State of Readiness for the 2010 Soccer World Cup
Presentation to the Portfolio Committee on Provincial and Local Government
Presented by: William Smith
Date: Tuesday, September 6, 2005
THIS CITY WORKS FORYOU
Agenda
·
Programme Calibration
·
Submission of Financial Requirements
·
Athlone Stadium Precinct Upgrade
·
Ongoing Development of Projects
·
Consultations
·
The Way Forward
Programme Calibration
·
Project Calibration Workshop on 29, 30 August 2005 -Followed up on 5 September 2005
·
Review of Programme Structure
-Defining the projects
-High Level Strategic Deliverables
-Critical Success Factors
-Risks
·
Programme Functioning
-Roles of Project Managers
-Initial Identification of Project Managers
Submission of Financial Requirements
·
Priority Statements Submitted to Provincial Finance by 17 August
2005
·
Included financial requirements for
- Athlone Stadium Precinct
- Athlone Area Upgrade
-Practice Venues (Barcelonal Swartklip)
-Transport
- Athlone & Borchards Quarry Waste Water Treatment Works
·
Priority Statements submitted by Provincial Finance to National Treasury on 2 September
·
Financial requirements submitted to Development Bank of South Africa (DBSA) on 5 September 2005
·
Financial requirements for Athlone Stadium submitted to LOC on 5 September 2005
Athione Stadium Precinct Upgrade
·
Business case for Athlone Stadium
-Present case to political bearers - September 2005
-Present case to LOC - October 2005
·
Financial Requirements submitted to Province, National Treasury,
DBSA, LOC
·
Installation of additional floodlights completed
·
North Parking Area and Access Road completed
·
East Stand Upgrade
-Contract Awarded
-Contractor on site
Ongoing Development of Projects
Currently in Progress
·
Tourism Marketing
·
Trade & Investment Marketing
·
Arts & Culture
·
Communications
·
Sports Development
·
Transport & Traffic Management
·
Safety and Security
Consultations
·
Ongoing consultations with City representatives
·
Ongoing consultations with Province
·
Parastatals
- Airports Company South Africa (ACSA)
-South African Rail Commuter Corporation (SARCC)
·
Private Sector
-Presentations to Cape Chamber of Commerce
·
Feedback sessions to general public and sub-councils
The Way Forward
·
Finalisation of Project Structure & Functioning
·
Appointment of Project Managers to identified work streams
·
Finalisation of Financial Submissions
·
Presentation and finalisation of the Athlone business case
THIS CITY WORKS FOR YOU
Conclusion
Let us work together for a better city