PRESENTATION TO THE PARLIAMENTARY
PORTFOLIO COMMITTEE ON HOME AFFAIRS
By
I Lambinon
Acting Director-General
18 March 2003

  1. INTRODUCTION:

It is a privilege to meet with this distinguished Committee once more and to report to you on pertinent matters that relate to policy initiatives and operational progress within the Department of Home Affairs. The guidance provided by the Portfolio Committee in the determination of the future direction of the Department, as well as the practical support demonstrated in resolving pressing issues such as inadequate funding, is highly appreciated.

Notable progress has been made with regard to some important matters reported to this Committee at the previous meeting. A number of key issues remain and require priority attention. Both are discussed in this document.

The Portfolio Committee has addressed some specific questions to the Department on which it requires elucidation. These are dealt with in this presentation and can be further clarified, if so required, during the discussions.

Of particular note, especially in the light of the forthcoming Home Affairs Budget Vote, are financial expenditure and allocation trends in the Department. This, consequently, forms the main thrust of the discussion. Allocations and expenditure per programme, as well as per standard items are reflected upon and the actual budgetary increase analysed.

The Department has for some years steadily been working on the introduction of a strategic management approach. Apart from thereby complying with the strategic planning requirements of the Public Finance Management Act, 1999 (Act 1 of 1999) as amended, as well as the Integrated Strategic Framework of Cabinet, decision-making and action within all departmental cadres have progressively been mobilised and directed towards the achievement of identified change objectives and the realisation of the Home Affairs vision of rendering a world class service. The third annual departmental Strategic Plan has recently been finalised and will shortly be formally submitted to Parliament. We have thought it appropriate to attach the final draft of this Plan hereto for the information of the Portfolio Committee. In fact, many of the issues raised by the Committee have been incorporated in the Plan and are therefore already receiving systematic attention.

 

2. DETAILS ON PARTICULAR MATTERS LISTED BY THE PORTFOLIO COMMITTEE:

    1. ACCESSIBILITY TO HOME AFFAIRS’ SERVICES IN RURAL AREAS:

The Department is aware of the persistent inadequate reach of its services in deeply rural and marginalised urban communities. As a consequence, the matter received in depth attention during the last two annual strategic planning workshops of the Department. It is addressed in the departmental change plan under the focus area on service delivery processes (Change Objective 5). Various ways and means were considered to provide office infrastructure and services to those communities.

Of particular note is the way in which services to such disadvantaged communities are being addressed in the investigation on the determination of the new structure and personnel establishment of the Department that is presently being undertaken and will be finalised by 30 June 2003. The scientific formula designed to determine the location and staffing of offices, in fact, contains a built-in bias towards these areas, compensating in particular for distance in sparsely populated areas and taking into account, as well, the availability/absence of public transport. Areas with a population of less than 5 000 will be serviced by a fleet of mobile units that will be beefed-up significantly and these units will also be deployed in accordance with special requests, e.g. presentations from old age homes, schools, etc. In areas where the population exceeds 5 000, temporary service points will be opened (servicing those communities according to need on predetermined days). Where the population exceeds 40 000, permanent service points, and where it exceeds 80 000, district offices will be established. Evenly important is the new personnel dispensation for these eventualities, which for the first time provides for a dedicated personnel contingent attached to mobile units and service points. Up to now the staff of already understaffed district offices had to perform services in mobile units and service points, an arrangement that seriously impeded service delivery at district offices. Consequently, this development will have a tremendous overall positive effect on rural operations of the Department.

The Department does not allocate a specific budget for setting up mobile units. The following expenditure was, however, incurred at the Regions during the 2002/03 financial year, regarding transport costs, which included the mobile units.

REGION

TRAVELLING COSTS

SUBSISTENCE COSTS

TOTAL

R’000

R’000

R’000

Western Cape

439

79

Northern Cape

209

206

415

Eastern Cape

895

440

1 335

Gauteng West

917

23

940

Gauteng East

647

32

679

North West

1 345

232

1 577

Northern Province

959

360

1 319

Mpumalanga

646

90

736

Kwazulu-Natal

1 093

176

1 269

Free State

343

61

404

TOTAL

In practical terms the sharing of mobile services between various stakeholder departments has evolved in certain locations. This is a worthy development that needs to be expanded and formalised. The involvement of Home Affairs in the Eastern Cape Interim Management Team (IMT) established by Cabinet will, amongst other service delivery improvement efforts, also pertinently focus on this aspect.

The Minister of Home Affairs has on various occasions stated his strategic vision of the devolution of the delivery interface of Civic Services to third tier government. A thorough investigation into this matter has been initiated and a first report has been produced. Various modalities of the departmental devolution initiative are currently the subject of further discussion and negotiation at the intergovernmental level. It is hoped that substantial progress will be made hereupon during 2003. Meanwhile, numerous interim arrangements between the Department and various municipalities, traditional leaders and NGO’s on the sharing of facilities, and co-operative service delivery have substantially progressed. Moreover, the Minister of Home Affairs has instructed that the Department provides services at all Multi-Purpose Community Centres. We are currently active at 34 MPCCs. Also, the Department has increasingly, and in line with Government policy, embarked on a process of utilising the services of volunteers to augment its in-house personnel capacities. Marked success has already been obtained in this field. Unfortunately the container office concept that was reported on to the Committee during the briefing of 4 June 2002 did not materialise. Apart from problems that occurred regarding the tender procedures followed, further investigations revealed that more cost-effective alternative options for rural infrastructure provision might be available.

The computerisation of Home Affairs offices, especially in remote rural areas, is a cornerstone of quality service rendering. During the current financial year 30 such rural offices were identified for computerisation. Of these 22 have already been fully computerised whilst the remaining eight are awaiting Telkom line upgrading in order to be linked. The cost hereof was R 4, 405 million. For the 2003/2004 financial year the computerisation of a further 30 offices at the cost of R 5 million is envisaged.

The IT backbone of Home Affairs is situated in Civitas Building, Pretoria, and constitutes the national and international communication platform of the Department. The ageing thereof has inhibited envisaged electronic transactions and thus necessitated upgrading to accommodate the expanded network of computerised offices. This was done at a cost of
R 5 million during the 2002/2003 financial year, whilst a further
R 1,4 million has been budgeted for this purpose during the 2003/2004 year. Largely due to the sensitive nature of our information and transactions, a project was also initiated at an initial cost of R 1,5 million to secure the entire Department against unauthorised access. This included technical risk assessment analyses, the formulation of sound security policies, as well as the purchase of security software and hardware. It is envisaged that a further R 10 million will be spent on this project during the ensuing financial year on: (1) the securing of five regions against unauthorised access; and (2) the securing of the Head Office environment against unauthorised access.

Obviously the ever-expanding business requirements of the Department dictate that our electronic systems and infrastructure needs be strategically aligned with such developments. We have embarked on a thorough analysis of our electronic infrastructure upgrade requirements.

2.2. STAFF SHORTAGES:


Currently the Department has 1 915 vacant posts on its personnel establishment, including 358 vacancies at the Government Printing Works. The situation is aggravated by the fact that this establishment was determined as far back as 1995 and does therefore not take into account the spiralling need for departmental services since then. The current investigation into the establishment of the Department, referred to above, is directed at addressing this imbalance in a dynamic way. As an interim measure, Cabinet has approved the filling of 349 critical posts during the financial year 2003/2004. These posts will be filled as soon as possible after 1 April 2003. It is envisaged to fill the other critical vacant posts as soon as possible after the finalisation of the restructuring process of the Public Service, depending on the availability of funds. An amount of R20,933 million is included in the 2003/04 financial year, for the filling of these critical vacant posts. However, as indicated in the Budget Planning Submission (MTEF) 2003/04 – 2005/06, an additional amount of R67,908 was requested for the filling of 704 vacant posts during 2003/04. Capacity building among existing staff in order to enhance effectiveness and efficiency has been incorporated in an imaginative departmental human resources development strategy.

2.3 ELECTRONIC DOCUMENT MANAGEMENT SYSTEM (EDMS)

BACKGROUND

The objective of the EDMS is to implement an effective, real time, online solution that will cater for automated document management processes from capture to business transaction solution resulting in the overall improvement of business process efficiency. The system will make all Home Affairs records and archiving information, within the scope of the contract, available for access to any authorised individual at any workstation in the entire system.

The contract for the supply and implementation of Phase 1 of the EDMS was awarded to Choice Technologies in October 2001.


Phase 1 of the EDMS consists of the following:

PROGRESS

All hardware and system software related to the EDMS have been installed. A replica of the core system was installed in the New Cooperation Building for disaster recovery purposes.

A GB White Laser Communication infrastructure has been installed between Civitas and New Cooperation buildings. This allows for the transfer and replication of data between the two head office sites.

The new GIGABYTE Local Area Network backbone to cater for the data transfer volumes required by the EDMS was installed.

53 million images (approximately 19 000 rolls) previously stored on microfilm were successfully converted and electronically stored on the EDMS. During the conversion process problems were experienced with 1709 rolls (due to poor quality films or problems that have been experienced with the cameras during the microfilming process).

A Bureau Scanning service was acquired for the scanning and indexing of the original documents related to the faulty microfilm records into the EDMS (and estimated number of 6.4 million pages).

Training on EDMS comprises of End-User and Technical training. The bigger percentage (95%) of all training (related to 250 users) has been successfully completed.

The implementation of the EDMS required several structural changes to the current environment. A training facility was established in the Basement 2 area of Civitas. Structural changes that are still outstanding include the establishment of Paper Preparation, Scanning, Quality Assurance and Indexing facilities in the Civitas and New Cooperation buildings.

The developing of the Bespoke Application covering all business related areas in Births, Marriages and Deaths sections has been completed. User acceptance testing (UAT) has been completed on 98% of the system.

An electronic interface to the NPR has been developed to allow for the creation of additional indexes for the images in the EDMS archive.

The EDMS fax server was installed to enable faxes related to BMD to enter the EDMS electronically.

OUTSTANDING ITEMS

Most of the work in regard to Phase 1 has been completed and at this stage it is only the following elements that still have to be finalised before the system can fully go live:

Due to unforeseen complications and delays in regard to the above it has unfortunately not been possible to go live on 1 September 2002 as originally planned. The projected commissioning date is now set for 30 May 2003.

The total costs for Phase 1 will be ± R70 million.

NOTABLE SYSTEM ACHIEVEMENTS

The microfilming process was stopped in order to make the required structural changes to the environment. This process was replaced by a Temporary Scanning facility based on the developed EDMS solution and therefore constitutes partial implementation of phase 1. Documentation for 336 880 have been prepared for scanning and 138 000 cases have been scanned.

WAY FORWARD


Implementation of Phase 3:

It is envisaged to integrate all the Home Affairs systems, i.e. National Population Register, Movement Control System, Passport System and HANIS to facilitate access to the different systems and thereby to improve functionality and efficiency.

EDMS BUDGET

2003/2004 : R52 500 000

2004/2005 : R78 000 000

2005/2006 : R82 680 000

2.4 REWRITE OF THE NATIONAL POPULATION REGISTER

The existing population register is more than 30 years old and needs to be rewritten. Not only does it largely use fairly antiquated programming languages and system approaches, but also, over the years, numerous programme patches were used to provide for changes in requirements. This has led to a situation where it is difficult to make further changes as it is often impossible to fully predict what all the results of a change will be.

The Department is presently in the process of appointing a project team to deal with the rewrite and with a view to inviting tenders for the rewrite as soon as possible.

The budgeted amounts for the rewrite are:

2003/2004 : R32 000 000

2004/2005 : R40 000 000

2005/2006 : R42 400 000

    1. THE HANIS PROJECT:

BACKGROUND

HANIS is basically a computer system intended to replace the old manual identification/verification processes at Home Affairs. By automating the processes, more accuracy is achieved at faster rates, thus improving service delivery while ensuring secure registration abilities by, among others, issuing a unique identity number. A machine-readable identity card, which would include a photograph and a thumbprint of the applicant, were envisaged as the key features of the HANIS card. The system has an interface with the Population Register System.

Above is the original definition of the system. The scope, as shall be seen, and as could be expected, has changed dramatically, with Change Management introducing a few vital things.

The system comprises the following major components:

These are the HANIS business processes

These are the HANIS subsystems:

PROGRESS

The following table shows some significant events in the history of the HANIS project, as well as the corresponding dates.

17 January 1996

Cabinet approved the HANIS project.

6 December 1996

A comprehensive tender was published was published.

21 January 1999

Cabinet suggested an investigation into the change of the mode of the HANIS card from ordinary two-dimensional barcode card to smart card.

12 February 1999

After a protracted evaluation process the tender was awarded.

8 November 1999

Eventually, the HANIS Supply Contract between the Department of Home Affairs and the Marpless Communications Technologies (Pty) Ltd. Consortium was signed on. Through change Management (CR #1) the ID Card component was excluded from the contract.

31 January 2000

The Honourable Minister launched the HANIS Project.

18 February 2002

The HANIS Basic System Commissioning (BSC) milestone was reached.

27 August 2002

The HANIS Basic System Operational (BSO) milestone was achieved.

 

NOTABLE SYSTEM ACHIEVEMENTS TO DATE

CURRENT SYSTEM DRAWBACKS

WAY FORWARD

The following are the short-term implementation strategies:

These are the long-term implementation strategies:

The PPP procurement model for implementing the card component would entail:

    1. THE MOVEMENT CONTROL SYSTEM:
    1. An amount of R146 420 000 was allocated for the rewrite of the MCS.
    2. After allocation and before tenders could be called for, it transpired that the current network used by the Department would not be able to support the envisaged system. This implied that the network used by the Department would have to be updated before tenders could be called for.
    3. The Department’s IT Directorate is currently addressing the network issue and it is envisaged that the tenders for the rewrite of the system will be called for in approximately four months’ time.
    4. The funds allocated for the rewrite include amounts for equipment that has to be purchased or upgraded. Some of the equipment can be purchased at this stage, but most can only be purchased once the tenders have been awarded. Consequently the Department has started purchasing the first mentioned equipment and R4 200 000 has been spent during the 2002/2003 year. The amount of R1 970 000 was utilised for the implementation of the Computerised Visa system at 12 Missions, and R 2 230 000 for the upgrading of equipment at various border posts. The rest will be rolled over and spent once the tenders have been awarded.
    5. Despite the setback it is expected that the full rewrite project will have been finalised within the three-year programme.
    6. The yearly allocations were:
    7. 2002/3 R45m

      2003/4 R35,5m

      2004/5 R32m

      2005/6 R33,920m

    8. The visa system will be finalised during the new financial year and the system will be implemented at 10 new missions at a total cost of R4 450 000.
    9. Due to the fact that the roll out of the rewrite of the Movement Control System could not take place during 2002/2003, Phase 1 and 2 will be addressed during 2003/2004.These phases entail the following:
      • Implement a centrally driven and managed system which will function on a real-time online basis between ports of entry, SA missions abroad, regional and district offices and a central database and developing an effective Management Information System
      • Integration of the Refugee and Deportation systems
      1. It is foreseen that the following expenditure will be undertaken:
        • Hardware - R 28 million
        • MCS Software - R 7.5 million
        • Workflow Software - R 2.5 million
        • Training - R 1.8 million
        • System integration - R 3.5 million
        • Professional services - R 9 million
        • Core infrastructure upgrades - R 6 million
        • Change Management - R 3 million
        • Hardware and software support - R 10 million
        1. PORTS OF ENTRY

      The Committee is aware of the dire need for the refurbishment that exists at the country’s land border posts to meet the increasing demand to clear travellers and goods efficiently and to ensure an orderly flow of persons through the border posts, which is conducive to the control over the cross border movement of persons and goods. This need, as was reported before, has been met to a certain extent by means of the R101million approved by the Cabinet in 1997 in terms of the erstwhile National Crime Prevention Strategy (NCPS). However, divided over three years between 53 ports of entry, the improvements, although marked, could not address all the needs. The majority of these funds have now been expended, enabling us to take stock of the situation. The Department, in collaboration with our border control sister departments, has therefore made a further detailed assessment of funds needed in this regard. This need will be factored into our respective budgetary processes and will also be jointly promoted with Treasury.

      As indicated above, the Department’s staff establishment is currently being reviewed, but the reality is that this has not been done since 1995, and therefore staff shortages also prevail at ports of entry. We were, however, able to address critical areas by supplementing staff figures at the Lebombo and Beit Bridge border posts, as well as the Johannesburg International Airport. This has enabled us to extend the hours of operation at Beit Bridge to a 24-hour service for passenger vehicles, and at the Johannesburg International Airport, to successfully deal with events such as the OAU and NAM (Non Aligned Movement) Summits, the World Conference against Racism, the World Summit on Sustainable Development and the Cricket World Cup. We are currently considering the extension of the hours of operation at the Lebombo border post in collaboration with our Mozambican counterparts. At the Maseru Bridge border post a separate pedestrian facility is now in operation full time, resulting in the easing of congestion within the passenger vehicle section of the port of entry. The complete redesign of the Golela border post will now commence after a R7million contribution by the Department to the interdepartmental process.

      The events of 11 September 2001 resulted in an upswing in overseas tourism figures, as South Africa is now perceived as a relatively safe holiday destination. According to our un-audited figures for 2003, the number of persons cleared on entry and departure at our ports of entry has grown from 26,1million per annum in 2002 to 34,9million in 2003, and we were able, with our limited resources, to successfully deal with this increase of over 33%.

      Initiatives driven by other departments such as the Departments of Environmental Affairs and Tourism (DEAT) and Trade and Industry (DTI) often further impact on the Department of Home Affairs, our Department being a service delivery department in essence. For example, the creation of the Great Limpopo Transfrontier Park necessitates the creation of a new port of entry with Mozambique whilst the creation of the Trans-Kalahari corridor necessitates the complete rebuilding of the Skilpadshek border post, as well as the phasing in of longer hours of operation. The creation of a new seaport at Couga and the relocation of the Durban International Airport to La Mercy in 2006 are other challenges that affect us and for which we are preparing ourselves to meet.

      3. ACTUAL BUDGET (2002/03) IN COMPARISON WITH BUDGET PLANS (2003/04)

      3.1

      BUDGET ALLOCATION: VOTE 4

      FINAL BUDGET ALLOCATION 2002/03

      BUDGET ALLOCATION 2003/04

      INCREASE

      INCREASE

      R'000

      R'000

      R'000

      %

      1 486 752

      1 971 053

      484 301

      32.57%

      NOTES:

      Although the increase of R484,301 million (32,6%) on the previous financial year's budget seems to be substantially, the following should be borne in mind:

      If the funding for items such as Projects, Transfer payments and other earmarked amounts are deducted from both years’ allocations as illustrated hereunder, the increase in the Department's budget will only be 11.1%.

      2002/03

      2003/04

      R'000

      R'000

      ALLOCATION

      1 486 752

      1 971 053

      LESS:

       

      HANIS PROJECT

      357 937

      258 061

      HANIS SMART CARD

      -

      15 000

      ELECTRONIC DOCUMENT MANAGEMENT SYSTEM

      35 000

      52 500

      REWRITE OF POPULATION REGISTER

      -

      32 000

      ID CAMPAIGN

      -

      15 000

      MOVEMENT CONTROL SYSTEM

      45 000

      35 500

      FILM AND PUBLICATION BOARD

      4 000

      5 200

      GOVERNMENT PRINTING WORKS

      1

      25 000

      INDEPENDENT ELECTORAL COMMISSION

      210 756

      640 960

      PUBLIC WORKS

      50 450

      21 279

      TOTAL

      783 608

      870 553

       

      3.2 ACTUAL EXPENDITURE: 2002/03

      PROGRAMME

      ADJUSTED ESTIMATE ALLOCATION

      EXPENDITURE AS AT 28/02/2003

      PROJECTION FOR THE REMAINDER OF THE FINANCIAL YEAR

      TOTAL ESTIMATED

      PROJECTED SAVING

      NOTES

       

      R’000

      R’000

      R’000

      R’000

      R’000

       

      1. Administration

      207 590

      194 562

      12 028

      206 590

      1 000

      1

      2. Services to Citizens

      729 667

      648 045

      57 622

      705 667

      24 000

      2

      3. Migration

      281 016

      182 711

      55 305

      238 016

      43 000

      3

      4. Auxiliary and associated services

      268 479

      220 224

      28 255

      248 479

      20 000

      4

      TOTAL

       
        1. R1,0 million - Implementation of Basic Accounting System (BAS) will not realise as anticipated. National Treasury will be requested to roll-over the amount to the 2003/004 financial year.
        2. R17,0 million - Projected delivery date for the image capture machines required by the Hanis Project is not within the 2002/03 financial year and National Treasury will be requested to roll-over the amount to the 2003/04 financial year. Furthermore, an amount of R7,0 million for the Electronic Document Management System will also not be utilised and will be requested to be roll-over to the 2003/04 financial year.
        3. R43,0 million - Upgrading of Movement Control System. Due to the delay in the approval of the delegations of the Immigration Act, 2002, the project has been delayed and only part of the equipment will be purchased during the 2002/2003 financial year. National Treasury will be requested to roll-over the amount to the 2003/2004 financial year.
        4. R20,0 million - Although the funds are committed for infrastructure and maintenance needs, the services will not be rendered and payments made by the end of the 2002/2003 financial year. National Treasury will be requested to roll-over the amount to the 2003/2004 financial year.

      3.3 ESTIMATE OF NATIONAL EXPENDITURE ALLOCATION: 2003/04

      PROGRAMME / REGION

       

      PERSONNEL EXPENDITURE

      ADMINISTRATIVE EXPENDITURE

      INVENTORIES

      EQUIPMENT

      LAND AND BUILDING

      PROFESSIONAL AND SPECIAL SERVICES

      TRANSFER PAYMENTS

      TOTAL

       
         

      R’000

      R’000

      R’000

      R’000

      R’000

      R’000

      R’000

      R’000

       

      1. Administration

       

      62 961

      36 308

      5 618

      9 470

       

      55 856

       

      170 213

       

      2. Services to Citizens

       

      84 614

      18 082

      36 287

      207 193

       

      146 058

       

      492 234

       

      3. Migration

       

      52 293

      6 216

      3 324

      2 325

       

      71 529

      1

      135 688

       

      4. Auxiliary and associated services

             

      3 505

      21 279

       

      671 160

      695 944

       

      5. Region

       

      414 120

      50 953

      6 197

      1 781

       

      3 923

       

      476 974

       

      Western Cape

       

      32 181

      2 741

      727

      167

       

      275

       

      36 091

       

      Northern Cape

       

      12 870

      1 829

      221

      118

       

      69

       

      15 107

       

      Eastern Cape

       

      54 713

      6 421

      1 093

      260

       

      520

       

      63 007

       

      Gauteng West

       

      44 706

      17 890

      618

      187

       

      631

       

      64 032

       

      Gauteng East

       

      55 703

      3 645

      922

      112

       

      879

       

      61 261

       

      North West

       

      48 907

      3 983

      488

      237

       

      503

       

      54 118

       

      Limpopo

       

      50 471

      4 228

      522

      129

       

      113

       

      55 463

       

      Mpumalanga

       

      39 431

      2 877

      673

      245

       

      365

       

      43 591

       

      Kwazulu/Natal

       

      45 402

      4 134

      464

      134

       

      369

       

      50 503

       

      Free State

       

      29 736

      3 205

      469

      192

       

      199

       

      33 801

       
                           

      TOTAL

       

      613 988

      111 559

      51 426

      224 274

      21 279

      277 366

      671 161

      1 971 053

       

      3.4 MAJOR SPENDING AREAS MTEF PERIOD: 2003/04 – 2005/06

       

      Actual Expenditure (Total Project to date)

      2003/04

      2004/05

      2005/06

      NOTES

      PROJECTS

      R’000

      R’000

      R’000

      R’000

       

      Hanis Project

      918 724

      258 061

      224 816

      238 305

      Allocation (2002/03) - R357,937 million

      Hanis Smart Card

      15 000

      200 000

      200 00

      To facilitate a complete feasibility study and options analysis for the Smart Card project.

      Electronic Document Management System (EDMS)

      50 838

      52 500

      78 000

      82 680

      Allocation (2002/03) - R35,0 million

      Population Register

      32 000

      40 000

      42 400

      Allocation (2002/03) – Nil

      Movement Control System (MCS)

      4 200

      35 500

      32 000

      33 920

      Allocation (2002/03) - R45,0 million

      OTHER

               

      Personnel Expenditure

       

      613 988

      678 571

      726 289

      An amount of R20,933 million is included in the 2003/04 for the filling of 226 crucial vacant posts. However, as indicated in the Budget Planning Submission (MTEF) 2003/04 – 2005/06, an additional amount of R67,908 was requested for the filling of 704 vacant posts during 2003/04.

      ID Campaign

       

      15 000

      To make provision for the ID Campaign before the national elections in 2004.

      Film and Publication Board

       

      5 200

      6 680

      7 081

      Allocation (2002/03) - R4,0 million

      Government Printing Works

       

      25 000

      Restructuring of the Government Printing Works.

      Independent Electoral Commission (IEC)

       

      640 960

      478 029

      664 258

      Allocation (2002/03) - R210,756 million

      Infrastructure projects

       

      21 279

      58 489

      60 825

      An amount of R7,0 million for renovations of border posts and regional offices. Furthermore an amount of R12,354 million for upgrading and renovation projects and R1,925 million for maintenance on infrastructure. The projected saving of R20,0 million in 2002/03 for infrastructure upgrading will be requested for roll-over.