PHASE
|
TASKS |
OUTPUTS |
IMPACT |
Conceptualization
July 2003 – Aug 2003
|
- Drafted Terms of Reference
- Published Tender
- Appointed successful bidder
|
- Terms of Reference developed
- Tender was published
- Appointment of service provider
|
|
Design of Programme
Sept 2003 – Feb 2004
|
- Development of Training Programme
- Development of Training Manual
|
- Completed the Training Manual
|
- Programme and Training Manual was proved to be appropriate and useful
|
Pilot
April 2004 - July 2004
|
- Implemented 3 of the 3-day workshops
|
- Successfully trained two groups of 25 people
|
- The groups now implementing the INDS
|
Assessment of Impact
August 2004 – March 2005 |
- Evaluation study of the participants
|
- Received the evaluation report
- Had a breakfast seminar for senior government officials with SAMDI
|
- Members are now participants in the IDCCD and the Cluster Task Teams
|
Design of Second Phase
August 2005
|
- Review of the Manual
- Development of the Toolkit
|
- Improved manual and toolkit
|
- Improvement in the implementation of second phase
|
Implementation of Second Phase
October 2005
|
- Implement workshops for 2 groups of 25 each at national level
- Implement workshops in 3 provinces for 25 people in each case
- Implement two workshops at local government level
|
- Implementation of the training
- Officials with capacity to implement INDS
|
- Officials with impact to implement INDS
|