DRAFT COMMITTEE REPORT
AREAS |
TARGETED |
ACHIEVED |
Santombe |
450 |
None |
Extension 7 |
341 |
None |
Extension 8 |
500 |
None |
Silvercity |
941 |
None |
4.3 Recommendations
(a) We recommend that province should look at projects as housing unit seem not to adhere to norms and standards.
(b) Clarity needs to be given as there is no clear hosing suot centre. Only storage is in place.
(c) The community seemed to be in a state of despair as many houses are incomplete. Municipality as developer must take charge of projects.
(d) The project needs a Project Manager that is stationed in Umzimvubu.
O5 August 2003
4.4 Imbizo/ public Hearing
Mayor Munyu chaired the meeting
Proceedings
The funding of projects that were already approved and funds had been transferred to the municipality's account are a problem to take off in Umzimvubu Municipality. The land claim process has delayed the housing delivery in almost all the projects in Umzimvubu. Some of the land belongs to residence, the others to Inkosi and the land claim office in Bisho is dragging to respond. Public servants bought land from the poor for business and that has became a habit. The community raised a concern about the closing down of offices in Kokstad and they requests that staff members from Umzimvubu Municipality be allocated in those offices because of their experience in housing issues. People needed houses in their sites and not to be moved to town to get houses.
4.5 Recommendations
The officials from the Department of Housing and Councillors need to meet and strategize the funding issue.
The issue of land invasion by public servants is crime and it needs to be addressed.
People should have houses in their sites as this is cited in the Communal
Land Bill that people have the right to have houses in their sites.
An improved communication system between municipality and the province is needed.
Project manager to be stationed at the district municipalities’ office.
4.6 Rural Housing
This project was approved at Mphemba ward 11 with 1000 subsidies. The Department of Housing, Local Government and Traditional Leaders are to see to it that the project resumes immediately. Other villages have submitted a list of potential beneficiaries. The project is not yet of the ground.
4.7 Recommendation
The department and municipality must account why the project is not off the ground if 1 000 subsidies have been approved.
5. Buffalo City Municipality
5.1 Duncan Village Hostel B
Duncan Village Hostel B was built in 1960. It is owned by the East London City Council. It was originally a single person hostel and accommodated 752 units. It used to be well managed and rentals were charged and paid for by the residents. The buildings were destroyed by fire during unrest in 1985 and many residence refrained from paying rentals and the building standard deteriorated. Various attempts were made to upgrade the hostel between 1991 and 1994, and progress was only made in 1995 when hostel a re-development program was successfully implemented.
5.1.1 Consultation Process
The planning and construction of the B hostel project was a fully consultative process where all role-players made valuable contributions. Hostel residents were workshopped on the formation of housing association. It was later decided that the B hostel should function as a municipal rental stock and the housing association be considered at a later stage.
5.1.2 Funding
An amount of R8 million was received from various sources such as Amatola District Council, Duncan Village Presidential Project, PHDB and the East London TLC. An amount of R10 000 was also received from charity in Netherlands, and
the hostel was upgraded up to 302 family units and 96 single.
5.1.3 Challenges
There is an illegal occupation of units, people who have absconded allocated people into their units. This made it difficult for Buffalo City Municipality to allocate people who were on the waiting list for the accommodation. An informal settlement has mushroomed in the vicinity of Hostel B . There is an illegal connection of electricity. Houses are leaking during rainy days. The houses do not have steps. There are no lentels on doors and windows and the walls are cracking.
5.1.4 Recommendation
For a way forward, all relevant stakeholders need to be brought on board to solve this dilemma.
5.2 Haven Hills South Housing Development- Own Haven Housing Association
The Haven Hills project was developed by the Van der Leij Habitat Foundation. It was identified by Buffalo City municipality as a Pilot Village to demonstrate an integrated and sustainable urban living environment with a range of higher-density housing options as an alternative to the traditional low-density urban sprawl.
The project has approved 556 units, including 132 project-linked to low cost units. It has 354 rentals apartment and 70 credit-link plot-and-plan dwellings. The project allows for the demonstration of different types of houses and ownership options while providing a balance between affordability, sustainability and quality. The first project of Own Haven Housing Association, namely the construction of 318 two-and three-storey walk up units as the rental component of Haven Hills South, commenced in September 2002. It was awarded tender to the amount of R28 million to Grinaker-LTA, a national construction company. Own Haven Housing Association were to own and manage these rental units to ensure their
sustainability.
The development of Haven Hills South has progressed well, with the first tenants of the rental units taking occupation on 15 March 2003. It is anticipated that all the units will be completed and occupied by mid-August 2003. There is a prepaid water and electricity system.
5.3 AMALINDA CO-OPERATIVE SETTLEMENT PROJECT
This development consists of 196 services sites and houses within 8 housing Corporatives. The project is being implemented via the PHP with Buffalo City Municipality as Support Organizer.
The key role player of the project is the East London Housing and Management Co-operative (ELHMC), which is a local organization. The ELHMC is supported by Afesis Corplan, a local NGO promoting co-orperatives through Swedish Funding.
The project utilizes institutional subsidy of R20 300-00 per beneficiary plus a 15% variants. Individual beneficiaries also contribute approximately R2500-00 each which is jointly saved through the East London Credit and Savings co-operative.
The properties will be communally owned by the members (beneficiaries) of the 8 co-operatives. The internal services within the co-operatives will also be owned and maintained by the co-operatives. After 4 years members will then have an option of individual ownership.
The total project budget is approximately R4,6 million and the project is expected to be completed in February 2004. The typical house size is 45m2 with concrete tile roof. The main challenge experienced in this project is insufficient capacity of emerging contractors.
5.4 CHRIS HANI VILLAGE: MDANTSANE
The project is in the first phase of development at the Mdantsane-Bufferstip, which consists of approximately 2000 informal houses on the fringe of Mdantsane. The Chris Hani Project entails the development of 302 services sites and houses via the People Housing Processes. Buffalo City Municipality (BCM) is the Support Organizer of this Community Development.
A partnership agreement exists between BCM and the Chris Hani Community Development Trust, which is the beneficiary representation body. The project budget is around R7.2 million and houses vary from 40 to 51 m2 in size. The service installation stage has been completed and houses are expected to be completed by September 2003. The contractors were made of local builders and emerging contractors.
5.4.1 Challenges
Material price escalation versus the project implemantation period. There was a communication breakdown which led to community conflicts. There is an insufficient capacity of key role players at Buffalo City Municipality , Chris Hani Community Development Trust and appointed project co-ordinator. There were no lentels on the windows and doors and this resulted in cracks.
5.4.2 Recommendation
The province must ensure the adherence to norms and standards. Any housing defect is an attack on housing policy which stresses the importance of quality housing units.
5.5 BERLIN - LINGELITSHA
Berlin consisted of conventional housing project of 411 houses. Housing construction started in February 2002 and was completed in May 2003. Buffalo City Municipality was the developer of this project. Houses are 40m2 in size, and they were built on R16 000 subsidy band. Estimated project amounted to R6 500 000.
5.5.1 Challenges
Five of the beneficiaries could not be found for occupation of their houses. Properties have already been registered in their names. Houses are not partitioned.
5.5.2 Recommendation
If these beneficiaries are not found, houses should be given to other beneficiaries after thorough investigation and public engagement.
5.6 KING WILLIAMS TOWN HOUSING ASSOCIATION
It was awarded two projects by the Department of Housing the first being for 420, and the second for 2047 subsidies. The first project 420 subsidies allowed for the development of established vacant serviced to be developed which had been blocked for various reason including banks"red lining" and finance.
The second project 2047 subsidies allowed for more affordable units. Each unit has a maximum of 2 bedrooms, bathroom, kitchenette and lounge. Specifications were reduced to exclude plastered walls and internal painting. The basic rentals of the units range from at R360 to R450 per month, excluding insurances and municipal charges.
5.6.1 The 42 houses need to be unblocked.
The MEC should follow up this matter as a matter of emergency.
5.6.2 Home ownership
King William's Town Housing Association pursued the rent-to-own options which allowed tenants to purchase their units over a twelve- year term. It provided a full service in terms of the Social Housing concept by facilitating true Home Ownership. It developed a beneficiary equity which is not only facilitated by rental schemes.
5.6.3 Challenges
The escalation of costs of the house in the second project started by eliminating salary of R1 500 per month and later pushed the entry level up to above R 2000 per month.
5.6.4 Recommendations
Meeting with companies that supply our building material remain acrocal way in which the price of building material cold be addressed. Especially when that increase in linked to increase in subsidy.
5.7 SWEETWATERS PHASE 3
Phases 1 and 2 were completed, with 1600 units.
5.7.1 Phase 3-550 units.
This is a green fields for 620 subsides at which 550 units will be developed. The contract for the provision of a full level of services was awarded in June 2003 and is due for completion by January 2004. The project will be converted to the Peoples Housing Process for the construction of the top structures.
House construction is expected to commence early in 2004 and is to be completed by the end of 2004. The current approved budget of R16 000 with 15% top-up is expected to increase to the new subsidy value of R23 100.00 giving a total budget of R 14 740 000.00.
5.7.2 Recommendations
(1) The province or the municipality must clarify as to who the authentic contractors of this project are.
(2) There is a need to explain what the RHP process mea. There is a lot of confusion about this province.
6. Meeting with the MEC Gugile Nkwinti -Buffalo City Offices- 07 August 2003
The MEC admitted that they are underspending and according to their calculations, they were to spend 6 Billion a day as they did in May 2003. They spent R20 Million in July 2003 and later the amount dropped gradually. The MEC and the Mayor are going to meet and discuss this matter.
With regard to the support centres, the MEC said that there are number of centres to monitor, to keep records and to administer projects. There was no capacity or quality control as they have employed only one civil engineer in each region, and this was not enough.
The civil engeneer has been a conceptual problem as there was no civil engeneer in the Eastern side of the Eastern Cape. The Department of Housing, in consultation with Dymler Chrysler is offering bursaries for student to study municipal studies and engineering and they gave grants to Rhodes University. A turn-around strategy was agreed upon as a way forward but it seemed not to be working. A workshop will be conducted to address this.
The energy efficiency is not common it was once introduced in a pilot project but it is no longer in use.
Regarding women constructors, there is one in Queenstown and she was given 20% share on tender. Project managers were employed to monitor and advise in projects and they visit municipalities weekly. Traditional leaders are participating in municipal activities and campaigns. The MEC said municipalities should budget for traditional leaders subsistence and transport allowances (S&T)
The Chairperson raised the issue of Kokstad staff, who were sent back to Bisho because their offices in Kokstad were closing down. The chairperson said the community requested that those staff members could help in the municipal offices as they had experience in housing issues. The MEC said the municipality would have to apply for staff from the Kokstad offices.
Incomplete projects will be looked at as a matter of urgency, and there are funds to finish them especially the one in uMdantsane. The MEC also said that people from rural areas have no houses,he also mentioned that he phoned for certain project that was delayed, and plans were approved. Suppliers delivered the material, the problem was with ward committees who were not doing their work.
7. Imbizo Public Hearing/meeting
The MEC welcomed everyone present and informed the community that they must speak out about everything relating to houses, they must complain or praise the Department of Housing.
7.1 Deliberations
The issue of slow pace on housing delivery was raised, infrastructure in Ward 41 Mdantsane area. Houses in Hani Park were poorly built and they do not look like they are going last even ten years. Doorframes are falling apart.
There are people who are still waiting for houses since 1982. Disabled people were not receiving houses suitable for their condition. Their houses were not spacious enough and the roads were uneven for wheel chairs.
People who were moved to Senari Park raised their complaint about the area that there was no community hall, roads or an entertainment centre for their children. The question of people sharing in uMdantsane was a problem, and there is nothing being done about it. Residents were frustrated, especially those who have been saving for three years and already bought and owned land, about the waiting period for receiving government subsidy to build houses. The Nkonkobe Builders Association also had a problem of tenders that were given to big companies.
7.2 Responses
The MEC said there are many problems that hinder the progress of development. Ward Committees were affected. People sharing in uMdantsane will be considered. He further said that people will be moved to Postam where there were houses to be built, sewerage pipes will be extended to Postam. All municipalities were requested to submit a list of people with disabilities and the funds that have been approved so that they could be accommodated. There were other 300 rural areas that joined Buffalo City Municipality who will also receive all the necessary services.
Buffalo City is busy with the housing policy, and is hoping to complete it in September 2003. The issue of infrastructure, the elderly and the victims of HIV/Aids are also being considered. On the completion of the housing policy, the Department of Housing will advise on the way forward. In rural areas, Buffalo City will provide VIP toilets instead of normal toilets.
The Provincial Department of Housing said that Peoples Housing Process needs to be given priority on the delivery of houses although there is a huge backlog i.e. nationally and provincially. The MEC and the Department of Housing are aware of Nkonkobe Builders Association's concerns and this matter will be dealt with.
7.3 Recommendations
(1) Department must make a follow-up in the following projects that are not completed:
(a) Umzimkhulu Town Ext. 6
(b) Tyoksville Project only 100 completed out of 700.
(c) King Williams Town Housing Associations 420 houses of first project need to be unblocked.
(d) Projects have not yet been built - Santombe 450, Extension 7,- 341 and Extension 8 - 500.
(2) Many of the projects visited showed the non-adherence to norms and standards. The poor quality of housing units undermines the government's ability to deliver adequate houses.
The Committee urges the department to look at this matter as a matter of urgency. When NHBRC is engaged in this process, houses that we are referring to are:
(i) Umzimkhulu xt. 6, where doors and windows are built without lentels. Doors and walls are cracking.
(ii) Quality of houses in Tyoksville is very poor. Similarly to Chris Hani Village in Umdantsane and Hani Park.
(3) There is a need for clarity given of what is meat by a PHP process.
(4) The Committee has also noted in many projects there was no clear defined developer - projects being managed by an absentee Project Manager - this has to be resolved as a matter of urgency by he MEC, e.g. Tyoksville project Manager who is based in East London. Manager has to be located at the District Municipality.
(5) The Committee has noted with concern that subsidy given for house to e built at extension 6, deposited R800.00 - what happened to the rest of the subsidy - Committee wants an investigation to this matter.
(6) Housing Support Centres and Capacity Building programme for the community has to be set up by the department as a matter of emergency.
(7) Issues of land continue to hinder the housing delivery process. Communal Land Bill is seen as the only solution.