Report of the Portfolio Committee on Water Affairs and Forestry on Study Tour to Western Cape Region, dated 10 September 2004:
The Portfolio Committee on Water Affairs and Forestry, having conducted a study tour to the Western Cape Region from 2 to 6 August 2004, reports as follows:
Table of Contents
1. Names of delegation
2. Purpose of study tour
3. Places visited
4. Structure of the report
5. Day 1: Presentation by the Department of Water Affairs and Forestry at the Knysna Log Inn
5.1. Conservation Forestry Management
5.2. Key achievements identified by DWAF
5.3. Challenges faced by DWAF
5.4. Concerns raised by DWAF
6. Forestry restructuring in the Southern and Western Cape
6.1. Background to commercial forestry restructuring
6.2. Background on SAFCOL’s Restructuring in the Southern andWestern
Cape
6.3. Background on the Southern Cape and Tsitsikama forests transfer to
South African National Parks (SANPARKS)
6.4. Progress with Cape conversion and the MTO transaction
6.5. Progress with the SANPARKS transfers
6.6. Outstanding Issues
6.6.1. The conversion process and the MTO
6.6.2. SANPARKS transfer
6.6.3. Implications in the transfer process
6.6.4. Challenges in the transfer process
7. Planning and management of the Southern Cape Forests
7.1. Community involvement through Participatory Forestry Management
7.1.2. Successes
7.1.3. Challenges
7.2. Concerns raised by the Committee
7.2.1. Responses by DWAF to concerns raised by the Committee
8. Day 2: Field visit: Diepwalle Forestry Estate
8.1. Staff Complement
8.2. Diepwalle Community
8.3. Diepwalle Crèche
8.3.1. Problems with regards to the Cr che
8.3.2. Successes with regards to the Crèche
9. Harvesting of SevenWeek Ferns from the Forests in the Southern Cape
9.1. Target groups
9.2. Processes and procedures followed to implement The project
9.2.1. Selection of participants
9.2.2. Price structure
9.2.3. Key findings
9.2.4. Lessons learned
10. Khoisan Village Community Project
10.1.Advantages of the project
10.2.Analysis of the Nursery Community Project
11. Storms River Forest Station site visit: Storms River Adventures and Tree Top Canopy Tours
11.1. Joint activities as presented to the Committee
11.1.1. Questions raised by the Committee
11.1.1.2. Responses to the questions raised by the Committee
12. George: Presentation of Sanitation Project
12.1.Water and sanitation overview
12.1.1. Recommendation made by Mayor
12.2. Presentation: Sanitation Project
12.2.1. Roles and responsibilities
13. Day 3: Visit to the Farm Dweller Sanitation Project at Calitzdorp and the introduction of Geohydrology/groundwater by DWAF
13.1.Geohydrology/groundwater
13.2.Area visited by the Committee
13.2.1. Questions raised by the Committee
13.2.1.1. Responses by DWAF
13.3.Outeniqua Pass Groundwater Project
13.3.1. Responses and concerns of the Committee
13.3.1.1. Responses by DWAF
14. Farm Dweller Sanitation at Calitzdorp
14.1.Community involvement in the process of VIP toilets and in the
decision-making process
14.1.1. Challenges identified by DWAF
14.1.2. Concerns and responses by the Committee
14.2.Community Project, Gamka Wes-Calitzdorp
14.2.1. Questions by the Committee to the Community
14.2.1.2. Responses by the Community
15. Departure to Heidelberg
15.1.Concerns and questions raised by the Committee
15.1.2. Responses by DWAF
15.2.Heidelberg: Overberg Water Board
15.2.1. The future role of the Overberg Water Board
15.2.1. The nature of the schemes of the Overberg Water Board
15.2.2.1. Challenges
15.2.2.2. Questions and concerns raised by the Committee
15.2.2.3. Reponses by Overberg Water Board
16. Arabella Water Recycling
17. Day 4: Theewaterskloof Dam
17.1.Overview of the Theewaterskloof Dam
17.1.2. Questions raised by the Committee
17.1.3. Responses by DWAF
17.2.Trans Caledon Tunnel Authority (TCTA)
17.2.1. Berg River Project
17.2.2. Questions raised by the Committee
17.2.2.1. Responses by TCTA
18. The Working forWater Programme
18.1.The Assegaaibos Working for Water Programme
18.1.2. Questions asked by the Committee to the workers
18.1.2.1. Responses by the workers
18.1.3. Concerns of the Committee raised with TCTA
19. Boland District Council
19.1.Sanitation conditions in Boland
20. Day 5: Khayelitsha, presentation and site visit with The City of Cape Town
20.1.Questions raised by the Committee
20.1.2. Responses by the City of Cape Town
20.2.Khayelitsha site visit: VIP pilot project
20.2.1. Questions raised by the Committee
20.2.1.1. Responses by the City of Cape Town
21. Water services management in the City of Cape Town
22. Recommendations made by the Committee
22.1.Conservation forestry management
22.2.Planning and management of the Southern Cape Forests
22.3.Field visit: Diepwalle Forestry Estate
22.4.Khoisan Community Project
22.5.Water supply Calitzdorp
22.6.Community Project, Gamka Wes, Calitzdorp
22.7.The bucket system in Zoar
22.8.Overberg Water Board, bucket system in Genadendal
22.9.Khayelitsha, water and sanitation
22.10.Khayelitsha site visit, VIP sanitation project
23. The Way Forward
24. Note of appreciation
1. Names of Delegation
Ms. C.C. September (ANC), Ms. S. Maine (ANC), Ms. M.M. Gumede
(ANC), Ms. M.S. Manana (ANC), Mr. Z. Kati (ANC), Ms. L. Ngwenya
(ANC), Ms. T.E. Lishiva (ANC), Mr. J. Phala (ANC), Mr. V. Mabuyakhulu
(ANC), Mr. S. Simmons (NNP), Ms. D. van der Walt (DA), Mr. M.W.
Sibuyana (IFP), Ms. S.N Sigcau (UDM), Mr. G.D. Corker (Researcher),
Ms. S. Cassiem (Committee Secretary), Ms. O. Siebritz (Committee
Assistant).
2. Purpose of Study Tour
A delegation of the Portfolio Committee on Water Affairs and Forestry
undertook a study tour in the Southern Cape and parts of theWestern Cape
from the 2nd to the 6th of August 2004. The Committee previously visited
the other provinces, excluding the Southern and Western Cape. The
purpose of the study tour was to:
_ Evaluate the delivery of Free Basic Services (water and sanitation).
_ Evaluate the viability of forestry and deforestation, including poverty
alleviation.
_ Assess water resources management in the Western Cape.
3. Places Visited
The delegation held sessions in eight towns of the Western Cape, i.e.
Knysna, George, Calitzdorp, Heidelberg, Bot River, Franschoek,
Stellenbosch and Khayelitsha in Cape Town. The delegation also visited
and had a session in Tsitsikama and Stormsrivier in the Southern Cape.
During these sessions, the delegation engaged in discussions with various
stakeholders, including the Department of Water Affairs and Forestry,
non-governmental organisations, the Khoisan community who presented a
community project. In Khayelitsha the Committee had a session with
officials from the City of Cape Town and also embarked on a visit to
Khayelitsha where officials from the City of Cape Town presented the
Committee with a pilot sanitation project.
4. Structure of Report
The report presents the daily activities undertaken by the delegation while
on the study tour. The report therefore outlines the various presentations
introduced to the Committee by the various stakeholders. Secondly, the
report outlines site visits undertaken by the Committee. Thirdly, the report
identifies the concerns and questions raised by the Committee to the
institutions who presented to the Committee and in addition the report
outlines the responses of the institutions. The report also discusses the
salient issues and common problems that were identified by the Committee
during the presentations and while on site visits. Lastly, the report outlines
the recommendations put forward by the Committee for action.
5. Day 1: Presentation by the Department of Water Affairs and Forestry at the Knysna Log Inn
The delegation met with the officials from the Department ofWater Affairs
and Forestry, namely, Dr. Henk van Vliet (Chief Director, Southern
Region), Mr. L. Mossop-Rousseau (Manager, Forestry), Mr. Ceba Mtoba
(Director, Forestry) and Mr. M. Lucas (Area Manager, Southern Cape).
Other officials present were introduced as Mr. J Truter, Mr. Mfeleshake
Mahlangu, Mr. Kobus Venter, Mr. G. Durrheim, Mr. Siya Kobese, and Mr.
W. Vermeulen. Other officials who joined in the study tour at a later stage
are Mr. Rashied Khan (Director,Water Affairs and Forestry,Western Cape),
Mr. Klaas Havenga (Estate Manager, Diepwalle), Mr. K. Havenga, Mr. L.
du Plessis, Mr. J. van Staden and Mr. Mike Smart. The objective of the
Committee was to obtain a sense of Forestry and Deforestation, and also to
determine whether these two aspects are benefiting the notion of poverty
alleviation. These Officials were tasked to inform the Committee about
these issues. From their presentation, the following was extracted:
5.1. Conservation Forestry Management
_ DWAF manages 41 538. 6 hectares of State forest land in the Southern
Cape and Tsitsikama. This land is scattered on the narrow coastal strip
to the South of the Outeniqua and Tsitsikama mountain ranges,
between George in theWest and Kareedouw in the East, with a small
area known as Loerie Nature Reserve occurring further East at
Longmore plantation near Hankey.
_ 43 000 mountain catchment areas (MCA’s) have been added to the
areas managed by DWAF from the 1st April 2004 after the SAFCOL
area was sold to Cape Timber Resources.
_ With the exit of SAFCOL another 41 000 hectares will be added to the
Southern Cape and Tsitsikama management areas over the next 12 to
15 years because of the conversion process of Commercial Forestry
State Land to other land users.
DWAF officials informed the Committee that they have a limited number of
staff with a limited budget to manage areas under DWAF management.
Table 1 represents the number of existing staff for existing management
areas. Table 2 represents the existing budget for existing management
areas.
Table 1. Number of existing staff for existing management areas.
Functions Gender Race Disabled
Persons
Total
Male Female Black Coloured White Indian
Management 6 5 3 1 7 0 0 11
Administration 0 16 0 10 6 0 0 16
Scientific Services 5 2 1 3 3 0 0 7
Supervisors 8 0 1 (11*) 0 0 1 8
Other 100 1 6 72 1 0 2 (101*)
Total 119 24 11 97 17 0 3 (128*)
Vacancies 83
Table 2: Budget for existing management areas.
AO SS REG DIEP FARL TSIT TOTAL
Employees 3 814 4 113 2 271 2 523 12 721
Goods & Services 1 743 531 118 2 200 1 973 2 040 8 656
Transfers/Subsidies 10 13 13 18 54
Machinery &
Equipment
22 30 20 50 47 96 215
Total 5 589 561 138 6 376 4 304 4 677 21 646
According to DWAF officials with the number of staff (as depicted in Table
1) and the budget (as depicted in Table 2), DWAF has to manage the
following:
_ 46 000 hectares of indigenous forests.
_ 5 000 hectares of fynbos.
_ Arboretums (FVC research areas).
_ An area office and three estate offices.
_ The infrastructure of 215 buildings.
_ Seven water schemes.
_ Eleven water reservoirs.
_ Five sewerage purification plants.
_ Two licensed radio communication systems.
_ A fleet of 21 imperial vehicles.
_ Fifteen road construction and specialized harvesting machinery.
_ Thirty-two horses.
_ 318, 93 km of A and B types roads.
_ Seventeen picnic spots.
_ Two hiking trails (173 km) with 9 overnight huts and day walks (127
km).
_ Mountain bike trails (130 km).
_ Three horse trails.
_ Two viewpoints with one in the Garden of Eden and the other at the
Tsitsikama Big Tree, together these viewpoints attract approximately
120 000 visitors per annum.
_ A youth group center.
_ An up market tree top chalet.
5.2. Key achievements that were identified by the officials of DWAF
were:
_ Transformation: DWAF has a sub-forum in place, consisting of
sixteen members.
_ Participatory Forest Management (PFM): DWAF has three established
PFM community forums with several projects in place. In
addition DWAF also has conservation forums in place.
_ Women’s Day Award: DWAF recently won the mini women’s day
award in theWestern Cape. In addition some women will be awarded
at the next women’s day for their achievements in the communities
and forest villages.
_ The Forestry Certification Award (FSC): The Indigenous forests in
the Tsitsikama and the Southern Cape managed by DWAF received
the FSC certification for the sustainable management of these forests
during December 2002. The area managed by DWAF in the Southern
Cape and Tsitsikama which received this certification comprises 36
000 hectares (ha) of indigenous forests and 5000 ha of Fynbos. The
assessment was done by the SOCIETE GENERALE DE
SURVEILlANCE (SGS), the world’s largest independent inspection
agency.
5.3. Officials of DWAF highlighted the following challenges faced by
the Department:
_ Promoting poverty alleviation and reduction through the participatory
forest management of indigenous forests.
_ Providing sufficient indigenous timber for the indigenous timber
industry to avoid or minimize job losses.
_ Proper and sufficient control and eradication of alien vegetation in
indigenous forests, fynbos and management areas, through the proper
management of the area’s budget.
_ Working together with other governmental departments to create an
enabling environment within forestry management.
_ The Biodiversity Act, Forestry Act, Veld Fire Act, makes significant
impact on how things are done. This requires sustainability of forestry
management. Forestry management should therefore be rural-based
and should focus on rural development.
5.4. Concerns raised by DWAF officials
_ One of the major concerns raised by DWAF officials was that the
forests were invaded by communities.With invasion trees are felled to
build houses, for firewood and agricultural purposes. Communities
should be made aware of participatory forestry management. There is
a need to create awareness amongst communities and inform them of
what they can do and what they cannot do. Communities should be
informed about protected trees in the forests, so that when they engage
in harvesting of the trees they would know what to do and what not to
do.
_ Another concern raised by DWAF officials was that trees lying on the
edge of the mountains are mainly fynbos trees, andDWAF has no staff
to manage these trees. In addition, there is no budget available to
manage these trees or to acquire additional staff.
_ With a limited budget it should be noted by the Committee that 90%
of the commercial areas will be converted into conservation areas and
this will put more pressure on DWAF. DWAF with a limited staff and
budget already manages 580 000 ha of forests in theWestern Cape. In
addition DWAF also maintains two types of roads within the 580 000
ha of forestry namely A roads which are used by visitors and the
public and B roads which are used internally by DWAF.
6. Forestry Restructuring in the Southern and Western Cape
6.1. Background to commercial forestry restructuring
SAFCOL was established in 1992 in terms of the Management of State
Forests Act, Act 128 of 1992. SAFCOL was incorporated and registered on
21 September 1992 in terms of the Companies Act, Act 61 of 1973, with the
State as sole shareholder. SAFCOL’s mandate was to manage State owned
plantations on a fully commercial basis and to report profits made through
the ‘‘commercialization of State owned plantation forests’’. The State’s
commercial plantations were transferred to SAFCOL on 01 April 1993. In
1996, it was decided that Government should exit from plantation forestry
operations. This was to be achieved through the privatization of SAFCOL,
who during this period had management authority over the State’s
plantation forestry assets based on an agreement between the State and
SAFCOL in 1994, whereby Government was to sell the State forest land
and standing timber to SAFCOL.
However, the incorporation of the former homeland plantations by DWAF
required the State to reconsider the privatization of State plantations.
DWAF’s plantations were mostly situated next to the SAFCOL plantations
which made selling a combined asset more of an option for Government if
it was to exit from all its plantation operations without having residual
liabilities.
This led to DWAF and SAFCOL combining their forestry activities into
seven regional forestry packages and categorized plantations as follows:
_ Komati package: comprising State and SAFCOL forests in the
Northern Province, subsequently joined with the Mpumalanga forests.
_ Siyaqhubeka package: comprising mainly SAFCOL plantations in the
northern parts of KwaZulu-Natal.
_ Singisi package: comprising State and SAFCOL plantations in the
former Transkei regions of the Eastern Cape.
_ Amathole package: comprising State and SAFCOL plantations
around the Border-Kei region.
_ Mountains to Oceans package: mainly SAFCOL plantations in the
Southern and Western Cape regions.
DWAF officials informed the Committee that in April 1996, Prof Kader
Asmal (then Minister of Water Affairs and Forestry), informed SAFCOL
that the sales agreement was no longer enforceable in terms of the
provisions in the National Forests Act, Government’s programme for
restructuring State owned enterprises as well as its objectives with the
restructuring of State owned forestry interests.
The Department of Public Enterprises (DPE) lead Government’s team to
restructure SAFCOL through placing its five forestry business units on the
market, inviting offers from interested bidders to purchase a majority share
in the forestry business. The land on which the businesses were located
would be retained as State forest land, pending its transfer in terms of the
land reform programme to their rightful owners. The forestry businesses
would lease the land back from Government and the new landowners for a
period of 70 years.
6.2. Background on SAFCOL’s restructuring in the Southern and
Western Cape
In June 1999, SAFCOL’s Board was asked to consider phasing out its
plantation forestry businesses in the Southern andWestern Cape as well as
parts in the Eastern Cape. Government contended that these plantations
were not economically viable as it had a return of less than 10 cubic metre
hectares a year. This issue was raised at Cabinet level, and in September
1993, Cabinet approved in principle to remove approximately 45 000 ha of
State owned plantation land from further commercial forestry production
under SAFCOL and to make the land available for conversion into other
land uses. Cabinet’s decision was announced in a joint media statement on
14 September by the Minister of Water Affairs and Forestry. Cabinet
mandated an inter-departmental committee, generally referred to as the
Cape Conversion Committee, to oversee the process. The Cape Conversion
Committee commissioned a study to investigate the most viable alternative
land uses for the so-called exit areas. A report from the Cape Conversion
Committee was presented to Cabinet in 2001 (Cabinet Memorandum No 21
of 2001). On 27 June 2001 Cabinet approved that within a twenty year
period, approximately 45 000 ha of plantations should be converted into the
following land uses:
_ 29 000 ha for conservation.
_ 6000 ha for community forestry.
_ 9000 ha for agricultural purposes.
_ 200 ha for housing and settlements (this excluded DWAF villages).
6.3. Background on the Southern Cape and Tsitsikama Forests
Transfer to South African National Parks (SANPARKS)
The transfer of the management functions of the Southern Cape and
Tsitisikama State forest areas to SANPARKS is part of DWAF’s objective
to transfer its management functions to other agencies while retaining
policy-making and regulatory functions.
In 2001, a combination of Cabinet memorandums and agreements at
Ministerial level identified three priority areas to be transferred to
SANPARKS through delegation and assignment provisions in the National
Forest Act. These are:
_ The Knysna Tsitsikama forests in the Southern Cape, to create the
Garden Route National Park.
_ Forestry areas around Port St. John’s in the Eastern Cape to create
Pondoland Park.
_ Blyde natural forests and conversion plantation areas in the
‘‘Lowveld’’ to create the Blyde Canyon National Park.
The delegation of the management functions of 97 294 ha of State forest
land in the Southern Cape and Tsitsikama to SANPARKS are:
_ The Southern Cape (Knysna) indigenous forests currently under
DWAF’s management totaling 35 756 ha.
_ The plantation forest areas released by SAFCOL in terms of the MTO
conversion process totaling 14 229 ha.
_ The adjacent mountain catchment areas also previously under
SAFCOL management, totaling 33 562 ha.
Also transferred with the management function was all movable and
immovable assets, budget and staff of the indigenous forests attached to the
establishment and these are:
_ Offices and housing, including movable assets and stock, valued at
approximately R6 million.
_ Personnel and an operational budget of approximately R21 million.
_ Secondment of approximately 130 operational staff.
The additional responsibilities associated with the incorporation of the land
areas previously under SAFCOL’s control are not provided for in DWAF’s
budget and represents an additional budget implication for the Department
and subsequently, Government.
6.4. Progress with Cape conversion and the MTO transaction
The Committee was informed that the conversion process is place and is
managed by the conversion manager together with the Cape Conversion
Committee. The objective of the conversion process is to transfer the
ongoing management responsibility over commercially viable State owned
plantation forest land areas which has been managed by the State for
approximately 70 years to a private enterprise in terms of a lease
agreement. Given the nature of the land areas, three leases are being
finalized and these are:
_ A sustainable forestry lease.
_ An exit areas forestry lease.
_ The Tokai Cecilia lease.
In addition another objective is to transfer, economically unviable forest
land areas, which has been cleared back to the State, for rehabilitation and
conversion into land uses other than forestry. Transfer agreements are
therefore being negotiated with:
_ WCNCB: areas west of the Touws River into the Boland for
conservation purposes.
_ DWAF: for incorporation into the areas going to SANPARKS for
conservation purposes. These areas are areas east of the Touws River
into Tsitsikama.
_ Land Affairs or Agriculture for areas of such nature throughout the
region.
_ Local authorities and SAFCOL to take over 9 forestry worker
villages.
_ DWAF to take over community forestry areas the details of which
have not yet been resolved.
Officials of DWAF also reported to the Committee that the clear-felling
programme, scheduled for a duration of more than 20 years, have over the
past 4 years been implemented and is envisaged to end in 2020.
Approximately 11 000 ha of land is already available for transfer to the
receiving agents. DWAF is therefore under pressure to accept transfer of
management for the land, but is concerned about additional budgetary
allocations for additional line functions.
6.5. Progress with the SANPARKS transfers
In the beginning, DWAF opted for a temporary delegation for the Knysna
transfer. This was because of a result of the inability of SANPARKS to
manage any other land other than a park. It was envisaged that the
arrangement of a temporary delegation would change to an assignment as
soon as the appropriate legislation and systems is in place.
The delegation document was then negotiated and signed by the DWAF
Minister in November 2003. The delegation covers all aspects of
management functions, assets and finance, excluding the transfer of staff.
However, employees entered into a dispute about the delegation document
and its contents. DWAF officials, however, believes that the dispute could
not affect the actual delegation. The dispute process of employees is in the
process of being resolved.
6.6. Outstanding Issues
6.6.1. The conversion process and the MTO
_ The finalisation of the lease negotiations should be completed by 20
August 2004.
_ The finalisation of the Tokai Cecelia lease should also be completed in
the near future.
_ The finalisation of the transfer agreements is also in the process of
being completed.
_ DWAF is still waiting for the approval of the budget for the additional
line function.
6.6.2. SANPARKS transfer
_ DWAF officials reported to the Committee that one of the main
outstanding issues is employee dissatisfaction around the security of
tenure demanded by the workers living in the four villages owned by
DWAF. The workers staying in these houses have demanded that they
are granted ownership of the land and houses since they have been
staying in these houses for a long time. Most of these workers have
been staying in these houses for approximately 30 years. DWAF’s
official position is that workers only have occupier rights in terms of
the ESTA Act. DWAF officials also stated that if they allow workers
security of tenure it could set a precedent for other Government
departments with similar accommodation arrangements. DWAF is
careful as this could have far reaching implications for Government as
a whole. The matter was referred to the GPSSBC to resolve with the
workers Union. A collective agreement is expected at the end of
August 2004.
_ In addition is the taxation of the workers pension at the time of
transfer to other funds. DWAF officials told the Committee that this is
unfair as restructuring has not been workers doing. In addition
workers state that it is against S197 of the Labour Relations Act
(LRA) as it results in workers being worst off. The matter has been
taken up with the Department of Public Service and Administration
and the National Treasury. DWAF also informed the Committee that
some of the workers have demanded cash payouts of their retirement
benefits. However, the Department has rejected this demand as it is
against the principle of continued employment as reflected in S197 of
the LRA transfer. In addition granting workers cash will be morally
irresponsible from the Department given the history of wastefulness
that results in some workers making little provision for retirement.
6.6.3. Issues reported as implications in the transfer process:
_ The reallocation of management over approximately 88 000 ha of
what is now categorized as State forest land to conversion agencies
over the next 20 years.
_ The transfer of 9 former SAFCOL worker villages and 4 DWAF
managed villages to local authorities.
_ 12 600 ha of land for agricultural settlement.
_ The settling in of DWAF over its new function (policy making and
regulatory role).
_ Incorporation of particular large land areas into the conservation
network of the Southern and Western Cape, and preserving a part of
South Africa’s national heritage and securing important water
catchments for future use.
_ Unlocking former State forest land for new economic opportunities,
including:
— Increased investment of approximately R143 million in terms of
agricultural and urban land values.
— Doubling work opportunities from 2400 presently to 4900 at the
end of the exit and conversion period.
6.6.4. DWAF officials reported the following as being challenges:
_ Securing enough finance (R134 over 20 years or R53 million as a once
off payment) to fund the additional conversion line-functionary
responsibility for Government.
_ To assess the financial implications of incorporating agricultural use
areas and villages into Government programmes.
_ Seek and establish greater involvement and participation between
government departments and tiers of government to ensure
sustainability of process during and after implementation. There has
to be ongoing development responsibilities between different stakeholders.
7. Planning and Management of the Southern Cape Forests
7.1. Community involvement through Participatory Forestry Management
DWAF officials reported to the Committee that the Chief Directorate
Forestry within DWAF has undergone a re-orientation and transformation
process in line with the current South African democratic principles,
policies and international trends.
Within this context the Chief Directorate is now considering local peoples
forestry based needs, their role in forest management and is empowering
them through sharing decision-making over forest utilization.
Prior to 1994 the management of indigenous forests in South Africa had a
narrow scientific focus and there was little concern for the social
development potential for forests and forestry. Consequently the majority
of people, especially the poor rural communities, were deprived of access
to forest resources and the benefits derived from them. To enhance the
capacity of poor rural communities to participate in forestry management,
the concept of participatory forestry management was considered by
DWAF.
As a first measure to address the newly adopted departmental approach of
participatory forestry management (PFM), workshops were held throughout
the region to introduce the local communities to this aspect of service
delivery. Contributing to the success of the workshops was the involvement
of the South Cape Business Centre; a non-governmental organization
(NGO) specializing in empowerment of previously disadvantaged communities.
The local communities expressed interest in becoming involved in
the management of forests in their localities and wanted to derive any
possible benefits from PFM.
As a means to promote more community participation in indigenous forest
management, PFM forums, comprising the local communities and DWAF
staff were set up on the three forest estates. Extensive training to local
communities, through PFM forums, on basic management and business
enterprise formation and management skills took place. This resulted in:
_ The development of a PFM Constitution for the region.
_ There was a general consensus across forums that their status is
advisory only, their role being limited to tabling recommendations.
_ Potential projects were introduced which were either accepted or
rejected.
Arising from the above, the following internal systems and procedures
were developed:
_ Procedures for the approval of PFM projects.
_ Criteria for project approval/selection.
_ The formulation of standard project proposals/business plans.
_ The development of a register for PFM projects.
PFM projects included:
_ Harvesting of ferns once they attain seven weeks of age.
_ A nursery and woodturning project in the Khoisan Village.
_ A joint venture in conjunction with Stormsriver Adventures.
7.1.2. DWAF officials reported the following as being successes:
_ Established forums on all three estates (Farleigh, Diepwalle,
Tsitisikama).
_ Communities derived tangible benefits in the form of skills development,
training in business skills, and permanent employment in the
tourism industry (approximately 80% permanent jobs).
7.1.3. DWAF officials reported the following as being challenges:
_ The realization of more PFM projects to ensure tangible benefits to the
communities.
_ Community ownership of PFM projects.
_ Maintaining continuity of membership on PFM forums.
_ DWAF has to play a more pro-active role in identifying and initiating
forest based enterprise.
7.2. Concerns Raised by the Committee
_ Transformation: The Committee expressed concern that the transformation
of DWAF is not gender sensitive, and this is reflected by the
officials of DWAF present. The officials present are all male with no
female representative, which raises questions around transformation
within DWAF.
_ Black Empowerment: The Committee expressed their concern in that
the transfer of forests was only taking place amongst sectors and not
considering the poorest of the poor. It was the opinion of the
committee that empowerment helps the poorest of the poor and thus
far in DWAF’s presentation they have not indicated to the Committee
how the poorest of the poor are facilitated.
_ Vacant posts: From the presentation handouts the Committee has
noted that there are 83 vacant posts. The Committee inquired as to
why these posts are still vacant, for how long has it been vacant and
whether there is a budget to fill these posts? In addition, the
Committee inquired as to whether DWAF has considered how many
of these posts will be filled by women as the existing staff component
are imbalanced, with very little women and only 11 Black staff
members.
_ Involvement of the local community: The Committee inquired as to
whether DWAF has a plan in place for the involvement of the local
community. Has DWAF considered why the local community should
be involved, how they will be involved, and if they are involved, will
their involvement alleviate poverty, sustain peoples lives and will it
create employment?
_ Budget: The Committee was concerned as to why DWAF was not
sufficiently covered in the budget. When applying for money, do
DWAF not consider the reasons for applying for money?
_ Youth Empowerment: What plans have DWAF put in place to
capacitate and empower the youth, and have DWAF done anything
thus far to facilitate youth.
_ Mpumalanga and National Parks Board: DWAF officials mentioned
that the Mpumalanga Parks Board was going to manage one of the
National Parks, has an agreement been reached on this aspect and is
there any budget to manage National Parks?
_ Worker/Union deadlock: In terms of the worker/Union deadlock what
arrangements/agreements has been reached with the Unions? The
Committee also required from DWAF officials to inform/brief them
more on the issue of women’s day in the department.
7.2.1. Responses by DWAF to concerns raised by the Committee
_ Transformation: DWAF indicated to the Committee that there is a
huge backlog in terms of Black staff members and women in the
department. It is envisaged that with the 83 vacant posts, these posts
will be filled by women and Black staff members.
_ Black empowerment and community involvement: DWAF informed
the Committee that through participatory forest management (PFM),
the department would inform the community about forestry. DWAF
also intends to create community structures, through which the
community can be informed about legislation covering forests which
are subject to land claims (i.e. how to gain access to forests).
Communities can also be made aware that plantations were created
for their use and access. Through PFM, DWAF would be able to
provide communities with opportunities (i.e. what can be done with
mushrooms, medicinal plants and what trees can be cut for firewood,
etc.) DWAF is also of the opinion that through PFM employment
opportunities can be created, and also ensure that communities are
given permits to allow them these opportunities. DWAF is also of the
opinion that through PFM, communities can be educated about forests
for commercial use and forests for own use. DWAF wishes to ensure
that communities are given shares in transfers and hopes that
communities will be given access to forests by those taking over
forests. DWAF feels that they are challenged to ensure that they
optimize opportunities to benefit the poor through these structures.
_ Budget: DWAF could not satisfactorily answer the Committee in
terms of their budget deficit and indicated to the Committee that they
did consider all avenues when applying for money.
_ Vacant Positions: DWAF officials informed the Committee that they
are aware of the gender sensitivity issues in the department. The
managerial positions of the department is male dominated and has
been so for many years. In the Knysna Conservation Forestry
management employment equity requires 60% female, therefore,
DWAF officials expect that the 83 vacant positions will be filled
mostly by women. DWAF officials admitted, that the whole of the
Southern cluster is underrepresented by women.
_ Youth: DWAF officials informed the Committee that they have
employed youth in the department. Youth have been employed as fire
foresters, with 6 administrative clerks and 2 young women have been
employed in the scientific services section. DWAF is looking at
employing more young people in the future to capacitate the
department.
_ Mpumalanga Parks Board: The Committee was informed that the
agreement has been signed. The plantations was supposed to be taken
over by SANPARKS, but was eventually taken over by the
Mpumalanga Parks Board. However, there is no budget to manage
these plantations and this will be the case foe next year as well.DWAF
is in the process of applying for money to add into the Medium Term
Framework (MTEF). Approximately R53 million is needed in
additional funds, to assist in managing these plantations. If this proves
to be successful, there are 10 000 ha of plantation land. For
environmental reasons these plantations would be cleared. The
clearing process would result in pulp and firewood being available to
communities; this would also create more jobs for communities. An
impact study is in the process, and negotiations have been done with
all stakeholders as to what is best to do in this regard. DWAF needs to
ensure what is the best land use for the area, taking into account the
socio-economic impact that this venture will have.
_ Worker and Union deadlock with DWAF: The workers are trying to
secure tenure of land and this led to the deadlock between DWAF and
the Unions. Currently, the case is in a conciliation process, however,
it seems that progress is being made. SAFCOL has offered 2 pieces of
State land to Knysna Municipality for the development of residential
areas. These workers would be offered first choice for housing and
these would be serviced properties. DWAF hopes the workers and
Union will accept this instead of wanting ownership of Diepwalle
Village.
_ Women’s day: The Committee was informed that DWAF launched the
competition between provinces. It was a request submitted as to how
to uplift women. This does not only include women in the department,
but also includes women from the villages. TheWestern Cape panel of
judges decided that Knysna has done the best for women. DWAF is
initiating that for the next women’s day competition, which will take
place on the 11th August 2004, women from the community will be
invited to participate. The Minister will identify which women
contributed the most over the past couple of years in the regions and
the Minister will announce the winner the Friday after the 11th August
2004.
8. Day 2: Field Visit: Diepwalle Forestry Estate
The objective of the Committees visit was to observe the management of
the Diepwalle Estate.
The Diepwalle Estate is situated in the center of approximately 45 000 ha
of forest land. The Estate has approximately 20 000 ha of land, of which
1000 ha constitutes fynbos. The Diepwalle forest station remains open 7
days a week.
During the December holidays, approximately 30 to 35 000 people visit the
Diepwalle Estate. Places visited by tourists on the Estate includes, the
Garden of Eden and the Big Tree. The Estate also hosts events such as cycle
tours on its cycle trail. DWAF officials informed the Committee that
Diepwalle Forest Station is the largest Forest Station in South Africa and
hosted the recording of Fiela se Kind (a South African film) featuring one
of South Africa’s famous actors, Dalene Mathee during the apartheid era.
The roads running into the estate are also used for television commercials
during the year.
8.1. Staff Complement
The Diepwalle Forestry Station has approximately 75 posts of which 40 is
occupied. The following table represents the staff compliment at the
forestry station only, of which other posts are occupied by field/site
workers.
Position Number Gender Race
Estate Manager 1 Male White
Assistant Forester 2 Female 1 White/1 Black
Senior Administrative
Assistant
1 Female Coloured
Administrative Assistant 1 Female Coloured
Cleaner 1 Female Coloured
8.2. Diepwalle Community
The Diepwalle community consists of approximately 160 people, of which
only 50 are employed. In one case the Committee heard that in the houses
of Diepwalle one family living in a house consists of 10 people and the
home has only one income. With the salary paid by Forestry these people
cannot survive and mothers are therefore forced to go and work. These
mothers have to leave home early in the morning to reach their workplaces
and return home very late at night, often not having transport and having to
walk home. Recently, contract work was arranged for the mothers, and
many of the children had nobody to care for them during the day. In some
cases, children were left alone at home, some locked out of their houses,
and there was a situation where a child of 2 years old was locked into the
house for the whole day. This had DWAF realize how desperate these
mothers were and approximately 5 months ago (March 2004) a cr che was
opened for the children.
8.3. Diepwalle Crèche
From the houses built by DWAF one of the houses was identified as a
crèche. Seven children between the ages of 2 to 5 were enrolled
immediately, with 3 being enrolled shortly afterwards. DWAF officials
reported that they have 9 children from Buffelsnek (SAFCOL), who can
use the facility, but have no transport. DWAF is struggling to arrange
transport for these children with the school bus, and have recently started to
negotiate with the Department of Education for transport.
The crèche project has been financed by the community through
fundraising and hard work. The cr che is also sponsored by the local people,
Pick & Pay in George who supplies bread for the soup kitchen, and Fruit &
Veg in Knysna who sponsors vegetables and fruit. In addition a soup
kitchen has also been opened at Buffelsnek school and the same is provided
for the community as for the community in the forest village.
8.3.1. DWAFofficials reported the following problems with regards to
the crèche:
_ There is no transportation and they are not able to make use of the
States vehicles as they did in the past.
_ The children are unable to go on field trips.
_ The soup kitchen in Buffelsnek is in danger of being closed down, as
they rely on private transport to take the soup ingredients to the
school.
_ If a child should become ill and needs to be transported to a hospital
there is no vehicle to take the child.
8.3.2. DWAF officials reported the following successes with regards to
the crèche:
_ The créche has a committee who has already drawn up a Constitution,
which will be sent to a Non-profit organization for a fundraising
number, to enable the crèche to achieve more credibility.
_ The library, which was started a few years ago, is being used again.
Old books have been repaired, and other books were also received
from the Knysna Library. They are awaiting more books from the
library.
_ A community vegetable garden has been started, people are supplied
with onion and spinach seeds, and seedling turnover is encouraged.
From this project successful people earn a basic minimum wage of
R35 00 per day.
9. Harvesting of Seven Weeks Fern (Rumohra adiantiformis)
from the Natural Forests in the Southern Cape
The harvesting of ferns on an economic scale from natural forests in the
Southern Cape dates as far back as 1970 when private landowners were
issued permits to harvest small quantities of ferns on their land for the local
flower market. These licensed suppliers could not meet the increasing
demand for fern fronds, resulting in the escalation of illegal harvesting on
State forest land.
In 1982 4 000 ha of State forest land was released for commercial
harvesting of ferns for the European market when tenders were invited to
harvest for a 1 year period. The rapid growth of the industry and the
employment opportunities created, resulted in major economic benefits for
the region, and by 1989 20 000 ha of State forest land was subject to fern
harvesting.
However, little was known about the ecology and dynamics of the species
when commercial harvesting commenced to guide planners and managers
to enforce measures to ensure the sustainable harvesting of the species. In
1983 a research programme was initiated to gain more information on the
ecology, dynamics, phenology and demography of the species and its
response to harvesting. This resulted in the initial picking rotation of five
weeks gradually being increased as research results became available to the
current 15 months. Initial results from intensive monitoring since commercial
harvesting started, indicates that the current levels of harvesting is
sustainable and that fluctuations in yield could be attributed to natural
trends.
9.1. Target groups
Target groups are the unemployed, previously disadvantaged individuals,
especially women, living in close proximity of the natural forests of the
Goudveld section of Farleigh Forest Estate. Fifteen individuals were
identified by the existing Farleigh PFM forum through the PFM structures
to participate and benefit from the project.
9.2. Processes and procedures followed to implement the project,
entailed the following:
9.2.1. Selection of participants
Communities closest to the Goudveld forests were earmarked as beneficiaries
to the project. The communities included communities from Keurhoek,
‘‘Lapland’’ and ‘‘Nuwe Gedeelte’’. Approximately 15 people benefited
from the project and the 3 areas were ‘‘awarded’’ participants in relation to
their population size. Existing community structures (local leaders)
together with PFM forum members devised a representative composition
for each area, taken into consideration gender and specifically targeting the
poor.
9.2.2. Price structure
The minimum tariff prescribed for ferns are R3. 00 per armload, and the
quantity thus not clearly defined. It was decided to give the project a ‘‘once
off harvest’’, giving consideration to a second rotation harvest at a later
stage. It was determined that a team of 15 pickers can earn R35.00 per day
if each picker earns R0.07per leaf harvested. It was decided that prospected
buyers (flower export companies, florists, etc.) must pay at least R0.10 per
leaf frond in order for the beneficiaries to earn R35.00 per day and for the
department to cover overhead costs.
9.3. Key findings
_ Although the harvesting of Seven Week Fern fronds from the
Southern Cape forests became less attractive to larger buyers, it could
still be a viable business opportunity for the small entrepreneur. New
price structures need to be developed to improve the economic
viability of the project.
_ Communities do not have the necessary infrastructure to start
businesses of this magnitude, and needs to link up with already
established businesses to provide logistics like cooling rooms,
transport, existing markets, etc.
_ The department could play an important role in the identification of
viable business opportunities for communities and offer support to get
projects going. The sustainability of projects would require the
development of business skills within the target community.
_ An adaptive management approach whereby provisional harvest
prescriptions are formulated, subject to baseline surveys and the
implementation of monitoring programmes, was successfully followed
to get the project off the ground.
9.4. Lessons learned
_ Sustainable harvest systems should be revised as product specifications
(e.g. size, dimension) change with market demands. An adaptive
management approach is required to quickly react to new demands.
_ Consumptive use of non-timber forest products requires scientific
input in the form of applied research and monitoring to ensure
sustainability. DWAF must be prepared to provide this support to
ensure that consumptive forest-based community projects are successful.
An adaptive management approach can be used successfully
to get projects off the ground while more scientific studies are
conducted to refine harvest prescriptions.
_ The input required from DWAF to develop and adapt sustainable
harvest systems, where necessary, should not be underestimated.
These costs should be viewed within the context of the long-term
benefits from such projects, and DWAF’s commitment towards
ensuring access to forest resources by local communities.
_ The uncertainty regarding the compatibility of DWAF’s PFM policy
and objectives, and other Government legislation, departmental
policies and tariff instructions could handicap the implementation of
PFM projects on the ground and the realization of benefits from forest
resources.
_ Legitimate PFM forums or community structures, through which
projects could be initiated, are essential. Identifying beneficiaries for
projects must be done by the PFM forum in conjunction with existing
structures within the community, and not by DWAF alone. Expectations
must not be raised by DWAF and PFM forum members must
form part of the initial planning (cash flow projections, etc.)
10. Khoisan Village Community Project
The Committee visited the Khoisan Village with the objective of observing
the practical side of the Nursery Community project initiated by DWAF in
joint partnership with the community. DWAF officials informed the
Committee that off-cuts from the trees that have been cut is used by the
community to make different types of woodcrafts. Examples include:
blackwood bowls, honey scoops, goblets, oak-rolling pins etc.
In addition, before harvesting,DWAF allows the community to take out the
small plants from the forests, and these plants are then prepared at the
nursery by the community and sold by the community. The nursery has a
community trust with the members originating from the Tsitsikama area.
The members are prominent leaders amongst the community and are
chosen to represent the community on the trust. Moneys from the trust are
used to assist sports programmes, school projects etc. DWAF depends on
the trust budget for money distribution. People from the community are
trained by Setas, in areas such as fundraising, awareness programmes,
administrative skills (i.e. announcing events, co-coordinating the placing of
notices etc.).
10.1. DWAF officials therefore believe that the project:
_ Creates employment opportunities.
_ Opens up opportunities for skills development.
_ Helps to reduce poverty.
10.2. Analysis of the Nursery Community Project
Although the nursery existed, on the arrival at the Khoisan Village, the
Committee was met by only one person (female) who was introduced as
being the project co-coordinator. The community, involved in the projects
as explained by DWAF officials was not present for the Committee to
capture the working of the actual projects by the community. However, the
Committee was escorted by DWAF officials and shown completed bowls,
roller pins, honey scoops, goblets etc., by the officials of DWAF and the
project co-coordinator. The Committee was also escorted by DWAF
officials and the project co-coordinator to the nursery to see the plants that
are removed from the forests, by the community and cared for at the
nursery. Here as well none of the community involved in the projects could
be observed and the Committee could not capture the working of the
project as explained by DWAF officials.
11. Storms River Forest Station Site Visit: Storms River Adventures
and Tree Top Canopy Tours
The Committee visited Storms River Adventurers and Tree Top Canopy
Tours with the objective of observing the joint activities between DWAF
and Storms River Adventurers and Tree Top Canopy Tours. In addition, the
Committee intended to observe the Bark Harvesting Project as indicated by
DWAF in their presentation, and to be informed about sustainable bark
harvesting.
11.1. Overview of the joint activities as presented to the Committee
The Committee was informed through a presentation that these joint
activities were established in 1998. The activities are based on ecoadventure
tourism and have a 10-point commitment statement, which is
compatible with environmental issues. Tree top canopy tours are operated
in partnership with DWAF and are conducted in such a manner that the
trees are not damaged. The activities consist of mountain bike trails (bike
riding along these trails), cannoning (water activities and bunji jumping),
abseiling, tubing and a woodcutter’s journey.
The Committee was told that in 1998, communities from Storms River
were employed to develop products. In addition, forests and rivers was
utilised to create additional employment. Communities are employed from
five villages around Stormsriver and include, Colestream, Petrusville,
Thornim, Mpumele Village and Sandriftridge. Approximately 180 people
have been trained in field guiding. Communities develop the basic skills
needed in tourism and tour guides. According to the presenter, some of the
youth employed by Storms River Adventures have over the past few years,
obtained employment in Dubai through the skills that they had developed.
In addition, they also have a canopy tour and recommended black-water
tubing as being one of their main products. The canopy tour is based on a
concept from Costa Rica, and is done in an environmentally free manner,
bringing in more tourists and creating more employment. Storms River
Adventures is ranked on the BEE scorecard with approximately 86 points.
In addition, employment was created through the opening of a kitchen,
where ladies from the community provides refreshments and meals. The
kitchen sells approximately 28 000 meals per annum.
11.1.1. Questions raised by the Committee
_ The Committee was interested to know who actually owns Storms
River Adventures and Tree Top Canopy Tours.
_ What opportunities are created for the youth?
_ What is the staff complement of the business?
_ What types of people use the facilities, because drawing from the
pictures outlined on the walls it creates the picture that the activities
are only for those who have money and can afford it and does not cater
for the poor.
_ In what manner does the company give back to the poor?
11.1.1.2. Responses to the questions of the Committee
_ The Committee was informed that the company is a Close Corporation
(CC) company and has an individual owner who has sole surety
for the company. The owner has however set empowerment through
the opening of the kitchen and catering services which is 49% owned
by women from the community. The owner mentioned that he would
however start looking at equity shareholding in the near future, so that
he can give back to the community.
_ The Committee was informed that opportunities are created for the
youth; tour guides are employed and vary between the ages of 18- 30
years old.
_ The Committee was informed that 84% of employment is created for
the disadvantaged.
_ The Committee was informed that the activities created by the
company do apply to people who can afford to pay for the activities.
The market are split between 60% South Africans and 40%
International tourists.
_ The Committee was informed that the company creates job opportunities
for the local community, and on occasions schools from the
local areas are treated to a free day at Storms-river.
12. George/Eden: Presentation of Sanitation Project to Committee
The objective of the Committees visit to George was to be informed
through presentations with the water and sanitation project presently
underway in the Eden District. The Committee was welcomed to George by
the Mayor Mr. Andy Lamont who gave the Committee a brief overview
about the water and sanitation conditions in Eden; the sanitation project
was presented by Mr. Faan van der Merwe, the project co-coordinator.
12.1. Water and Sanitation overview
Eden is situated along the garden route stretching from George into the
Klein Karoo. The Klein Karoo being the area that is highly scarce in water
resources.
According to the Mayor, the Eden District Municipality is meeting its
targets in service delivery. With its money coming from the Consolidated
Municipal Fund and DWAF, in August 2004, 1514 VIP toilets have been
completed. The Mayor stated that it is envisaged that by November 2004 a
total number of 3500 VIP toilets will have been completed in Eden.
The Mayor however, stated that, in Uniondale a settlement not far from
George, the Municipality is experiencing problems in delivering water to
the people. According to the Mayor, ‘‘just to lay the pipeline into the area
has been very problematic with lots of red tape, the people of Uniondale
could have had water supplied to them more than six months ago, but every
six weeks there is a hitch in the process’’.
Water, intended to supply Uniondale, comes from the Harlem Dam, which
also partly supplies the Harlem area with water. However, the ownership of
the Dam is divided between different role-players, for example, the
municipality, DWAF and farmers. This causes lots of discrepancies in
creating the pipeline. The pipeline will supply 86 homes with some homes
having approximately five children per household, a school with approximately
150 pupils in Uniondale with water. However, the Mayor is
optimistic that these problems will be sorted out and that water will be
supplied to Uniondale by December 2004.
The Mayor informed the Committee that a reservoir in Uniondale has been
identified, to build houses for a certain number of people, with the required
infrastructure to make it possible for these people to have access to the
basic water and sanitation services. In addition, Zoar, a town not far from
George, still uses the bucket system. Nothing has been done to provide the
town with water and sanitation. However, the Mayor on the successes
achieved by the Municipality wishes to extend the help of the Municipality
to other Municipalities in other Provinces who are busy struggling to
provide water and sanitation to its people.
12.1.2. Recommendation made by the Mayor
The Mayor recommended that services for the people be decentralized for
example, the Home Affairs offices is situated in George, people from
Uniondale wishing to get to Home Affairs for example to register a birth
have to pay R70 in transport, and these people only earn a salary of
approximately R150.00 per week. This places more burdens on these
people in terms of poverty and survival. If services for the people are
decentralized, it would make living for the people much more convenient.
12.2. Presentation: Sanitation Project
Information gathered for water services development during 2000 showed
that a total of 3791 households in particularly the Klein Karoo, which forms
part of the Eden District did not have adequate sanitation. A structural
approach including both technical and social operations in terms of the
provision of sanitation to farm dwellers was considered and eventually
instituted by the Eden District Municipality. Also needed was a strategic
approach in terms of conducting participating hygiene and sanitation
training (PHAST) for farm dwelling communities prior to the provision of
sanitation units. It was also agreed that peer educators from the
communities be trained to assist health officials with the training of the
various communities.
The vast implementation area and the pressing need for sanitation facilities
asked for new ideas, innovative thinking and planning. After careful
consideration of the different practical ways of construction and bearing all
other constraints in mind, it was decided to provide toilets from lightweight
prefabricated concrete panels (commonly known as VIP’s). The presenter
acknowledged the following advantages of the VIP toilets as:
_ Easy handling.
_ Easy transport.
_ Quick construction, which adds to a vastly reduced logistical process.
It was estimated that with the necessary groundwork, approximately 15 to
20 units (toilets) could be constructed per day. The project would take 6
months to complete i.e. from September 2003 to February 2004. A total
budget of R2.6 million for the first phase and the number of toilets to be
constructed during the first phase should be 1152. Labour intensive
construction methods would be used and the toilets would be constructed
by local small emerging contractors.
12.2.1. Roles and responsibilities:
The Eden District Municipality will fund the project, monitor the project,
approve budgets for implementation, procure pre-fabricated units and
equipment and provide feedback to DWAF.
DWAF will approve the business plan, provide funding, provide guidelines
for groundwater protocol, provide monthly progress reports, and give
variation order approval. The contractor will determine the salary and
labour standards of workers.
It was also decided that there will be a special project steering committee,
which will monitor the project as a whole, appoint the contractors, approve
the budget for implementation and provide feedback to DWAF. In addition,
the project agent, Vela VKE Engineers, would co-ordinate the management
of the project, provide in service training and capacity building of key
personnel, train small contractors and supervise the technical and social
implementation.
The Committee was informed that:
_ The number of people served thus far is 6912.
_ The number of toilets constructed is 3791.
_ The construction cost is estimated to be R8 754 000.
_ The labour cost is estimated to be R300 000.
_ Training costs is estimated to be R380 000.
The Committee informed the presenters that they will not give their views
and opinions on the presentations made, as the Committee had arrived in
George from their previous visits very late. The Committee will however,
ask questions, and give their views and opinions to the presenters the
following day, when making site visits to some of the areas mentioned in
the presentations.
13. Day 3: Visit to the Farm Dweller Sanitation Project at
Calitzdorp and the introduction of Geohydrology/groundwater
by DWAF
The objective of the visit was to observe the Sanitation Project, which was
completed at a farm in Calitzdorp and to be informed by DWAF about
geohydrology, better known as groundwater. The Little Karroo RuralWater
Supply Scheme utilizes groundwater to supply Dysselsdorp and the rural
communities between Dysselsdorp and Calitzdorp, as well as drinking
water for livestock. The scheme is the property of DWAF, with Overberg
Water appointed for operation purposes according to the guidelines of
DWAF.
13.1. Geohydrology/groundwater
On route to Calitzdorp, the Committee was introduced to the term
groundwater by the officials from DWAF. The Committee was informed
that the geology of the area consists predominantly of Table Mountain
Group (TMG) sandstone/quartzite and Bokkeveld Group shale and
sandstone. These rocks are folded and faulted and are overlain by young
reddish coloured Enon Formation conglomerate.
The TMG forms the higher mountains in the area (Swartberg, Kamanassie
and Rooiberg Mountains) and the Bokkeveld Group and Ennon Formation
the lower areas and hills in the Olifants and Gamka River Valleys.
Groundwater is being abstracted from fractured rock aquifers (groundwater
transmitted through fractures in rocks, yielding usable quantities of water),
located in the TMG rocks in which highest yields and better water quality
are obtained.
Up to the beginning of 1998, 18 boreholes were used and another 15 were
used as non-pumping monitoring boreholes. The number of active
production boreholes has since been reduced to 9. Water abstracted from
the boreholes is transferred via pipeline to the two water purification works
situated in Calitzdorp and Dysselsdorp. PVC pipes are used because of the
corrosive nature of the water.At the purification works the water undergoes
the following processes:
_ Oxidation.
_ Lime addition, to reduce the iron concentration in the water and to
raise the pH of the water.
_ Chlorination.
The water then flows to the different reservoirs and distribution points.
Water flows for most of the time under the influence of gravity through the
pipe system over a total length of approximately 365 km.
The Committee was also informed about the monitoring processes in place
in terms of groundwater abstraction, groundwater chemistry, the practical
abstraction process, and how the abstraction rate is determined. In addition,
the Committee was told that the scheme currently subsidizes the water for
domestic consumption and excessive usage is discouraged. A sliding scale
tariff system for water payments is utilized to stop water wastage. As long
as a family keeps within the planned usage per household per month, the
water is very affordable. The water becomes much more expensive if more
than the planned usage is used. Water for stock watering is not subsidized,
and sold at full operating cost.
The Committee was also informed that the Little Karoo RuralWater Supply
Scheme is the largest water supply scheme in South Africa that abstracts
water from fractured rock aquifers.
13.2. Area visited by the Committee
The Committee requested that DWAF officials provide a brief explanation
of the area that the Committee will be visiting. In addition the Committee
requested that acronyms not be used when making presentations or giving
explanations to the Committee.
DWAF officials acknowledged their use of acronyms and assured the
Committee that they will try to use full sentences. The Committee was
informed that the area that they will be visiting forms part of the Klein
Karoo, where the Committee will be shown the VIP toilets that were
completed on a farm. The area is very dry with very little surface water and
for this reason groundwater is the main source of provision. The Water is
clean and disease free (potable water) as the water undergoes the normal
cleaning procedures. The water is extracted from the ground (deep ground
water) so as not to have an impact on agriculture. A policy was
implemented by DWAF and the farmers, whereby water is given to the
farmers, who in turn, deliver the water to the farm workers and livestock.
DWAF is in the process of transferring the scheme to local government, as
this is a non-core function.
There are also farm schools and local schools in the area, of which farmers
donated land to build farm schools, DWAF will supply the water and
sanitation, but the responsibility to ensure that schools gain access to water
remains with the Department of Education.
13.2.1. Questions raised by the Committee
_ What is the possibility of building dams in the area, and has any
studies been done in this area?
_ DWAF mentioned that farmers would be supplying water to farm
workers, according to a policy established, has this process been
negotiated and what progress has been made?
_ How far has DWAF come in supplying free basic services, if targets
for supply were not met what is the problems that is being
experienced?
_ Was a feasibility study done on the VIP toilets mentioned at the
presentation of the Eden Municipality?
13.2.1.1. Reponses by DWAF
_ Dams cannot be built in the area, because of the dryness of the area.
There is no surface water in the area and the area experiences very
weak rainfall.
_ Yes, the process with farmers has been negotiated, but DWAF
acknowledges that there is room for improvement.
_ Progress has been made on water supply but sanitation remains a
problem. Two pilot projects have been instituted in the Central Karoo,
but because there are two municipalities in Eden, one being the Eden
District Municipality, and the other the Local Municipality, an
agreement on operating standards have not been reached. This creates
a cross boundary scheme between the municipalities, and also causes
cross subsidization, together with other social issues, this might
impact on the community. However, the transfer of the schemes is in
process. The same agreement needs to be reached with the farmers as
well. DWAF is sure that an agreement will be reached soon.
_ A feasibility study was done before the building of the toilets.
Feasibility studies were also done in Zoar, and the results were
recommended to Government. Communities were also educated
about health issues and this was also a success.
13.3. Outeniqua Pass Groundwater Project
On route to Calitzdorp, the Committee was introduced to a possible project,
which will be undertaken by DWAF to see whether water can be drawn
from the aquafirs, in the mountains. The Committee was informed that the
mountains has a fracture drop, which extends from the Outeniqua Pass,
through Citrusdal and into Port Elizabeth and also into Cape Town. These
rock fractures in the mountains contain a vast amount of water.
The Cedarberg Mountains, which extends into Port Elizabeth, for example
contains a vast amount off hidden water. This water, according to Mike
Smart and Jannie van Staden, is not only at surface depth, but also at the
bottom of the ground. The rocks also have vast amounts of fracturing and
it is here where lots of water is stored. DWAF therefore needs to look into
this, and see if water is drawn from these mountains, how it will affect the
ecosystem.
The Committee was informed that the Cape Town Municipality is busy
doing a pilot project in Oudtshoorn, to establish if ground water is drawn to
the surface, what types of effects it will create.
13.3.1. Responses and concerns of Committee
_ The Committee asked DWAF what the relationship of the aquifer in
the Klein Karroo and other areas is to that of the aquifer in False Bay.
The Committee also believes that some problems were experienced
with the bottling companies, however, would these companies not
have completed a study already and could DWAF not inquire from
them.
_ The Committee was also concerned about the fluoride content in
groundwater, as this is a problem in Limpopo, where groundwater has
a high fluoride content which affects the children and especially
elderly people who because of this suffer from arthritis.
13.3.1.1. Responses by DWAF
The groundwater in the Western Cape does not experience high intensities
of fluoride. However, DWAF is aware of the high intensities of fluoride and
iron in groundwater, however, concrete solutions to these problems have
not as yet been achieved.DWAF is however sure those possibilities do exist
to cure these problems.
Because of ground water reticulation, the interpretations of studies are
based on geology. It is always difficult to do studies underground, and
therefore interpretations of studies are accumulated from surface observations
and through this attempts are made to interpret what is happening
underground.
The Committee was informed that the CSIR had set up networks to monitor
procedures. It is estimated that ground water lies approximately 5
kilometers below the earth’s surface. The Oudtshoorn Municipality will
therefore use the pilot project as a study to see if water can be drawn from
the ground, what effects it has on surface water, as surface water are used
extensively for agricultural purposes. Therefore monitoring systems will
have to be put into place to monitor the project.
14. Farm Dweller Sanitation at Calitzdorp
14.1. The Committee was interested to know how the community
was involved in the processing of the VIP toilets, especially,
their role in the decision making process.
DWAF officials informed the Committee that a meeting was first held with
the local farmers ward where the idea was relayed to them. A meeting was
then called between the farmers and farm workers and a liaison committee
was formed, and the implementation of the project was agreed upon.
The farmers would identify the houses on the farms where the VIP toilets
were to be set up.An environmentalist was called in to do an environmental
impact assessment. Thereafter, it was advertised for tenders and local
contractors to put up the units (VIP’s). The local community is being used
to set up these VIP’s and this creates employment. The units cost
approximately R55.00 per unit.
Holes are dug on the farms, and if the hole is okay, these holes are filled
with bags and rocks and the units are placed on these holes. On completion,
the community are given training around health issues, by a peer training
educator who is identified by the farmer, who in turn uses those that has
been trained to train others as well, and then plays the role of
co-coordinator and monitor.
The project at Zoar however, is incomplete, with some communities having
access to drinking water via communal taps while others do not have.
Communities in Zoar are still using the bucket system as no VIP toilets
have been placed there as yet.
14.1.1. Challenges identified by DWAF officials include:
_ The involvement of women in the projects.
_ The possibility of Government transferring maybe R1800 to farmers
directly to allow the farmer to give the farming communities flush
toilets.
14.1.2. Concerns and responses of the Committee
The Committee was concerned that getting women involved in processes
still remains an issue. Is there enough being done to get women involved,
or is nothing just being done at all? The notion of wanting to transfer
monies to farmers remains an issue. Can farmers be allowed to control
Government finances? The Committee also finds it strange that the farmer
can find ways and means to provide his household with flush toilets and
inside taps, but finds it difficult to provide this to his workers.
DWAF is saying that the land around is barren and that there is not enough
water. Does this mean that there is not enough water for everybody, or for
only a selected few? The Committee finds it strange that water cannot be
provided for sanitation, but somehow, there is water to feed into the
communal taps.
The Committee feels that water is a national resource and this allows
everybody equal access to water. The water should not be considered as
being for farmers use alone.
14.2. Community Project: Gamka Wes — Calitzdorp
The Committee was taken to a farm and shown a sanitation project that has
been completed by DWAF officials. The VIP toilets are situated on the
outside of the house, with a latrine (toilet pot), on the inside, attached to a
hole at the bottom. The toilet has open spaces at the top that allows for
ventilation.
The communal taps are also situated outside the house, with one communal
tap per household. The Committee was informed that the Overberg Water
Board operates the scheme, which is subsidized by DWAF. This however,
will change once these schemes are transferred to the municipalities. It is
envisaged that the end users will then pay for the water that they use.
Present on the farm was some of the farming community who lived in
adjacent houses where the Committee was shown the pilot project. This
created an opportunity for the Committee to pose questions to the
community.
14.2.1. Questions posed by the Committee to the community included:
_ Whether they were happy with the VIP toilets?
_ Are they happy with both the communal taps and VIP toilets?
004
_ Did they participate in the decision-making processes?
_ How many families use these facilities and do all homes have the
facilities?
14.2.1.2. Responses of the Community
The responses of the communities present varied significantly, however the
Committee was informed that there are approximately 12 families living on
each farm. Some houses have 4 people per family, where in others one
could find close to 8 people living in a house.
Although the community is happy that they are provided with water, the
problem is that the taps are outside the house, and when it rains they have
to go out to fetch water. Sometimes it rains so hard that they are drenched
when fetching water and are exposed to illnesses such as flu.
The toilets are also problematic in the sense that it is situated outside the
house and they have to move from inside to the outside to use the toilet. At
night, this is a problem because it is dark, and there is no lighting on the
farm and people have to grope around in the dark to reach the toilet. The tap
is also far from the toilet and they just have to ignore washing their hands
and this is also unhealthy, especially for their children. One gentlemen
informed the Committee that he is very unhappy that his wife must be
exposed to such conditions, but this takes away her dignity, where he at
times feels so bad that he walks into the field to go and relieve himself.
The Committee also found out that one of the houses on the farm has a flush
toilet. This house the Committee was informed belongs to the foreman of
the farm. The Committee was informed that the foreman’s mother used to
work for the previous owner of the farm as a domestic and he had the toilet
installed for her. The Committee was informed by the community that there
is pipelines hat supplies water running past the farms from the Overberg
Mountains, but the farmer does not want to have extensions from his farm
to the pipeline fitted to supply water to the farm. The farmer is happy
drawing water from the borehole to supply the farm-workers with water.
The Community felt threatened when the farmer arrived at the farm and
informed the Committee that they could not speak to the Committee with
the farmer present, as they would be victimized by the farmer once the
Committee had left. The Chairperson assured the workers that they have
the full support of the Committee if they are victimized by the farmer and
should not hesitate to contact the Committee if they were victimized. A
contact number was forwarded to one of the community members present.
15. Departure to Heidelberg
The Committee departed for Heidelberg with one of the objectives being to
capture the conditions of the people living in Zoar, who currently still use,
the bucket system. The other objective was to be informed by the Overberg
Water Board, on the progress made in terms of free basic water and
sanitation to the people. However, with limited time in hand, and the long
bus trip to Heidelberg, the Committee decided not to stop at Zoar, but to
proceed directly to Heidelberg.
On route to Heidelberg, Zoar was shown to the Committee by DWAF
officials. DWAF officials reminded the Committee that Zoar, still has no
proper sanitation in place and still uses the bucket system. Zoar is home to
about 450 people who are mostly unemployed. The Committee was also
shown a town called Amalienstein and was informed that most of the town
had RDP houses with potable water and sanitation.
15.1. Concerns and Questions raised by the Committee
The Committee was interested to know why Zoar is still using the bucket
system, and what is being done to change this. In addition, DWAF
mentioned that most of the people are unemployed. The Committee wanted
to know whether no community projects was conducted in Zoar because
this could in some way help people to earn a living. The Committee was
also concerned about the health of the people of Zoar, because without
proper water and sanitation people and especially children remain
vulnerable to diseases.
15.1.2. Responses by DWAF
DWAF officials informed the Committee that one of the reasons for Zoar
not having proper water infrastructure was due to a flood which occurred in
January 2004 most of the pipeline which supplies water to Zoar was
washed away. A recurring flood in March 2004 washed away another part
of the pipeline. The Municipality installed a temporary plastic pipeline to
supply water to Zoar. DWAF officials informed the Committee that
approximately R13 million is needed to eradicate the bucket system in
Zoar. The Committee was also informed that the Kanaland Municipality
has no funds to install proper sanitation facilities.
DWAF officials also informed the Committee that at present there are basic
health care services in Zoar. There is also a primary health care facility for
the people of Zoar. The town also has two people working on home-based
care services. People are given voluntary counseling about the Aids
pandemic, and mother to child transmission services are also done.
15.2. Heidelberg: Overberg Water Board
The Committee met a delegation of the Overberg Water Board in
Heidelberg who informed the Committee through their presentation of the
current issues at the institution.
The Overberg Water Board is the only Water Board in the Western Cape.
Although the OverbergWater Board cannot be compared to the RandWater
Board, it is equally important in terms of service delivery.
The Overberg Water Board is proud of its transformation achievements in
terms of equity, with the Board as well as its staff. The Board is also proud
of its transformation processes and has fared well over the past years. It has
a proud record in terms of skills development and staff capabilities ad is
proud of the results of its restructuring. The Board has a bad legacy in terms
of its financial position, where in the past the Board was lying close to
bankruptcy, but this has changed significantly over the past years and the
Board now has a positive financial position.
15.2.1. The Future role of the Overberg Water Board
The Overberg Water Board is a market leader of its sector in the region. It
has the basic systems and structures in place (management and other
structures) for water services delivery that has the potential to expand. The
Overberg Water Board leads discussions in institutional reform i.e. future
transformation, efficient and effective delivery of quality water services.
The Overberg Water Board has a purification plant and it is the first
purification plant in the Overberg region, however, it needs upgrading. The
Overberg Water Board is the leader in the whole of the Western Cape
regarding delivery in the Working for Water Programme (WFW).
2004
The Overberg Water Board foresees itself in a significant role as service
provider fro Catchment Management Agencies (CMA’s), including
amongst others, the management of rivers, dams and other resources. It also
sees itself as and important provider of services to DWAF.
15.2.2. The nature of the Schemes of Overberg Water
_ Provides water for human consumption and stock watering. This,
according to Overberg is unique in the whole country.
_ It provides water to the most important economic sector in its region,
SA Molsters (SAM), who exports ostrich meat, etc.
_ The schemes are by nature designed by DWAF and are expensive
schemes to operate. It has a legacy of financial difficulties, and
receives no financial provision or support. Overberg however, is in the
process of overcoming this predicament.
_ Overberg Water supports the curtailment of water provision and is
positive that with partnerships it is possible to achieve goals through
tighter management.
Overberg still plans to grow. It has an imaginative management team, and
good development of secondary activities.
15.2.2.1. Challenges
_ Overberg Water is not subsidized by DWAF.
_ It has an interest free loan of approximately R35 million.
_ A town called Genadendal in the region still has the bucket sanitation
system in place with very little untreated water that usually runs dry in
the summer.
_ OverbergWater is in the process of working on a proposal to have the
loan written off in particular for the benefit of Genadendal, and also
for the region in general.
15.2.2.2. Questions and concerns raised by the Committee
The Committee acknowledges the achievements that Overberg has raised
to the Committee, however, the Committee is concerned that the present
representation of the Overberg officials shows the Committee that they are
not gender sensitive, as there seems to be no women present in the
delegation as outlined. This raises cause for concern, as Overberg stated
that it is proud of its transformation. The Committee needs to know why
Overberg has a debt of R35 million and what mechanisms are in place to
overcome the debt.
In addition, the Committee would also like to know from Overberg, what is
the progress in terms of the free basic service delivery policy? The
Committee also wants to know if there is any other areas that has the bucket
system in place? The Committee also needs to know whether farmers in the
region buy quotas, and whether they pay tariffs during the dry season? The
Committee needs to know how the water is allocated for agricultural
purposes and domestic use?
The Committee informed Overberg that theWorking forWater Project was
initiated in Genadendal some time ago, and the Committee would like to
know what happened to the project.
15.2.2.3. Responses by Overberg
The top management structures of Overberg consist of 7 councilors of
which 1 is female and 6 male. Overberg officials present informed the
Committee that they are unclear as to the gender representiveness of the
Institution and could not inform give the Committee the true reflection of
the situation at present.
Overberg Officials informed the Committee that in the past there were not
enough reserves (finances) to allocate to the upgrading of the Overberg
region. Ten years ago the scheme that is now in place was a Government
scheme and made no provision for reserves. Overberg has tried to turn this
around through tariffs. Ten years ago, the schemes cost Overberg
approximately R70 million when handed over to theWater Board. The then
Water Board negotiated a take over price of approximately R40 million,
and over the last ten years Overberg has slowly attempted to pay off this
debt. Overberg will submit an application to DWAF and to the Treasury to
write off this debt, and then lend Overberg the money again, to use to the
advantage of Gendendal to eradicate the bucket system.
Overberg officials informed the Committee that the municipality makes
arrangements for free basic service delivery. It is not the duty of Overberg
to ensure that the people have free basic services. Theewaterskloof
municipality ensures free basic service delivery to every household within
its jurisdiction. Free basic service provision does not apply to service
providers but to water associations. In terms of other area’s in the region
that is using the bucket system, Overberg was not sure, but indicated that
there could be.
Overberg informed the Committee that farmers do not buy quotas for water
but applies for their water. Overberg then manages the allocation of water
by keeping the water at a constant level through hydraulic pressure. Tariff
structures are based on how efficient farmers use the water.
On theWorking forWater Project in Genadendal, Overberg firstly wishes to
inform the Committee that Overberg is the best service provider for the
Working for Water Programme, however, the WFW project stopped in
Genadendal due to unforeseen circumstances. In terms of water provision,
the Committee was informed that 60% of the water is allocated to farmers,
20% for domestic use, and the other percentages are allocated to SAM and
stock farming.
16. Arabella Water Recycling
The objective of the Committees visit to the Arabella Golf Estate was to be
informed through a presentation of the water recycling systems in place at
the estate.
Representatives of the Arabella Country Estate informed the Committee
that the Estate was built in 1995, on an old piece of farmland in Kleinmond,
with a water sewerage works, water treatment works and a golf estate. The
Arabella Estate is part of the Shukuba Group of Companies and invests
approximately R1 million per year in the country.
The estate alone creates about 250 jobs for people from the immediate
surroundings.With the construction of houses from a new development, the
Arabella has created approximately 1000 jobs also for people and builders
from the surrounding communities.
The Committee was informed that the Arabella has a sustainable
development plan. It attracts healthy tourism throughout the year, although
it attracts more tourists at during the summer holidays. It is the only golf
course, which is self-sustainable, with its own water supply, and the
Arabella has good quality water. The Arabella is famous for hosting the
Nelson Mandela Trophy (golf tournament).
The Arabella receives its water from the Hermanus River, which constantly
dries up during summer. Water is therefore mostly extracted during winter
via a pipeline, which runs directly from the river. The Arabella also makes
use of boreholes and surface storage water which is treated at the Estate’s
own water reservoir. Water is continuously recycled and treated at the
Estate’s water treatment works and therefore water is not wasted at the
Arabella.
Boreholes are continuously monitored through data reading, which is very
important. The Arabella also makes use of groundwater, which is extracted
from fractures between the rocks in the surrounding mountains. An
immense amount of iron is found in the water; therefore the Arabella relies
on its water treatment works where the water that is extracted is treated.
Ground water has the following positives:
_ It is close to the needs of the people.
_ It is close to the earth’s surface.
_ The smaller community can be easily facilitated (water supply).
_ It is easy to maintain.
The Committee was informed that the Arabella pours back into the
community through:
_ Creating opportunities for academics.
_ School projects, where matriculants are prepared/trained to become
chefs.
_ The Estate is part of the Overberg Development Plan.
_ It creates employment for the surrounding communities.
_ It also has other activities in schools.
_ It adds to the individual upliftment of skills.
_ It creates approximately 400 jobs.
_ It is busy with a housing construction and has created approximately
1000 job opportunities especially for builders from the surrounding
communities.
Representatives of Arabella informed the Committee that they are in the
process of constructing a new borehole in the surrounding mountains which
is done through aquifers, where fractures are identified in the mountain
rocks, and in these fractures, drilling takes place and boreholes are created
here water will be extracted to supply the Estate. Representatives of the
Arabella informed the Committee through presentation about the logistics
of the whole process.
Because the Committee arrived at the Arabella Estate very late in the
evening, from Helderberg, the Committee felt that they had been through a
tough day, and that they would appreciate it if the representative of the
Estate could visit Parliament to give the Committee an informed
presentation of the envisaged water supply area that the Arabella wishes to
create in the mountain area. The Committee will extend an invitation to the
Arabella, when the Committee arrives back at Parliament in Cape Town.
17. Day 4: Theewaterskloof Dam visit
The objective of the visit by the Committee to the Dam, firstly, was to
observe the low levels of water that the dam contains at present. Secondly,
the objective was to be informed about how the dam functions in its supply
and demand areas.
The Theewaterskloof Dam is the largest storage dam of the Western Cape
Water System. It is filled by runoff from its own catchments and by the
diversions during the winter months of the Wolwekloof and Banhoek
Rivers into the Riviersonderend-Berg River Tunnel System. In future it will
also receive water pumped during the winter months from the proposed
Berg River Dam at Skuifram.
The main irrigation demands from Theewaterskloof Dam comprises the
following:
_ Direct abstractions from the dam by riparian irrigators and releases
into the Riviersonderend River for downstream irrigators and
Overberg Water.
_ Releases via the Riviersonderend-Berg Tunnel System to irrigators in
the catchments of the Berg and Eerste Rivers for the City of Cape
Town.
17.1. Overview of the Theewaterskloof Dam
On arrival at the Theewaterskloof Dam, DWAF the Committee was
informed that the dam holds approximately 4,8 million cubic metres of
water. The Committee was shown the level of the dam currently, and what
the dam level should be if the dam is completely filled with water. At the
time of the visit the dam was approximately one third of its normal
capacity. This according to DWAF officials was a major concern, as dams
at such levels causes problems when needing to supply the greater Cape
Town community with water. If the dam and surrounding dams do not fill
up due to the shortage of rains at present,DWAF and the City of Cape Town
Would have no other alternative but to apply water restriction measures.
The Committee was also shown the reddish colour of the water in the dam,
and was informed that because of the colour of the water, which represents
the colour of rooi-bos tea, the dam was named Theewaterskloof Dam.
The Committee was taken to the dam’s main pumping station and
introduced to the logistics of the pumping station by an official from
DWAF.
17.1.2. Questions raised by the Committee
_ Because of the present conditions of the dams in the Western Cape,
and its water shortages due to a lack of rain, the Committee wishes to
know how the City is informed about the conditions of the Dams.
_ What mechanisms are in place for water distribution, for example how
are the water services to farmers and communities monitored and
controlled.
_ How is the water distributed to the farmers and to the wider
community?
17.1.3. Responses by DWAF
_ The officials informed the Committee that the City is part of the
Provincial Flood Management team, and they together link up around
issues of flooding, droughts etc. They have a good information sharing
system, and also links up with the weather bureau. They also have
emergency preparatory plans in place, which provides them with
indicators about the weather conditions and patterns. They can for
example warn farmers that live downstream of the rivers that there
will be chances of flooding occurring in the region. They also have
technical warning systems in place, which is of a high standard.
_ The Committee was informed that the Irrigation Board monitors all
individual water use; water monitoring is the responsibility of the
Water Board and farmer’s answer to the Board on how they use their
water. DWAF plays an oversight and monitoring role. The Irrigation
Board implements the procedures for water usage by farmers who
apply for water through quotas. Farmers are then monitored in terms
of how they use water through the quotas. DWAF bills the Irrigation
Board, who in turn bills the farmers.
_ Most water in the dam is used by farmers (no specific percentage), and
the other percentage goes towards domestic use. Farmers apply for a
licence to able to get water and have to predetermine how much water
they will need. For domestic use the same procedures for getting
water applies, however, in terms of water needs priority is given to
domestic use. For example, if farmers need more water and they have
used their total water in terms of their quota’s and water restrictions
are applied, they will have to get/buy water from someone else, as first
priority will be given to domestic use first. This is in terms of the
Water Act that states, the needs of the consumers comes before
irrigation needs. Farmers can, however, when applying for a new
licence obtain water again.
17.2. Franschoek Trans Caledon Tunnel Authority (TCTA)
The objective of the Committees visit was to be informed firstly about the
progress made in terms of the construction of the Berg River Dam.
Secondly, to observe theWorking forWater Programme, and determine its
achievements thus far.
17.2.1. Berg Water Project
The Department ofWater Affairs & Forestry (DWAF) has been involved in
a 14-year process that led to the decision to implement the Berg Water
Project (BWP). It started with theWestern Cape Systems Analysis (WCSA)
in 1989, to determine the future needs and water resources available in the
region, and was subjected to a rigorous public-participation process and
debate, after which a Record of Decision (ROD) was issued in 1999 by the
Department of Environmental Affairs and Tourism (DEAT).
In December 2001, the Minister was satisfied that appropriate progress
regarding water demand management had been made by the City of Cape
Town (CCT), and in April 2002, the Cabinet approved the implementation
of the BWP. On 6 May 2002, the Minister of Water Affairs & Forestry
directed TCTA in terms of section 103(2) of the NationalWater Act, 1998,
to fund and implement the BWP as the agent for DWAF.
The BWP is designed to overcome the impending water shortage in the
CCT and for agricultural water usage supplied from the Riviersonderend-
Berg River Government Water Scheme. It is the first bulk water resource
development project that is directly linked to water demand management.
The existing components of the Western Cape Water System (WCWS),
including the addition of the Berg River Dam (BRD), are depicted in the
diagram below. The BWP will increase the yield of the WCWS by 81
million cubic metres or 18% to 523 million cubic metres a year by 2007.
This project is an important benchmark of TCTA’s success. The full
responsibility for implementation and funding rests with TCTAand, unlike
LHWP, this project will be funded without Government guarantees. The
groundbreaking agreements between TCTA and DWAF, and DWAF and
the City of Cape Town (CCT) were signed on 15 April 2003. The two
agreements were:
_ An Implementation Agreement between DWAF and TCTA.
_ A Raw Water Supply Agreement between DWAF and CCT.
These are the first public-public agreements of their kind in South Africa
that guarantee service delivery between public entities. The agreements
provide a sound basis to obtain a favourable credit rating for the project and
offer a model to other similar projects in Africa.
The design and supervision consultants were appointed in December 2002.
An agreement was reached with the consultants and DWAF whereby
DWAF staff could be seconded to the consultants with the aim of
transferring commercial skills and capacity. Although this arrangement was
not fully exploited due to changes in DWAF staffing, it provided a sound
basis for future capacity building on similar projects. Since the review and
approval of the appropriate dam type, TCTA has completed the design of
advanced infrastructure development, compiled a shortlist of pre-qualified
construction contractors for the Berg River Dam (BRD) and issued tender
documents to them. The tender-evaluation process is under way. The award
of the BRD construction contract should be completed by the end of May
2004. Construction should start by June 2004. The construction of the
advanced infrastructure will also be completed during this year.
Adecision on the timing of implementation of the Supplement Scheme will
be taken during the next financial year. Further investigation is required on
the impact it may have on the salinity and water quality in the Berg River.
Examination of the extent of the original environmental approval issued in
1999 indicated that additional Environmental Impact Assessments (EIAs)
were required for the advanced infrastructure components such as housing
and access roads.
The DWAF Construction Unit was appointed to implement the advanced
infrastructure construction and mobilised in January 2004. The participation
of DWAF was agreed at Board level and flows from the directive
issued by the Minister to utilise DWAF technical resources. It also allowed
TCTA to make up time lost in obtaining the additional environmental
approvals mentioned above. Both the financial value and additional risks,
by not transferring risks to the contractor, are within an acceptable limit.
The process of preparation, approval and inception of an integrated
Environmental Management Plan (EMP) was the focus of
socioenvironmental activities during the year under review. Following the
July 2003 endorsement of the EMP by the Environmental Monitoring
Committee (EMC) — a representative forum of interested and affected
parties — the Department of Environmental Affairs and Tourism (DEAT)
gave its approval in October 2003. This facilitated the start of the
construction of project.
The EMC brought the issue of individual liability to the fore and this led to
the re-naming of the committee (from ‘management’ to ‘monitoring’),
while the entire liability issue has been taken up by Government. The
decision will affect the role of all similar bodies on future projects. An
independent EMC secretariat that will operate in a self-regulatory
framework has been established in the La Motte Village near Franschhoek.
It will include the Environmental Control Officer (ECO) who reports to the
EMC? The ECO will monitor compliance policies and procedures.
TCTAapproached development-financing institutions to provide long-term
funding for the project. Following various reviews (technical, environmental,
financial, governance, etc) the funding was approved subject to a
guarantee. The development-funding agency believes that the project could
provide an example and break new ground in the way it is implemented.
Going forward, TCTA will address:
_ Impact-mitigation strategies in both the natural and social environment.
_ Finalisation of the Working for Water contract with DWAF to clear
alien vegetation in the previous Assegaaibos State Forest, which
includes the future dam basin.
_ Finalisation of the tri-partite agreement between TCTA, Stellenbosch
Municipality and the community of La Motte regarding the transfer of
ownership of project housing to local government on completion of
the project. The financial benefit derived from the sale of the
properties will be shared with the other communities in the greater
Franschhoek Valley.
_ Continued rollout of the public-participation strategy to ensure
appropriate involvement of all communities from source to sea along
the Berg River.
_ Development of a Sustainable Utilisation Plan (SUP) for the BWP.
The Committee was taken to the offices of TCTA, where they were
introduced to the project through a model, which was displayed in the office
of the TCTA. The Committee was shown the development around the
various catchment areas, which would supply the dam for example, the
Assegaai Bos Dam, which is situated in between the mountain and was
never developed. This is a very large water catchment area.
The Committee was also shown control point areas, which will be used, and
these are, Klein Plaas Dam, with in-points in Wolwekloof and Waanhoek.
17.2.2. Questions raised by the Committee
The Committee requested TCTA to provide an explanation as to the
situation of small emerging farmers. In addition, the Committee wished to
know how many small emerging farmers is being served, or will be served
on the completion of the project?
17.2.2.1. Responses by TCTA
The Committee was informed that not enough small emerging farmers are
being served. However, there are some projects underway to include small
emerging farmers.
The Committee left the offices of the TCTA, for a site visit of the Berg River
Project, however, because of the rain, the Committee could not enter the
site. The Committee was shown the Berg River project on route to a site
visit on the Working for Water Project.
18. The Working forWater Programme
The Committee was informed that then Minister For Water Affairs and
Forestry, Minister Kader Asmal, initiated the Programme in October 1995
with a grant of R25 million from the RDP fund. The programme would
protect the water resource of the country from the rapid spread of invasive
alien vegetation, with the added social benefit of employing the poorest of
the poor to do the work through mainly manual labour. The programme has
since grown to the most successful poverty alleviation programme of the
Government and has won several awards including some international
conservation awards.
18.1. The Assegaaibos Working forWater Project
The Committee was informed that the upper reaches of the Berg River has
always been a very important source of water for primary use in the Cape
Peninsula and also for irrigation in the very fertile Berg River Valley, well
known for some of the world’s best wines. Over and above the water benefit
the upper catchment area is also a very important bio-diversity hotspot.
All these factors contributed to the start of the Assegaaibos Working for
Water Project in 2000. Most of the State owned land in this catchment was
used by the then SAFCOL forestry. A partnership between DWAF and
SAFCOL started the project with 8 contractors and approximately 96
workers.
The project has since spent more than R4 million in the catchment clearing
and following — up more than 4000 hectares. Of the money spent more
than 60% was spent on the workers.
In 2004 the project took a historic turn when TCTA with the support of the
City of Cape Town, agreed to contribute R21 million to the project in the
next eight years in an effort to control the spread of invading alien plants in
the catchment. This means that the project will now have an annual budget
of more than R5 million per year, employing more than 200 people. The
project staff consists of 2 project managers, a quality controller and an
administrator.
The Working for Water Programme forms part of Governments extended
PublicWorks Programme and exit contractors and workers after a two-year
employment period and the required training of 48 days. This is to support
the development of independent contractors/entrepreneurs who can compete
for work in the open market. Training includes:
_ Functional training.
_ Health and safety.
_ First aid.
_ Chainsaw operating.
_ Herbicide and life-skills training.
_ Business development.
_ Substance abuse awareness.
_ HIV/AIDS and primary health care.
The Committee was also informed that work in the Assegaaibos project is
extremely difficult due to steep slopes, mountains and the heritage of a
forestry plantation. This is coupled to environmental conditions of extreme
heat and cold. This requires special teams who can camp out in the
mountains; abseil the rock faces and conquer the elements to eradicate the
invasive alien plant species. All clearing in the area is done on a contract
basis. Teams obtain a clearing contact and get paid when the area is cleared
to the required standard. The programme also ensures that workers are
protected by the highest standard of health and safety.
The Committee was also shown on site training which people of the
community was receiving for the housing complex that would be built as
part of the development of the Dam.Workers were given in the site training
in bricklaying, plastering and construction of the types of houses that would
be developed in the area.
The Committee also had the chance to speak to workers who was employed
in the Working for Water Programme.
18.1.2. Questions asked by the Committee of the workers
The overall questions from the Committee was the happiness of employment
of the workers, whether they were happy with the types of skills
training they were receiving, whether they were happy that the project is
successful.
18.1.2.1. Responses by the Workers
The overall feeling of workers was that they were happy with the work that
they were doing, with the skills training that they were receiving. The only
concern was that as the Committee could see it was raining outside and that
in such conditions it was very dangerous to work out in the mountains.
18.1.3. Concerns of the Committee raised with TCTA
The Committee was concerned that once the houses have been built, then
these people would again be unemployed. How will they be able to prove
to other employees when seeking employment that they were trained in
building skills, because most of these people were uneducated and had no
school records.
18.1.3.1. Responses by TCTA
The Committee was informed that they are registered with the Sector
Education Training Authority (SETA), and they are given a number of their
file held by SETA, whereby they can when seeking employment obtain the
required information from SETA to prove to employers that they were
trained and had worked on the project.
19. Boland District Council-Stellenbosch
The objective of the visit to Stellenbosch, was to gather information on the
progress made by the municipality in delivering water and sanitation to the
people of Boland.
The Committee arrived in Stellenbosch, where the Committee met with the
Acting Mayor and some of his officials. The Mayor started his presentation
to the Committee by informing the Committee that the building of the Dam
was done without the participation of the Communities of Boland.
The Mayor informed the Committee that the community of the Boland is
upset about the building of the Dam as they feel that they are sidelined in
terms of employment and participation in decision-making processes. The
poor and marginalized are sidelined and the Mayor feels that he needs to
bring this to the attention of the Committee as it is the duty of the District
to seek help for the people, as it would benefit the community if they could
understand what is happening around them.
The Committee intervened in the issues that the Mayor was raising and
informed the Mayor that together with TCTA (convene a meeting), they
should thrash out the problems that they are experiencing. The Committee
informed the Mayor that they are not visiting to solve this types of problems
but that the Committee is here to be informed about the progress made to
deliver to the people the provision of basic water and sanitation. The
Committee would also like to know what progress has been made to
eradicate the use of the bucket system if they are still in use in the Boland.
The Committee would also like to know what has been achieved to supply
these services to the people.
19.1. The Committee was informed on the conditions in Boland as
follows:
In the former ‘‘towns’’ within the Boland, only Drakenstein and
Stellenbosch Municipalities reported to have any buckets still in use. In the
case of Drakenstein it was reported that 50 buckets were still in use in Saron
and 130 in Wellington. Funds are available and these buckets will be
eradicated within this financial year.
In the case of the Stellenbosch Municipality, buckets are still used in
Kylemore and Jamestown. Uncertainty does exist over funds allocated by
DWAF for the eradication of the bucket system as DWAF funds are now
included within the MIG allocations. If these funds are confirmed, all
buckets in use will be eradicated within this financial year. This is in
contrast to the figures of the 2001 Census and it is therefore assumed that
the bucket systems still operational during 2001 have all been eradicated.
Municipalities in general do not supply water and sanitation services in the
rural areas and the supply thereof is still a debatable issue on private land,
especially on farmland. All municipalities within the area have implemented
a policy for the provision of free basic water and sanitation in their
respective urban areas.
The Boland District municipality, in an effort to improve the provision of
water and sanitation in the rural areas, approved the following policy
during 2002. An amount of R 3 000 000 p/a has been spent by the Council
on the implementation of the policy while this amount can be multiplied by
at least two to get the annual amount spent (farm owners and Council) on
improving water supply and sanitation in the rural areas.
20. Day 5: Khayelitsha: Presentation and site visit with the City of
Cape Town
The objective of the Committee was to be informed by officials from the
City of Cape Town about its pressure reduction project and to evaluate the
pilot sanitation (VIP) project which in underway in the informal settlements
of Khayelitsha.
The Committee was taken to the pressure reduction pump station in
Khayelitsha, where the Committee was informed that the purpose of
introducing the pressure reduction system in Khayelitsha was because of
the high rate of water leaks that the area is experiencing. The Committee
was taken to the pressure pump and told that during the evenings and at
night, the pump is used to release the water flow in the pipelines that
supplies water to the area.
Water leaks has always been a problem in Khayelitsha, with lots of water
being wasted. This project has thus far proved to be successful in the sense
that when the pressure in the pipelines is released, the water flow slows
down, and prevents continuous water leaks.
20.1. Questions raised by the Committee
_ The Committee asked of the City of Cape Town to inform them how
the project is monitored to be able to detect whether the project is
successful?
_ The Committee inquired as to whether the City of Cape Town had
informed the people prior to the implementation of the project, and if
they did what were the responses of the people?
_ The Committee inquired if all the people in Khayelitsha, has been
served by this project, and if not by when will the project reach the
other people?
_ The Committee inquired about the situation of sanitation in the area,
and whether people have been given the basic sanitation requirements.
The Committee also asked the City of Cape Town to inform
them of the problems that are being experienced in terms of the
implementation of the basic services of water and sanitation?
_ The Committee inquired from the City of Cape Town as to how they
balance the supply of water to Khayelitsha and the adjacent Mitchells
Plain area?
_ The Committee inquired from the City if they were aware that
children are crossing the Lansdowne road to get water from the other
site on the opposite side of the road, which is very dangerous, and
children have been involved in accidents. The Committee informed
the City that this had been televised as well. The Committee would
like to know why this is happening?
_ The Committee wished to know how many of the bucket systems are
still in use in Khayelitsha?
_ The Committee inquired as to how the buckets are disposed of once
they are used, and what methods are in place to dispose of these
buckets?
20.1.2. Responses by the City of Cape Town
_ The City of Cape Town informed the Committee that the project is 2
years old, and that there are 25 000 water meters in the whole of the
area. Readings are taken each month and from the readings it is
determined how much water has been used. The Committee was
informed that at the beginning, 2 500 kilolitres of water were used per
hour, this then dropped to 1 500 kilolitres per hour, a saving of 1000
kilolitres of water on average. The challenge according to the City of
Cape Town is to make people aware of water saving methods.
_ The Committee was informed that with the implementation of the
project people were informed and made aware of the issues.
Therefore, feedback from the people is successful, and the
sustainability of the project has also proved to be successful.
_ The Committee was informed that a high amount of people has not
been served as yet. However, with the installation of the meters,
people will also start to be billed for the water that they use.
Previously, 2 households would use one water meter, and this created
problems in the billing system. However, the City of Cape Town is
sure that most of the people will served in the near future, and the
billing system will also be implemented within 3 years.
_ The City of Cape Town informed the Committee that not all the areas
in Khayelitsha have been provided with sanitation. However, 40 000
sites in Khayelitsha have been served with a tap and a toilet. Thus far,
installation on these sites have costed approximately R3 million.
There is also the problem of double occupation, in towns like Mxolisi
Phetani, Bongani, Victoria Mxenge, Graceland and Mandela Park. In
these areas, more than one family/household uses the communal tap
and toilet. In addition, the City of Cape Town informed the Committee
that some informal settlements are built on private land, and the City
of Cape Town has to obtain permission from the landowners if they
want to provide the land with the water and sanitation infrastructure.
This is problematic as the landowners are not easily available, or they
do not respond to the City at all.
_ The City of Cape Town informed the Committee that Mitchells Plain
and Khayelitsha use the same water supply (pipelines), and no
problems are experienced through the system. The Committee was
also informed that in Khayelitsha, most of the sites use the bucket
system, which means that lesser water are being used, and also
communal taps are used in Khayelitsha.
_ The City informed the Committee that the land that these children are
staying on is intersite (private) land, which is situated close to the
railway line. This land has not been serviced, and these children have
to cross the road to get water from the serviced site on the other side
of the road. The City is in the process of acquiring land in Mfuleni,
and would then service the land and propose to move the people to this
area. This is always a problem, as people are not prepared to just move
from the place where they are staying. The City has asked to purchase
this piece of land, but is still waiting for a response. The City of Cape
Town also informed the Committee that the upgrading of land started
in July 2004. R140 million (capital and operating expenses) was set
aside for the project. Initially, the project will take 5 years, with a
review period of 3 years. It is envisaged that R600 million for
expenditure will eventually be set aside for upgrading purposes.
_ The City informed the Committee that 95% of the informal
settlements have been served with the VIP systems and communal
taps. It will take the City approximately 3 years to eradicate the bucket
system completely.
_ The Committee was informed that the disposal from the buckets is
transported to the purification plant at Sandvliet Waste Water
Treatment Works. The buckets are cleaned twice a week.
20.2. Khayelitsha site visit: VIP pilot project
The Committee was taken on a site visit. The objective was to observe a
completed VIP toilet, which was installed as a pilot project at one of the
informal houses in Khayelitsha.
The Committee was shown the completed pilot project (VIP toilet), at one
of the informal houses in Khayelitsha. Because informal houses in informal
settlements are built quite close to each other, the toilet was situated
between quite a few of the informal houses. The Committee also observed
piles of solid waste lying around the informal houses, and on the pavement
along the road.
20.2.1. Questions raised by the Committee
_ The Committee was interested to know how the Community is
involved in the building of the VIP toilets, and especially in the
decision making process. The Committee also wished to know to what
extent the youth is involved, and how the implementation of these
toilets is monitored?
_ The Committee was interested to hear from the City of Cape Town, for
what informal house the toilet was actually constructed?
_ The Committee inquired from the City of Cape Town, why the solid
waste was lying on the pavement, and when the municipalities remove
solid waste.
20.2.1.1. Responses by the City of Cape Town
_ The City of Cape Town informed the Committee that the community
had an established forum, with two representatives from each ward
serving on the forum. The forum acts as a task team, and monitors the
provision of services in the whole of Khayelitsha. Representation on
the forum also includes youth and is highly represented by women.
The youth is also involved with the rollout and construction of the VIP
toilets.
_ The City of Cape Town informed the Committee that the toilet was
constructed for the house, which was closest to the toilet. However, it
was brought to the Committees attention that the people living around
the constructed toilet was all using the same toilet, and believed that
the toilet belonged to all of them and not only to the one informal
house.
_ The City of Cape Town informed the Committee that solid waste is
removed twice per week.
Upon questioning some of the community who gathered close by, the
Committee was informed that the rubbish has been lying there for quite
some time. According to the community the rubbish is not always collected
twice a week, and some times lies around for a long time. With the rains
over the week, the rubbish spreads everywhere, and causes problems in
terms of health, and blocked drains.
The Committee departed to the Faure Water Treatment Plant, with the
objective of listening to a speech delivered by Mr. Saleem Mowzer, and
also a presentation by the City of Cape Town. The Committee however felt
that it was late in the afternoon, and recommended that Mr. Mowzer deliver
his speech, and upon an invitation from the Committee the City of Cape
Town can do their presentation at Parliament, on a day that will be decided
by the Committee. The Committee will inform the City of Cape Town,
when they will be able to listen to the presentation.
21. ‘‘Water Services Management in the City of Cape Town’’ by
Saleem Mowzer
Trading Services encompasses the directories of Electricity Services, Solid
Waste Management and Water Services, including the sanitation function.
Its vision is to provide quality, affordable, efficient and sustainable services
to all households and consumers in the City of Cape Town.
The city has stark contrasts, but possesses immense development potential.
However, the city severely suffers from the effects of decades of apartheid
policies, planning and service delivery that have created urban slums,
sprawling informal settlements and disparate inequities in service delivery,
particularly among underdeveloped and disadvantaged communities.
In line with Government’s vision to eradicate poverty and underdevelopment,
we have prioritized the need to overcome these contrasts as a central
component of effective leadership and governance in Cape Town and to
place the city on a sustainable growth path.
Over the past few years there has been a fundamental rethink of the way in
which the water services is managed and delivered. This has been aimed at
ensuring greater alignment with national government’s policy and service
delivery agenda for the water sector, including:
_ Meeting the strategic objectives of the recently released Strategic
Framework for Water Services;
_ Enhancing sector regulation, policies, planning, investment and
delivery;
_ Ensuring adequate investment into critical water infrastructure to
support growth and development, including the extension of services
to unserviced informal settlements; and
_ The provision of free basic water and sanitation to assist in poverty
eradication
The City is proactively engaging the Department of Water Affairs and
Forestry at a local level through the regional operations headed by Mr.
Rashid Khan and at a National level through the strategic engagement and
consultation of the Director General, Mr. Mike Muller and Minister
Buyelwa Sonjica.
Internally we have ensured the alignment of water services functions with
the Council’s Indigent Policy, Equitable Services Framework and Integrated
Development Plan. In this respect the tariff is designed to
accommodate the needs of low-income households and poor consumers by
providing the first six kilolitres of water free, per month. This is consistent
with government’s policy on the provision of free basic services.
The remaining tariff structure is broken down as follows. Consumption
between:
_ 6 to kilolitres is charged at R2, 15 per kilolitre;
_ 12 to 20 kilolitres is charged at R4, 30 per kilolitre;
_ 20 to 40 kilolitres is charged at R5, 48 per kilolitre;
_ 40 to 60 kilolitres is charged at R6, 67 per kilolitre; and
_ Consumption above 60 kilolitres is charged at R8, 60 per kilolitre.
The progressive nature of the tariff allows for the needs of the poor to be
met and discourages excessive consumption.
By the end of September, we hope to be in a position to make a final
assessment of dam levels in the Western Cape Water System to inform the
severity of restrictions on domestic water consumption. The City will
embark on a highly visible and intensive public awareness, user education
and media campaign, to support the restrictions.
The development of future water supply options has already commenced
through the construction of the Berg River Dam, which the Committee has
recently visited. The city is also considering various alternative water
resource development and management options, including:
_ The extraction of ground water between rock fissures one kilometer
below the earth’s surface through the Table Mountain Group Aquifer;
_ Feasibility studies into desalination;
_ Feasibility studies into domestic prepaid water meter installations;
_ A comprehensive bulk water supply and infrastructure planning
study;
_ The establishment of a ‘water think tank’ comprising experts in the
water sector and large water users in the industrial, commercial,
institutional, sports, recreation and tourism sectors of the Cape Town;
and
_ Sustained enhancement of the City’s Water Demand Management
Strategy to respond the ever-changing urban landscape.
Further with regards to water demand management, earlier today we visited
one of Cape Town’s world-class installations, the Khayelitsha Pressure
Management Station. This facility represents state of the art technology and
international best practice in water pressure management, not to mention
the fact that is the largest of its kind in the world. Since being
commissioned the project water leakage and the amount of unaccounted for
water passing through the City’s water supply system.
International best practice for the amount of unaccounted for water stands
at approximately 15% and is held by the Yarro Water Utility of Australia.
Through this installation and the maintenance and repair of aged and
damaged water fittings Cape Town’s record for unaccounted water stands at
around 18%, placing us in a favourable position to narrow in on the
international benchmark.
Through this project it is now possible to provide lower water pressures to
the Khayelitsha community thus reducing their monthly water consumption
to levels to which they can afford. These high pressures previously
caused serious damage to the plumbing and reticulation networks in
Khayelitsha resulting in household leakage that accounted for more 80% of
the non-revenue water supplied to the area.
We are striving to eliminate the existing inequities and inequalities in the
delivery of the service, thereby tackling the inequities and inequalities of
the city as a whole. We are beginning to turn the tide on decades of
sustained under-investment in the water network, particularly the systematic
under-investment in un-serviced informal settlements, townships,
disadvantaged and underdeveloped communities.
This is being achieved through the provision of basic water, sanitation and
sewerage services to informal settlements through the Informal Settlements
Upgrading Project. Through the site visit today, you would acquired an
appreciation for some of the interventions we have made on the sanitation
front through grant funding assistance totaling R52 million from DWAF.
In light of the heavy rainfall we received over the past 24 hours, you would
also have been informed through the media and witnessed for yourselves
this morning the problem of flooding faced in informal settlements during
winter months. This, together with the fact that the upgrading of informal
settlements is a moving target due to the constant sprawl of new
settlements, demonstrates the need for a coordinated approach for the
upgrading of informal settlements. For this reason we have established a
dedicated project office that is appropriately staff and resourced.
This project office coordinates with the City’s and the provincial
Government of the Western Cape’s Disaster Management function to
address flooding and appropriate contingency measures for the 171
informal settlements located within the city. Together these settlements
house approximately 520 000 people, many living direct access to safe
water and sanitation services.
During this financial here R8, 48 million has been allocated for community
water and sanitation supply through the Municipal Infrastructure Grant
(MIG) administered by the Provincial Government of theWestern Cape, to
implement the Informal Settlements Upgrading Plan. In terms of this
business plan we are awaiting a response on an additional MIG funding
application of R16 million.
The Water Services capital budget for all projects in this financial year
totals R257 880 million — a significant increase from previous financial
years. This figures is expected to increase to more than R330 million in the
2005/6 financial year and to more than R358 million in the 2006/7 financial
year. In terms of water and sewage infrastructure investment, R137,3
million will be invested during this financial with an additional R11,3
million for further water supply and sewer extensions yet to be approved
through MIG allocations.
In previous financial years the investment into critical water infrastructure
and network to support city growth and development, was badly lacking
and resulted in sever asset stripping and disinvestments of the network.
These factors have resulted in the ageing of the water network without
appropriate replacement and upgrading of infrastructure.
In many cases infrastructure component have approached the end of their
lifespan, resulting in the high risk of non-compliance with regulated health
and environment standards and frequent breakdowns in service delivery.
From the facts and figures, it is clear that over the past 12 months our focus
has been to turnaround this high-risk situation through appropriate risk
management measures and to move in line with the levels of reinvestment
into the water network desired by national government and provide access
to water and sanitation to many more residents in terms of government’s
water ladder to achieve universal access by 2008.
Another budget feature is that, compared to previous years when the budget
was skewed in favour of affluent suburbs and well development areas of the
city, this year’s budget is geared toward reducing poverty, inequality, lack
of access and poor service delivery in disadvantage communities. It is also
aimed at injecting investment into the water network to support city growth
and development for economic purposes.
Despite all of this progress and the good work that has commenced, I will
be the first to admit that much, much more remains to be done to undo the
legacy we inherited in 1994 and which continues to be burdensome on
thousand of our people. This is a legacy that we are committed to unwind.
22. Recommendations made by the Committee
The purpose of this section of the report is to provide the recommendations
of the Committee on the findings of the study tour. To make better sense of
this section, it is necessary to consider the whole report.
22.1. Conservation forestry management:
DWAF officials consider as one of its major concerns, that forest’s, are
invaded by communities.With invasion trees are felled to build houses, for
firewood and agricultural purposes.
The Committee therefore wishes to informDWAF that globally, people live
in or at the edge of forests. They are some of the least privileged groups in
our global community. They depend on the forests for many important
products and environmental services. These services not only meet their
economic needs for food and shelter but also form an integral part of their
culture and spiritual traditions.
The Committee therefore recommends thatDWAF enhance participation in
decision-making and benefit sharing. Technically sound initiatives usually
fail to arrest deforestation because they are conceived without the true
participation of all interest groups (i.e. communities, and other land users).
DWAF must therefore take into account the special interest groups from
within the forest sector and the other sectors that share, and at times
compete for the same land base.
Of particular importance is deciding on a just formula for sharing in the
benefits and responsibilities that derive from using forest resources
sustainably as an alternative to deforestation.
22.2. Planning and Management of the Southern Cape Forests
Transformation: The Committee expressed concern about gender representativeness
by DWAF with their participation in the study tour. The
officials of DWAF were all male, and this led the Committee to question
DWAF about gender representation in the department. This can be noted in
the report. The Committee therefore recommends that DWAF pursue this
issue vigorously, and identify the gaps that are in place in terms of gender.
More women and especially Black South Africans should be the focus of
employment by DWAF.
Black Empowerment: What emerged from the presentations is that the
transfer of forests was only taking place amongst sectors and not
considering the poorest of the poor. The Committee therefore recommends
that the poorest of the poor be empowered when transfers of forests takes
place.
Vacant posts: The Committee recommends that the 83 vacant posts should
be filled by women as the existing staff component are imbalanced, with
very little women and only 11 Black staff members.
22.3. Field Visit: Diepwalle Forestry Estate
Creche: The Committee acknowledges the efforts that DWAF has put into
securing a crèche for the children of Diepwalle. However, the Committee
recommends that DWAF, works in collaboration with the Department of
Education to secure transport for the children. The Committee also notes
that there is a need for social development amongst the communities of
Diepwalle, in terms of social grants for the children, child support grants,
etc. This is a means to alleviate poverty amongst the community. DWAF
must ensure that the people of Diepwalle receives education around these
issues.
22.4. Khoisan Community Project
The Committee recommends that whenever DWAF presents projects to a
Committee that when visiting the project sites, communities involved in the
projects should be present. The Committee is concerned that that none of
the community was present, as it would have been more practical for the
Committee to see the community busy with the projects in the way DWAF
officials had informed the Committee during their presentation. The
Committee also requested to see the financial records kept in terms of the
profits and distribution of finances to the various beneficiaries as reported
by DWAF officials. DWAF officials had informed the Committee that
records of finances are not kept at the office of the co-ordinator, but is kept
at the office of the Trust. The Committee therefore recommends, that
DWAF officials should ensure that copies of reports of such nature be kept
at the office closer to the people for public scrutiny. This would be in
accordance with the concept of open and transparent governance. The
requests that a copy of the financial report be passed on to the Committee.
22.5. Water Supply Calitzdorp
The Committee was concerned when DWAF mentioned that the farmers
supplied the land to build farm schools and this creates problems when
DWAF wants to provide infrastructure for the basic water service. The
Committee informed DWAF that this provides room for debate. If the
farmers provided land to build the schools then the land that the school is
built on does not belong to the State but to the farmer. In essence there is
then no security over the land and neither over the school. The farmer can
then turn around and reclaim his land.
The Committee therefore recommends that DWAF find clarity on this
issue, because it can create problems in the long run. DWAF should
approach the Government about the issue, and the Government should
consider what is good for the children and the people. The Government can
negotiate with the farmer and seek the possibility to expropriate the land.
DWAF must also consider asking the Department of Education for
assistance, together they can look into the matter to see what the long-term
solution could be.
22.6. Community Project, Gamka Wes, Calitzdorp
The Committee reminded DWAF officials that a groundbreaking policy of
the provision of free basic water and sanitation has been implemented and
this means that everybody in South Africa has the right to a basic amount of
water and a basic amount of sanitation that is affordable. These basic rights
should also apply to farm workers, bearing in mind that they have to pay for
services where these are provided over and above a basic service.
In addition, farmers are employers and are responsible for the housing and
related services of their employees living on the farms. Farmers are
therefore intermediaries and are responsible for the provision of (at least)
basic services to farm workers living on their farms. DWAF should
therefore reconsider the position that the people on the farms are living in,
reconsider the responsibilities that the farmers have towards the people
living on their farms, see what is set out in the law, and see that the law is
enforced.
22.7. The bucket system in Zoar
The Committee felt that not enough was being done by DWAF and the
Municipality responsible, to assist the people to acquire the basic povision
of water and sanitation.
The Committee felt that DWAF officials were not responding to the issues
at Zoar positively and the Committee was not happy with the way the
problems of the people to access proper sanitation and water were
addressed. The Committee also felt that it would seem that municipalities
are always not having enough money to be able to provide the people with
the basic services that are constituted in the Constitution of the country.
However, the Committee feels that the municipalities are either not
planning there budget accordingly and therefore under spends and the left
over money goes as rollovers.
The Committee recommends that all Water Service Associations do the
Section 78 assessments in order to determine gaps and problems they are
facing to deliver services to the people. This would therefore allow the
council to make informed decisions whether to outsource these functions or
to do them in-house.
22.8. Overberg Water Board: Bucket system in Genadendal
Firstly, the Committee is concerned when Overberg states that they want to
borrow money again for the benefit of Genadendal. Who will have to pay
off this debt. Wouldn’t it be the People of Genadendal. The Committee is
concerned that the poor must always be the people who have to suffer.
The Committee recommends that Overberg investigate the condition of the
bucket system in the whole of its region as the Committee is of the opinion
that Overberg should be well informed about these circumstances.
Overberg also needs to determine what is the backlog in terms of theWater
Service Associations and what has been done in terms of service delivery.
Overberg should relook their Water Services Development Plan, because
through these plans Overberg can be informed as to what has been done in
terms of numbers of provision of services and what is going to be done
about it. Water Services Associations can come to the Water Service
Providers and together they can make informed decisions as to what is
going to be done, whether they are able to provide services to the people or
should they consider bringing in contractors to do the work.
22.9. Khayelitsha, Water and sanitation
The Committee acknowledges the plight of the City of Cape Town to
reduce the high rate of water leakages in the area. However the Committee
is concerned that so many people have not been provided with the basic
infrastructure for water and sanitation. The Committee is also concerned
that people are sharing these very same facilities. The Committee therefore
recommends that the City of Cape Town works towards reducing the
numbers of people that are not yet provided with the basic infrastructure for
water and sanitation and also the numbers of people sharing these facilities
should be reduced. Once people have to share facilities such as water and
sanitation, it becomes problematic and will remain a problem.
It will also be to the advantage of both the people and the City of Cape
Town, if water meters are installed at all households using water. In this
way people are able to monitor their water usage and the City of Cape Town
can monitor this as well. This also assists people in understanding the
importance of sustainable usage of water, as they will have to pay for the
services that are provided to them. The Committee therefore recommends
that the City of Cape Town speed up the process.
The Committee remains concerned that children have to cross the
Lansdowne Road to collect water from the other site. Children and even
adults are killed and remain prone to accidents. The Committee finds that
this has to be dealt with in all urgency by the City of Cape Town. The
Committee therefore recommends that the City of Cape Town either
accelerates the establishment of the new land in Mfuleni, or the problem
with land ownership between the City of Cape Town and private owners
should be solved in all urgency.
The Committee also feels that the cleaning of the buckets that is still in use
by the people should not be done twice every second week. This to the
Committee is problematic, because not only is one household using these
facilities, but in some instances more than one household uses these
facilities. The Committee is also concerned that over weekends these
buckets could create problems, because people use this facilities and the
Committee is sure that these buckets are not collected over weekends. The
Committee therefore recommends that the buckets are collected and
cleaned more than twice a week, and especially on Fridays, as this would in
some way help over the weekends.
The Committee also proposes that the City of Cape Town eradicates the use
of the bucket system as soon as possible. This bucket system takes away the
dignity of the people, and people are prone to illnesses and diseases.
22.10. Khayelitsha, site visit, VIP sanitation project
The Committee was not at all impressed with the VIP toilets throughout the
tour, as this was not far different from the bucket system. The Committee
feels that this type of toilet is not suitable for the people, especially disabled
people, the aged, and the sick. For example, a disabled person using a wheel
chair would find it difficult reaching the toilet, more so when having to use
the toilet.
The Committee also felt that people of Khayelitsha are not properly
informed when these toilets are constructed, hence the confusion around
the toilets which are used as pilot projects. The Committee was also not
impressed with the solid waste that was lying on the pavements of the site,
which the Committee visited and felt that this reflection shows that other
sites could be having the same conditions and this is a reflection that people
are not receiving proper services from the City of Cape Town.
The Committee therefore, after observation, feels that people are living on
land that is not suitable for living. This is reflected in the flooding that is
taking place in the informal settlements. These people need to be resettled
on land that is made suitable for living conditions. Although the Committee
was informed that in some cases people are reluctant to move, land needs
to be identified so that these people can live in better conditions.
The Committee therefore recommends that a land audit be undertaken, and
suitable land be identified, proper houses with the proper infrastructure for
water and sanitation be implemented on these lands, so that these people
could live in better conditions. The focus should therefore be on housing
delivery. Informal settlements are not the answer, and while informal
settlements exist, these problems will exist.
The Committee also recommends that the people should be better informed
about the use of the water and sanitation services that are being
implemented in the area. If people are well informed, this would lessen the
confusion that the Committee observed, is taking place amongst the people.
The Committee also recommends that the City of Cape Town, improve on
solid waste removal from the sites, as waste that lies around exposes people
to various diseases. Children play in the waste that lie around and become
seriously ill. Even animals dig in the waste, and carry around diseases,
which is easily spread amongst communities. As the Committee was
informed by the community, waste are not regularly removed and this
needs to change.
23. The Way Forward
In the report, the Committee has identified issues that should be acted on by
different role players. The major tasks identified are for DWAF to attend to.
The Portfolio Committee recognises, of course, that DWAF has a wide
range of responsibilities, and limitations of funds, resources and staff. The
Portfolio Committee is not suggesting that all the many tasks identified in
this report should be attended to immediately. However, over time, with
due recognition of the department’s constraints, the Committee believes
that action should be taken on these issues. The Committee intends to
discuss with the department what is practically possible, and will over time,
monitor developments in this regard.
Of course, it is recognised that DWAF on its own cannot address the many
issues raised in this report. Other departments, community organisations,
the private sector and other stakeholders have a crucial role to play as well.
So too do Parliament and the Legislatures, and in particular, our Portfolio
Committee.
The report should be published in the ATC (Announcements, Tablings and
Committee Reports) of the National Assembly.
The report should be debated and adopted in the House early in the next
quarter of Parliament.
Copies of the report should be sent to DWAF and the Committee should
ensure that all those who interacted in the study tour get a copy of the
report.
Obviously what and how much can be done to take forward the issues
raised depends on a wide range of factors. Among these, obviously, are our
legislative and other Parliamentary responsibilities, constituency work,
political party deployments, technical and other resources, funding, and the
co-operation of a wide range of stakeholders.
24. Note of Appreciation
DWAF were extremely co-operative and received us very warmly. The
Committee extends sincere appreciation to them. The George Municipality,
Overberg Water Board, Arabella Golf Estate management, Stellenbosch
Municipality, the TCTA and the City of Cape Town, your reception and
co-operation is highly appreciated.
The organisational details were dealt with by our committee secretary, Ms.
Shereen Cassiem, and her assistant Ms. Olivia Siebritz, to them the
Committee expresses their gratitude. Other organisational arrangements
were dealt with by the outstanding Mr. Tony Brutus from DWAF and to
him, the Committee expresses their gratitude. The Committee also thank
the Researcher who accompanied them on the study tour, Mr. Glen Corker
for the background reports he did which were helpful in drafting this final
report.
Report to be considered.