held with all the receiving municipalities. In order to monitor progress closely, bi-weekly reporting arrangement was also introduced.

E. AMOUNTS OWED TO MUNICIPALITIES

The table below shows the collection period in days for each municipality in Ehlanzeni District based on information obtained for the 2004/05 financial year. The formula used to calculate debtors’ days outstanding is [Debtors outstanding / (Billed revenue x 365 days)]. The norm is a 45-day collection period after consumers have been billed.

Debtors collection periods in days: 2004/05*

Municipality

Billed revenue

(R’000)

Outstanding debtors

(R’000)

Debtors days outstanding

(days)

Thaba Chweu

76 154

45 935

220

Mbombela

308 319

197 353

233

Umjindi

48 704

20 380

152

Nkomazi

81 982

11 895

53

Ehlanzeni

72 015

17 502

88

Total

587 174

293 065

182

(Sources: Direct enquiries, municipalities in the District, June 2006)
*
Bushbuckridge has been excluded in this section as there ere too many discrepancies in the financial data that has been obtained. (See also the section on audit findings.

All the municipalities in the District are exceeding the norm of not collecting billed revenue within 45 days of consumers being billed. Mbombela and Thaba Chweu Municipalities take on average 233 days and 220 days respectively to collect revenue from consumers from the date the consumers are billed. If debtors are outstanding for long period it is unlikely that these amounts will be collected and therefore may have to be written off.

 Nkomazi Municipality collects it debtors in a relatively short period but it still has to implement cost recovery for services in the rural areas. The cost recovery and stringent credit control measures are only taken place in the previously established towns. The issue of cost recovery for services is also highlighted in the section on service delivery and infrastructure.

F. EXTERNAL AUDIT RESULTS AND FINANCIAL MANAGEMENT CAPACITY

The information on external audit reports has been obtained from the municipalities directly.

Audit findings 2003 – 2005

Municipality

Report 2002/03

Issued Opinion

Report 2003/04

Issued Opinion

Report 2004/05

Issued Opinion

Thaba Chweu

No

No report

No

No report

No

No report

Mbombela

Yes

Unqualified

Yes

Unqualified

Yes

Qualified:

Fixed asset register incomplete;

Lack of supporting documentation for suspense accounts shown as creditors;

Incorrect accounting treatment of provision for bad debt.

Umjindi

Yes

Qualified:

Writing off of debt and inadequate provision for bad debt

Yes

Qualified:

Same reason as in 2002/03;

Incomplete asset register;

Problems with the cash flow statement in the financial statements

Yes

Qualified:

Same reasons as in 2003/04;

Water reticulation losses of 23%;

VAT control account not reconciled.

Nkomazi

No

No audit done

No

No audit done

No

No audit done

Bushbuckridge

Yes

Disclaimer:

Lack of supporting documents for financial transactions;

Financial systems problems.

Yes

Disclaimer:

Lack of supporting documents for financial transactions;

Financial systems problems.

No

Audit in progress

Ehlanzeni

No

No audit done

No

No audit done

No

No audit done

(Source: Direct enquiries, Municipalities in the District, July 2006)

The District Municipality, Nkomazi and Thaba Chweu local municipalities have not received audit reports for the last three financial years. One of the reasons is that the municipalities did not or were quite late with the submission of annual financial statements. Nkomazi Municipality was a participating municipality in the Project Consolidate initiative through which the dplg, the municipality and the Institute of Municipal Finance Officials (IMFO) worked together to ensure the eradication of the backlog in completion of annual financial statements of the municipality. There has also already been a provincial intervention in Thaba Chweu Municipality.

The qualified audit findings of Mbombela and Umjindi can be rectified. It flows generally from insufficient provisioning for irrecoverable debt and incomplete fixed assets registers. However, in the case of Umjindi the reasons for qualified audit reports are carried forward from one year to another with other reasons gradually being added to the reasons for the Auditor-General qualifying the audit reports.

National Treasury has classified the financial capacity of the Ehlanzeni District Municipality and Mbombela Municipality as high. Two local municipalities, Umjindi and Nkomazi, are classified as having high capacity, while Thaba Chweu is the only low capacity municipality in the District.

Intervention strategies

All the municipalities will benefit from credit control and revenue enhancement support. What is more important is to find ways to reconcile the ability of municipalities to recover costs and providing minimum level of services.

Thaba Chweu and Nkomazi Municipalities have already received assistance under Project Consolidate. In respect of those municipalities that received qualified opinions, support to rectify the circumstances giving rise to the qualification should be provided. This can be done as a following phase of the collaboration project amongst the municipality, dplg and IMFO.

G. CONCLUSION

The analysis of the viability of Ehlanzeni District Municipality and its local municipalities indicates that the District spent a relatively large portion of its operating budget on the repair and maintenance of property, plant and equipment in the District but that emphasis should be put on ensuring that the grant funded assets are adequately maintained and thereby enabling sustainable service delivery in the District to be rendered. The percentage of operating revenue that is spent on maintenance must be compared with the large amount of capital expenditure that is taken place on the provisioning of service infrastructure.

There is also a need to enhance revenue collection strategies in especially Mbombela, Thaba Chweu and Umjindi Municipalities. This will at the same time also address one the main reason for the qualification of audit reports, namely inadequate provisioning for irrecoverable consumer debt.