EHLANZENI DISTRICT MUNICIPALITY, MPUMALANGA PROVINCE
FINANCIAL VIABILITY AND FINANCIAL MANAGEMENT AS AT
4 AUGUST 2006
CONTENT |
A. Introduction |
B. Analysis of 2004/05 Budget |
C. Operating and infrastructure grants for 2006/07 |
D. Municipal Infrastructure Grant |
E. Amounts Owed to Municipalities |
F. External Audit Results and Financial Management Capacity |
G. Conclusion |
A. INTRODUCTION
The analysis of the viability of Ehlanzeni District Municipality and its local municipalities focus on the following four areas:
This analysis concludes with the overall findings and an indication of the possible strategies that may be needed to improve the viability of the District Municipality and its local municipalities.
B. ANALYSIS OF THE 2004/05 BUDGETS
The District Municipality and its local municipalities budgeted for a total expenditure of R1,094 billion for the 2004/05 financial year. Of this amount R221 million (20.2%) was for capital expenditure and R873 million (78%) for operating expenditure. Total budgeted operating revenue of R968 million resulted in an operating surplus of R95 million.
The operating and capital budgets of the District Municipality and its local municipalities for the 2004/05 financial year are summarised in the table below.
Operating income, operational and capital expenditure: 2004/05
Municipality |
Operating revenue
(R’000) |
Operating Expenditure (R’000) |
Capital Expenditure (R’000) |
Total Expendi-ture Budget (R’000) |
Capital as % of total Expenditure |
Capital grant funding as % of capital |
Thaba Chweu |
106 311 |
104 585 |
107 |
104 692 |
- |
0 |
Mbombela |
423 032 |
422 585 |
107 743 |
530 328 |
20 |
52 |
Umjindi |
67 186 |
66 763 |
29 850 |
96 613 |
31 |
88 |
Nkomazi |
122 361 |
121 431 |
56 250 |
177 681 |
32 |
52 |
Bushbuckridge |
105 170 |
105 170 |
12 776 |
117 946 |
19 |
100 |
Ehlanzeni |
144 355 |
52 374 |
14 098 |
66 472 |
21 |
0 |
Total |
968 415 |
872 908 |
220 824 |
1 093 732 |
20 |
57 |
(Source: National Treasury Local Government Database: September 2005)
Although it appears as if Ehlanzeni District Municipality had budgeted for an operating surplus of more than R95 million, it is not a true reflection. The correct situation is that the District Municipality included the operational intergovernmental grants of R64 million under revenue but excluded the spending of the grants from operating expenditure. The local municipalities have all budgeted for a small operating surplus. This indicates that planned expenditure will be financed by budgeted revenue and there should not be an adverse impact on the overall financial position of the municipalities if there is adherence to their budgets.
The budgeted operating revenue that is used to finance salaries and wages, repairs and maintenance, interest and redemption and the provision for bad debt is summarised in the table below.
Expenditure categories as percentage of operating revenue
Operating Budget Component |
Amounts budgeted (R’000) |
Percentage of total revenue (%) |
Total operating revenue |
968 340 |
100.0 |
Salaries and wages |
334 564 |
34.1 |
Repairs and maintenance |
73 344 |
8.5 |
Interest and redemption |
82 324 |
9.5 |
Provision for bad debt |
4 396 |
0.5 |
(Source: National Treasury Local Government Database, September 2005)
The expenditure on salaries and wages as a percentage of total operating revenue for the District and its local municipalities was 34%, which is higher than the norm of 30% of operating revenue determined by National Treasury. Repairs and maintenance at 7.5% of total operating revenue was slightly lower than the norm of 10-12% of operating revenue, also determined by National Treasury.
Interest and redemption was well below the norm of 15 – 20% of total operating revenue. This was due to more than 50% of infrastructural capital expenditure being financed from capital grants rather than other interest bearing and repayable forms of financing (see comments on budgeted capital expenditure below).
Hardly any provision was made in the budgets of the local municipalities within the District for bad debt. The less than a percentage of the annual operating revenue that are set aside by the District as a whole for the writing off of bad debt indicate that the collection of rates and service charges included in budgeted annual revenue was almost 100%. The Auditor General qualified the audit reports of one of the municipalities for inadequate provision being made for bad debt over the last three financial years (see table in section on audit findings). Three of the municipalities have not received audit reports for the three years under review, so the opinion of the Auditor-General on this matter in these municipalities is not known.
Capital expenditure as a percentage of total expenditure (consisting of operating and capital expenditure) was approximately 20% for the District Municipality and its local municipalities. Sustainable capital expenditure levels were deemed to be between 10 – 15% of operating expenditure. It should be noted that 54% of capital expenditure was financed through capital grants, which accounted for the relatively higher spending on this category of expenditure.
The budgeted capital expenditure by nature of asset for the District as a whole is summarised as follows:
Budgeted capital expenditure per asset category: 2003/04 and 2004/05
Asset category |
Budget 2004/05 (R’000) |
% of total capital expenditure (%) |
Budget 2003/04 (R’000) |
% of total capital expenditure (%) |
Land and buildings |
17 092 |
8 |
21 708 |
10 |
Roads and Storm water |
36 654 |
17 |
69 748 |
31 |
Water infrastructure |
102 732 |
46 |
46 015 |
20 |
Electricity infrastructure |
17 133 |
8 |
16 730 |
7 |
Sewerage infrastructure |
11 582 |
5 |
19 382 |
9 |
Housing |
0 |
0 |
0 |
0 |
Other infrastructure |
10 807 |
5 |
32 824 |
15 |
Community assets |
6 747 |
3 |
4 170 |
2 |
Movable assets |
12 897 |
6 |
10 064 |
5 |
Other |
5 200 |
2 |
1 739 |
1 |
Total Capital Budget |
220 824 |
100 |
224 659 |
100 |
(Source: National Treasury Local Government Database, 2004 – 2005)
The majority of capital expenditure was on infrastructure for the provision of water, roads and storm water. The spending on water infrastructure is supported by the information provided in the section on service delivery and infrastructure.
Grants and Intergovernmental Transfers
The following table shows the dependence on operating grants by the District Municipality and its local municipalities for the 2004/05 budgeted year.
Subsidies and grants as percentage of operating revenue: 2004/05
Municipality |
Subsidies and grants (R’000) |
Total Operating Revenue (R’000) |
Subsidies and grants as a percentage of total revenue (%) |
Thaba Chweu |
18 600 |
106 311 |
17 |
Mbombela |
72 433 |
423 032 |
17 |
Umjindi |
10 690 |
67 186 |
16 |
Nkomazi |
30 721 |
122 361 |
25 |
Bushbuckridge |
105 170 |
105 170 |
100 |
Ehlanzeni |
64 037 |
144 355 |
44 |
Total |
301 651 |
968 415 |
31 |
(Source: National Treasury Local Government Database, September 2005)
The operating grants were relatively higher in relation to total operating revenue and supported the provision of free basic services to communities within the District Municipality and its local municipalities. The benchmark for grant dependency is 5% of operating revenue. Operating grants were 31% of the total operating income of the District as a whole and indicate the need to develop the own revenue bases of the municipalities in the District.
The table below indicates the operating as well as the infrastructure grants funding for Ehlanzeni District Municipality and its local municipalities (including Bushbuckridge) in terms of the intergovernmental transfers for the 2006/07 financial year.
C. OPERATING AND INFRASTRUCTURE GRANTS FOR 2006/07 (R’000)
Grant
Municipality |
Equitable Share |
Financial Management |
Systems Improvement |
Water Services Operating |
Total Operating Grants |
Infra-structure |
Total Grants |
Thaba Chweu |
24 749 |
500 |
734 |
|
25 983 |
9 140 |
35 123 |
Mbombela |
102 361 |
500 |
734 |
|
103 595 |
66 580 |
170 175 |
Umjindi |
15 378 |
500 |
3 000 |
|
18 878 |
7 247 |
26 125 |
Nkomazi |
81 926 |
500 |
1 484 |
28 615 |
112 525 |
45 981 |
158 506 |
Bushbuckridge |
113 530 |
500 |
884 |
|
114 914 |
92 951 |
207 865 |
Ehlanzeni |
94 771 |
500 |
1 000 |
39 504 |
135 775 |
18 497 |
154 272 |
Total |
432 714 |
3 000 |
7 836 |
68 119 |
509 669 |
240 397 |
752 066 |
(Source: Division of Revenue Act, 2006.)
These levels of operating grants should ensure that the relatively high level of expenditure on infrastructure for the provision of water, roads and storm water included in the capital budget is sustainable given the under-developed own revenue base of the District. Included in the equitable share of Ehlanzeni District Municipality is a grant of R88 million to replace the RSC levies in 2006/07 financial year. This will make the District as a whole slightly more dependent on operating grants.
D. MUNICIPAL INFRASTRUCTURE GRANT (MIG)
MIG Allocations from 2004/05 to 2008/9
(Indicative figures published in the Division of Revenue Act 2006)
2004/05
The Ehlanzeni District Municipality received a total of R100, 250 million in the 2004/2005 financial year. The municipality managed to spend 99 percent of their budget by 30 June 2005. The reason for the 1% under-spending was that the Mbombela projects were registered late due to the lack of information on project registration. The Bushbuckridge projects were implemented by the Bohlabela district.
2005/2006
Ehlanzeni District’s total allocation for 2005/06 was R121,458 million. Umjindi and Nkomazi local municipalities received MIG funding for the first time in this financial year. Thaba Chweu Local Municipality’s allocation was channelled through the District Municipality. By June 2006 the District had spent 95% of its MIG allocations. The following factors contributed to the remaining 5% under-expenditure:
(Ehlanzeni District Municipality, Report: Presidential Imbizo: 04-05 August 2006).
2006/07
For the current financial year Ehlanzeni District Municipality received a total of R234,841 million. All of the local municipalities received their allocations directly with the resulting consequence of the District Municipality’s allocation being reduced significantly from the previous two financial years. Thaba Chweu received MIG funding for the first time in this financial year. As table 14 reflects, Ehlanzeni will get a MIG allocation in the 2007/08 and 2008/09 financial years.
Project Management Units (PMUs)
The Project Management Unit (PMU) is a ring-fenced unit within a municipality responsible for the management of (MIG) infrastructure (capital) projects. However, should a municipality have adequate capacity to fulfil project management functions, it is not necessary to establish a PMU. A receiving municipality may utilize from 0.5 – 5% from its MIG allocation, as determined on a sliding scale, for project management functions.
The following table reflect the maximum amounts allowed for PMUs per the municipalities, as well as the dates on which the PMUs were approved:
PMU’s Allocation
Municipality |
Allocation 2004/05 & Date Approved |
Allocation 2005/06 & Date Approved |
Allocation 2006/07 & Date Approved |
Thaba Chweu LM |
- |
- |
R443,000 29/03/2006 |
Mbombela LM |
R1,997,000 09/11/2004 |
R2,173,000 |
R2,151,000 |
Umjindi LM |
- |
R402,000 10/08/05 |
R351,000 |
Nkomazi LM |
- |
R873,000 11/07/05 |
R1,784,000 |
Bushbuckridge LM |
- |
- |
R2,463,000 |
Ehlanzeni DM |
R1,883,000 01/11/04 |
R1,489,000 12/08/05 |
R897,000 11/05/06 |
Unlike the previous financial years, all the Local Municipalities including the District have been allocated PMU funds for the 2006/07 financial year. Of these municipalities, only two (i.e. Thaba Chweu LM and Ehlanzeni DM) have submitted business plans for their PMUs for approval.
Commitments on projects
The table below presents the MIG allocations commitments for the 2006/07 and 2007/08 financial years per municipality as at 30 June 2006:
Commitments on MIG Allocation of 2006/07 and 2007/08
Municipality |
2006/07 (R'000) |
2007/08 (R'000) |
||
|
Allocation |
Commitment |
Allocation |
Commitment |
Thaba Chweu |
8 866 |
8 866 |
9 963 |
3 081 |
Mbombela |
65 189 |
65 189 |
70 754 |
47 203 |
Umjindi |
7 030 |
7 030 |
7 899 |
7 899 |
Nkomazi |
44 601 |
18 567 |
50 119 |
|
Bushbuckridge |
91 212 |
91 212 |
98 167 |
34 890 |
Ehlanzeni DM |
17 942 |
15 061 |
20 162 |
|
|
234 841 |
205 924 (88%) |
257 065 |
93 073 (36.2%) |
(Source: MIG June 2006)
2006/07 Commitments
All municipalities including the district have committed a total of R205,92 million (i.e. 88%) of the MIG funds allocated for 2006/07 financial year. Thaba Chweu, Mbombela, Umjindi and Bushbuckridge Local Municipalities have committed 100% of their allocations and are thus able to commit their 2007/2008 allocations. Ehlanzeni DM and Nkomazi LM have committed 84% and 42% of their allocation for the 2006/07 financial year.
2007/08 Commitments
All municipalities including the district have committed a total of R93,07 million (i.e. 36%) of the MIG funds allocated for 2006/07 financial year.
Projects registered per category since the inception of MIG April 2004
Project Category |
MIG Funds (R'000) |
Number of Households to benefit |
Libraries |
R 2,271 |
8,982 |
Multi Purpose Community Halls |
R 8,550 |
24,000 |
Multi Purpose Sport Centre |
R 1,000 |
|
Municipal Roads |
R 24,309 |
1,362 |
PMU |
R 4,458 |
|
Roads |
R 120,497 |
187,708 |
Sanitation |
R 98,573 |
76,461 |
Sidewalks |
R 8,237 |
11,323 |
SMIF |
R 1,952 |
|
Solid Waste Disposal Site |
R 1,414 |
4,887 |
Stormwater |
R 10,052 |
4,040 |
Taxi Ranks |
R 1,560 |
|
Water |
R 272,601 |
186,494 |
Total |
R 555,474 |
505,257 |
(Source: dplg MIG, July 2006)
Of a total of R555.5m utilised for infrastructure development in the District, 49% of MIG funds were utilised on water related projects. Roads projects made use of 22% of the funds. Sanitation projects made use of 18% of the funds.
Interventions by the MIG Unit
The National MIG Unit and the Provincial MIG Unit have engaged with Ehlanzeni District Municipality and the local municipalities to discuss challenges faced and how assistance can be provided. The Provincial MIG Unit provided hands on training to the MIG representative of Ehlanzeni District Municipality. It has been agreed that monthly meetings will be held with all the receiving municipalities. In order to monitor progress closely, bi-weekly reporting arrangement was also introduced.
E. AMOUNTS OWED TO MUNICIPALITIES
The table below shows the collection period in days for each municipality in Ehlanzeni District based on information obtained for the 2004/05 financial year. The formula used to calculate debtors’ days outstanding is [Debtors outstanding / (Billed revenue x 365 days)]. The norm is a 45-day collection period after consumers have been billed.
Debtors collection periods in days: 2004/05*
Municipality |
Billed revenue (R’000) |
Outstanding debtors (R’000) |
Debtors days outstanding (days) |
Thaba Chweu |
76 154 |
45 935 |
220 |
Mbombela |
308 319 |
197 353 |
233 |
Umjindi |
48 704 |
20 380 |
152 |
Nkomazi |
81 982 |
11 895 |
53 |
Ehlanzeni |
72 015 |
17 502 |
88 |
Total |
587 174 |
293 065 |
182 |
(Sources: Direct enquiries, municipalities in the District, June 2006)
*
All the municipalities in the District are exceeding the norm of not collecting billed revenue within 45 days of consumers being billed. Mbombela and Thaba Chweu Municipalities take on average 233 days and 220 days respectively to collect revenue from consumers from the date the consumers are billed. If debtors are outstanding for long period it is unlikely that these amounts will be collected and therefore may have to be written off.
Nkomazi Municipality collects it debtors in a relatively short period but it still has to implement cost recovery for services in the rural areas. The cost recovery and stringent credit control measures are only taken place in the previously established towns. The issue of cost recovery for services is also highlighted in the section on service delivery and infrastructure.
F. EXTERNAL AUDIT RESULTS AND FINANCIAL MANAGEMENT CAPACITY
The information on external audit reports has been obtained from the municipalities directly.
Audit findings 2003 – 2005
Municipality |
Report 2002/03 Issued Opinion |
Report 2003/04 Issued Opinion |
Report 2004/05 Issued Opinion |
|||
Thaba Chweu |
No |
No report |
No |
No report |
No |
No report |
Mbombela |
Yes |
Unqualified |
Yes |
Unqualified |
Yes |
Qualified: Fixed asset register incomplete; Lack of supporting documentation for suspense accounts shown as creditors; Incorrect accounting treatment of provision for bad debt. |
Umjindi |
Yes |
Qualified: Writing off of debt and inadequate provision for bad debt |
Yes |
Qualified: Same reason as in 2002/03; Incomplete asset register; Problems with the cash flow statement in the financial statements |
Yes |
Qualified: Same reasons as in 2003/04; Water reticulation losses of 23%; VAT control account not reconciled. |
Nkomazi |
No |
No audit done |
No |
No audit done |
No |
No audit done |
Bushbuckridge |
Yes |
Disclaimer: Lack of supporting documents for financial transactions; Financial systems problems. |
Yes |
Disclaimer: Lack of supporting documents for financial transactions; Financial systems problems. |
No |
Audit in progress |
Ehlanzeni |
No |
No audit done |
No |
No audit done |
No |
No audit done |
(Source: Direct enquiries, Municipalities in the District, July 2006)
The District Municipality, Nkomazi and Thaba Chweu local municipalities have not received audit reports for the last three financial years. One of the reasons is that the municipalities did not or were quite late with the submission of annual financial statements. Nkomazi Municipality was a participating municipality in the Project Consolidate initiative through which the dplg, the municipality and the Institute of Municipal Finance Officials (IMFO) worked together to ensure the eradication of the backlog in completion of annual financial statements of the municipality. There has also already been a provincial intervention in Thaba Chweu Municipality.
The qualified audit findings of Mbombela and Umjindi can be rectified. It flows generally from insufficient provisioning for irrecoverable debt and incomplete fixed assets registers. However, in the case of Umjindi the reasons for qualified audit reports are carried forward from one year to another with other reasons gradually being added to the reasons for the Auditor-General qualifying the audit reports.
National Treasury has classified the financial capacity of the Ehlanzeni District Municipality and Mbombela Municipality as high. Two local municipalities, Umjindi and Nkomazi, are classified as having high capacity, while Thaba Chweu is the only low capacity municipality in the District.
Intervention strategies
All the municipalities will benefit from credit control and revenue enhancement support. What is more important is to find ways to reconcile the ability of municipalities to recover costs and providing minimum level of services.
Thaba Chweu and Nkomazi Municipalities have already received assistance under Project Consolidate. In respect of those municipalities that received qualified opinions, support to rectify the circumstances giving rise to the qualification should be provided. This can be done as a following phase of the collaboration project amongst the municipality, dplg and IMFO.
G. CONCLUSION
The analysis of the viability of Ehlanzeni District Municipality and its local municipalities indicates that the District spent a relatively large portion of its operating budget on the repair and maintenance of property, plant and equipment in the District but that emphasis should be put on ensuring that the grant funded assets are adequately maintained and thereby enabling sustainable service delivery in the District to be rendered. The percentage of operating revenue that is spent on maintenance must be compared with the large amount of capital expenditure that is taken place on the provisioning of service infrastructure.
There is also a need to enhance revenue collection strategies in especially Mbombela, Thaba Chweu and Umjindi Municipalities. This will at the same time also address one the main reason for the qualification of audit reports, namely inadequate provisioning for irrecoverable consumer debt.